Presentation to the House Appropriations Committee Mike Maples - PowerPoint PPT Presentation

Presentation to the House Appropriations Committee Mike Maples Deputy Executive Commissioner, State Operated Facilities Jordan Dixon Deputy Executive Commissioner, Office of Transformation & Innovation March 21, 2018 Expanding


  1. Presentation to the House Appropriations Committee Mike Maples Deputy Executive Commissioner, State Operated Facilities Jordan Dixon Deputy Executive Commissioner, Office of Transformation & Innovation March 21, 2018

  2. Expanding Inpatient Psychiatric Infrastructure A Comprehensive Plan for State-funded Inpatient Mental Health Services Submitted August 2017  Defines strategy & goals  Outlines process improvements  Emphasizes collaboration  Proposes three-phased construction plan 2

  3. 2018-19 Projects Summary Plan Highlights Appropriation $300 million Construction l Amount Approved $47.7 million Significant Repair Capacity to be Added 338 beds Maximum Security Unit 130 beds (MSU) Capacity to be Added Rusk State Hospital: The Idealized Model 3

  4. 2018-19 Projects & Timeline Facility and Current Project Funding Estimated Project Timeline Austin State Hospital Pre-planning* Q2 FY 2019 Planning* Q4 FY 2019 Replacement | $15.5 million Construction Q4 FY 2023 Kerrville State Hospital Pre-planning Completed in 2017 Planning* Q3 FY 2019 70-bed MSU | $1.5 million Construction Q2 FY 2021 Rusk State Hospital Pre-planning Completed in 2017 Planning* Q2 FY 2020 100-bed MSU | $4.5 million Construction Q3 FY 2022 Rusk State Hospital Pre-planning Completed in 2017 Planning* Q2 FY 2020 100-bed non-MSU | $4.5 million Construction Q2 FY 2024 San Antonio State Hospital Pre-planning Completed in 2017 Planning Q2 FY 2019 40-bed non-MSU | $0.5 million Construction Q3 FY 2020 San Antonio State Hospital Pre-planning* Q2 FY 2019 Planning* Q4 FY 2019 Replacement | $14.5 million Construction Q2 FY 2023 UTHealth-Houston Pre-planning* Included in Planning Planning* Q4 FY 2019 228-bed Acute/Sub-acute Hospital | $6 million Construction Q2 FY 2022 4 *Indicates prior LBB funds dispersal

  5. Other Improvement Efforts • Higher education partnerships: Construction projects Telemedicine expansion Hospital affiliation • Stakeholder coordination: Advisory committees Project steering committees Employee town hall meetings Extensive collaboration with elected officials • Hospital system improvements: Governing body Review of existing resources Deferred maintenance projects 5

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.