Presentation to residents in Wardington
5th December 2018
Presentation to residents in Wardington 5 th December 2018 Nisha - - PowerPoint PPT Presentation
Presentation to residents in Wardington 5 th December 2018 Nisha Mejer Community Engagement Manager Area Central Community Engagement 2018 Visited local authorities, HS2 Liaison Group meetings. Attendance / updates at Parish Council
5th December 2018
Area Central
Warwickshire.
workshop –
HS2 has partnered with Commonplace to provide a locally focused website. This is currently being updated with content but you can still visit the site / sign up: https://hs2innorthants.commonplace.is/about The HS2 corporate website - https://www.hs2.org.uk is in testing and we are keen for feedback. There is a link on the site to give comments. Alternatively you can email comments to online@hs2.org.uk
Community and Environment Fund (CEF) & Business and Local Economy Fund (BLEF)
The administration of these funds is managed on behalf of HS2 by the charity
contact Groundwork by telephone 0121 237 5880 or by email at HS2funds@groundwork.org.uk
line of route.
Ground investigations – engagement around this. Bore hole surveys in areas. Drop ins – surgery in Culworth Further Parish Councils
HS2 helpdesk
High Speed Two (HS2) Ltd Two Snowhill Snow Hill Queensway Birmingham B4 6GA
Email: HS2enquiries@hs2.org.uk Freephone: 08081 434 434 Minicom: 08081 456 472
HS2 Engagement Team Nisha Mejer – Nisha.Mejer@hs2.org.uk
Northamptonshire and South Warwickshire
Experienced multi-national joint venture
Bretagne-Pays de la Loire high speed line in France
Hinkley Point, Crossrail, etc.
1MC07-CEK-SE-PRE-C003-000001
Scheme Design Target Price Delivery Proposals Stakeholder Dialogue Supply Chain Engagement
1MC07-CEK-SE-PRE-C003-000001
Now
Early Next Year
Beyond
1MC07-CEK-SE-PRE-C003-000001
Edgcote Viaduct
1MC07-CEK-SE-PRE-C003-000001
("LGVs") in each direction, per day.
progress and outcomes of work carried out to seek to mitigate construction related traffic effects.
Warden as soon as reasonably practicable, said haul road to remain in use for the duration
1MC07-CEK-SE-PRE-C003-000001
Community Liaison Officer Fusion JV HS2 Enabling Works
Advance Works Notices (AWNs) must be delivered to residents before any work can start Residents are given 14 days’ notice before work commences. Community Event Invitations – local meetings and programme of local surgeries
Works commencement / completion dates? What Traffic Management arrangements will be implemented during the project? Any full road closures? if so, when will this be and for how long? What will the diversion route be? We know there will be some lane closures, will the lane closures be daytime off peak only, or will the TM be up for the duration of the works? Will the TM for Wardington and Chipping Warden be in place at the same time? Will any parking bays be taken out of use? Where will the welfare unit be located?
Wardington Improvements Phased works
Wardington Traffic Management
Wardington Traffic Management
Wardington Traffic Management