presentation to nersa energy efficiency and demand side
play

PRESENTATION TO NERSA ENERGY EFFICIENCY AND DEMAND- SIDE RULES ( - PowerPoint PPT Presentation

Energy Efficiency and Demand-Side (EEDSM) Rules including the Standard Offer Program (SOP) PRESENTATION TO NERSA ENERGY EFFICIENCY AND DEMAND- SIDE RULES ( Rules ) INCLUDING THE STANDARD OFFER PROGRAM ( SOP ) 5 August 2010


  1. Energy Efficiency and Demand-Side (EEDSM) Rules including the Standard Offer Program (SOP) PRESENTATION TO NERSA ENERGY EFFICIENCY AND DEMAND- SIDE RULES ( � Rules � ) INCLUDING THE STANDARD OFFER PROGRAM ( � SOP � ) 5 August 2010

  2. Contents � Introduction � The Case for Energy Efficiency � Key Objectives of an Effective EEDSM Programme � Key Requirements for an Effective EEDSM Programme � Summary of Eskom Comments � Balancing Short-and Long � Term initiatives � Security of Supply � Cost-Effectiveness � Simplicity � Use of MYPD 2 Funding � Eskom Recommendations � Conclusion 2

  3. Introduction � This presentation will highlight a few key issues regarding the Energy Efficiency and Demand-Side (EEDSM) Rules including the Standard Offer Program (SOP) and must be considered together with Eskom � s written submission dated 20 July 2010. � Accept that some of the issues may relate to the policy that informs the Rules � There is clearly alignment on the crucial importance of energy efficiency � The SOP is also a useful tool in achieving this objective � Where we have different views, these relate in essence to the best way that the objective can be achieved.

  4. The Case for Energy Efficiency Security of Supply � Best form of � renewable energy � Challenges � Elimination of wasteful usage � Quicker and cheaper than new power generation � Positive impact on price path Common Solution � Allows time take informed decisions on capacity expansion � Unlocks economic efficiencies � Cost savings for consumers � Contribution to carbon reduction, climate Financial Environmental change and protection of the environment Challenges Challenges 4

  5. Key Objectives of an Effective EEDSM Programme � To ensure Security of Supply by: Solving Eskom and the country � s immediate supply / demand - challenge until new base-load stations start coming on line from 2012/2013. - Balancing Supply and Demand in the medium - term. � To achieve energy efficiency in the most cost-effective manner

  6. Key Requirements for an Effective EEDSM Programme � It must provide a holistic and integrated solution that takes into account : � Short � and long � term interventions � A combination of initiatives: � Use of a price signal � An optimal portfolio of EEDSM technologies with an even spread over markets and the technologies in order to maximise the savings yield. � Maximises the available EEDSM funding by leveraging customer self-funded EEDSM . � Appropriate incentives � Sets an appropriate balance between high yield energy efficiency solutions and the social objective of the Solar Water Heating programme. � Finally, it must be simple, cost effective and efficient

  7. Summary of Eskom � Summary of Comments

  8. Balancing Short-and Long term Initiatives Given the capacity situation in the country, EEDSM initiatives must be - supported with shorter-term initiatives that can yield maximum savings in the shortest possible time Elements of the SOP will take time to implement and could delay the - achievement of immediate savings Certain interventions may require implementation over a longer period - to ensure a sustainable outcome in the next 3 to 5 years

  9. Security of Supply The proposed initiatives do not rely on an optimal portfolio of - initiatives The focus is mainly on the Solar Water Heating, public and new - buildings and the Energy Conservation Scheme for large customers. This represents only a portion of the total market that can be targeted for savings. A large portion of the market , specifically in the industrial, mining - and commercial sectors (for customers consuming <100GWh � s pa) is not sufficiently covered . There is a strong focus on Solar Water Heating. Excessive funding of - SWH could lead to a limited exploitation of high yield savings technologies .

  10. Cost Effectiveness � The published rates for the Standard Offer is mainly based on the avoided cost of generation , however it should be based on the least amount required to incentivise self funding by consumers. � The proposed Standard Offer rates for Solar Water Heating does not constitute a viable model . � Utilising the MYPD2 funds to incentivise the Energy Conservation Scheme (ECS) will create an unquantifiable financial liability in a sector that could self-fund energy efficiency. � It is not appropriate that customers be paid for savings below the baseline of the ECS � not an integrated solution � The costs are therefore increased without the benefit that it will necessarily result in more savings

  11. Simplicity � Governance and Administration The Standard Offer requires Project Developers to fund initiatives up- - front. There are probably only two to three local ESCO � s that will be able to raise significant amounts of funding. Should Eskom participate as a Project Developer, this will create - additional funding requirements in an already cash constrained environment . It will take some time to create the necessary administrative - capacity to implement the Standard Offer, creating possible risk to roll-out of EEDSM.

  12. Use of MYPD 2 Funding A large portion of the MYPD 2 funds have been contractually - committed to identified projects. It would therefore not be feasible to set these funds aside for the - proposed SOP. With regard to funds not contractually committed, the reservation of - funds for the purposes of the SOP will result in the suspension of the additional initiatives Aside from the concerns raised by Eskom about the efficacy of the - SOP, the proposed � reallocation � of the MYPD 2 funds is beyond the authority of the Rules and Policy.

  13. Process � NERSA has powers to make rules � Not clear if NERSA views these Rules as giving effect to specific Policy or an exercise of its general powers � In either case the Rules and/or Policy is ultra vires in terms of the proposed � re-allocation � of MYPD 2 funds

  14. Eskom Recommendations � Given the implication of EEDSM on Security of Supply, specifically in the next two to three years, the current governance and administrative mechanisms to roll-out EEDSM should be maintained. � Eskom was allocated R5.4b in terms of the MYPD2 approval and these funds should be used for the projects identified � Eskom proposes a segmentation of the SWH market, with appropriate solutions, funding models and governance models per market segment. � An external market and financial review of our SWH segmentation approach will be obtained to test robustness and implementation ability. � The Standard Offer model could be applied to a section of the SWH market: - Focus should be on the ±554,000 geyser replacement in the Med / Low LSM market. - Government should obtain funding from sources other than the MYPD2. � Cost estimates of the NERSA proposed standard offer model seems understated - this needs to be confirmed prior to finalising an implementation strategy.

  15. Eskom Recommendations (continued) � The balance of the SWH target needs to be met through: - development and implementation of a solar water heating replacement programme in the high-end residential market (including replacement of failed geysers). - Eskom continuing the mass roll-out programme, using the R300m fiscal funding. and a re-allocation of R434m from the MYPD2 DSM funding giving a total target of 256 000 houses in this market � The Standard Offer could be a tool for other DSM products for Eskom to realise the IRP targets.

  16. Conclusion � The implementation of the Rules and SOP as proposed would not achieve the stated objectives of security of supply and energy efficiency in the most effective manner � The roll out of the current initiatives could be delayed resulting in increased risk in the next year and beyond (in fact, a slow down in the market has been noticed due to the uncertainty regarding the funding regime)

  17. Additional Slides

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend