presentation overview
play

Presentation overview Eskom project objectives Eskom key - PowerPoint PPT Presentation

Tender: Fleet Standardisation of Turbine Vibration Diagnostic System, Networks and Interfaces. (Technical overview) Presented by: Corrie Visagie Date:20 July 2020 Presentation overview Eskom project objectives Eskom key criteria


  1. Tender: Fleet Standardisation of Turbine Vibration Diagnostic System, Networks and Interfaces. (Technical overview) Presented by: Corrie Visagie Date:20 July 2020

  2. Presentation overview • Eskom project objectives • Eskom key criteria • Overview of scope • Overview of required solution • Interface requirements • Free issued equipment • Functional requirements • Documentation, training, standards, decommissioning and testing • Option • Technical Tender returnables 20/07/2020 2

  3. Project Objective • Eskom has identified the need for an integrated turbine vibration diagnostic system to support the running fleet in plant performance evaluation, risk management and outage planning. • The solution provided must provide a flexible approach to allow interfaces to the current turbine vibration monitoring equipment. • The solution needs to support the station condition monitoring concept which provide for a centralised station condition monitoring network at each station. • The turbine diagnostic system will provide access to the turbine vibration diagnostic information at station level as well as enterprise level. • The solution for the fleet turbine vibration diagnostic system must provide a long term cost effective solution which are maintainable and supported for seven years. • The solution needs to replace the current fleet obsolete turbine vibration diagnostic system. 20/07/2020 3

  4. Key Criteria • The solution provided must address the project objectives and conform to the requirements of the Works Information. • The main Tenderer must provide confirmation of the proposed turbine vibration diagnostic system’s OEM support and approval from the OEM on proposed turbine vibration diagnostic system solution. • The turbine vibration diagnostic solution need to be designed, supplied, installed and commissioned by an experienced contractor. • The Tenderer is responsible for the conceptual design, final design, installation, commissioning and optimisation of the turbine vibration diagnostic system at all indicated power stations as well as enterprise solution. 20/07/2020 4

  5. Overview of Scope Vibration Monitoring system Number of units Arnot SKF M800A / Vibrometer VM600 6 Camden Bently Nevada 3500 8 Duvha Bently Nevada 3300/3500 3/3 Kendal Bently Nevada 3500 6 Kriel Vibrometer VM600 6 Kusile Bently Nevada 3500 6 Lethabo Bently Nevada 3500/AEG System 3/3 Majuba Bently Nevada 3500 6 Matimba Epro MS6000 6 Matla Bently Nevada 3500 6 Medupi Bently Nevada 3500 6 Tutuka Alstom Type 7 / Bently Nevada 3500 4 / 2 Koeberg Bently Nevada 3500 2 20/07/2020 5

  6. Overview of scope continue 20/07/2020 6

  7. Overview of required solution Information to be accessible at Diagnostic system to be Eskom enterprise level via virtualized within Eskom existing Eskom assets. free issued servers. Unitised interface solution to extract information from Interface solution to export existing vibration diagnostic information to station monitoring systems condition monitoring network. 20/07/2020 7

  8. Detail breakdown of required solution Megawatt Park LIMS IGCC ERP RDS WEI 1. Supply, of user EH EH software licenses and installation of RMDC ROTEK Balance Plant Early RMDC Gx required Oper Of Performance Warning Config Alarm EH Data Collector W/Station RDS Turbine OCM Plant OCM OCM OCM TELECOMS software. 2. Interfacing with 20MB WAN Link NEOTEL RMDC LAN ROTEK LAN RMDC, MWP Witbank and RTSS. Generation Sites IT Station 1 Station x OT and DMZ network Firewall HA Pair acts as single device configuration same as Boiler 1. Supply, setting up OCM Station1 Firewall inside Firewall inside and commissioning DMZ Office DMZ DMZ of diagnostic building OT Server termination EH Data Generator Turbine room switches in software in VM ware Collector OCM OCM data centre 1. Interfacing environment. gateway 2. Assist with network OT 1Gigabit 1Gigabit 1Gigabit Fibre Fibre Fibre hardware with configuration with U6 U5 U4 U3 U2 U1 GHS GHS GHS GHS GHS 12G/8 12G/8 12G/8 12G/8 12G/8 existing vibration networks and racks. Switch Switch Switch Switch Switch 1Gigabit Fibre monitoring racks. 3. Configure OPC Generator SM200 SM200 SM200 SM200 2. Supply and interfaces to plant monitoring 100 Mb 100 Mb 100 Mb SM200 SM200 Fibre Fibre Fibre network PDA200 PDA200 PDA200 PDA200 commissioning of historian. PDA200 PDA200 Turbine Turbine Network 4. Optimise diagnostic 3006T 3006T 3006T 3006T 3006T monitoring Switch Switch Switch Switch Switch network information. to the Generator Connects to Generator 3500 3500 3500 3500 3500 3500 Monitoring network VMS VMS VMS VMS VMS VMS network switch. 5. Assist with firewall Transformer 3006T 3006T 3006T 3006T 3006T 3006T monitoring configuration Switch Switch Switch Switch Switch Switch network STP Patch STP Patch STP Patch STP Patch STP Patch STP Patch Connects to Generator Panel Panel Panel Panel Panel Panel STP cable STP cable STP cable STP cable STP cable Monitoring network STP cable STP cable STP cable STP cable STP cable STP cable STP cable Transformer Transformer Transformer Transformer Transformer Transformer Transformer Transformer Transformer Transformer Transformer Transformer Cage Cage Cage Cage Cage Cage 20/07/2020 8

  9. Interface requirements • Interface between the existing unitised vibration monitoring system and unitised vibration diagnostic network switch. This interface can be hardwired or a communication interface and is referred to as a gateway within the WI. Refer to appendix B1 and B2 of the WI. • Interface between unitised vibration diagnostic network switch and station generator condition monitoring network. The tenderer provide for the required fiber optic cabling as well as extension cards to the condition monitoring unitised network switches. The unitised vibration diagnostic network switched is installed within new individual unitised network cabinets. The Tenderer need to confirm the tenderer’s network requirements to confirm compatibility with existing station condition monitoring network. • Interface between Eskom vibration diagnostic server and Eskom Enterprise Historian. Interface need to be configured utilising OPC protocol. Refer to Appendix C of WI. 20/07/2020 9

  10. Interface requirements continue • The station vibration diagnostic solution will be virtualized within the Eskom provided servers. VM Ware solution is the chose of Eskom. Tenderers must confirm hardware and software requirements to allow virtualization of their product. • Interface via Eskom firewalls to Eskom end users. Eskom will provide configuration of the firewall to allow access through the firewall. Tenderer need to specify specific requirements and cyber security requirements associated with his solution. • Providing enterprise software solution to enable viewing of the software, by Eskom users, anywhere on the Eskom IT network. 20/07/2020 10

  11. Functional requirements Functionality which need to be provided by the overall Signal turbine vibration diagnostic processing Includes specilaised system plots and graphs Analytic System software and Administration displays Setup, recovery and configuration engineering Functions and information processing for specific running status Alarms and Archiving of event information Storage and access to recording historical information 20/07/2020 11

  12. Free issued equipment • VM Ware virtualised server to house the supplied vibration diagnostic software. • Generator condition monitoring network to interface the Turbine network covered in the scope. Note: Tenderer need to clarify hardware, network and software requirements for equipment free issued by Eskom at tender stage. 20/07/2020 12

  13. Documentation, training and standards • Documentation. Documentation needs to be provided as per the attachment VSDD. Note to reduce cost a once of per type documentation approach will be accepted for specific documentation as indicated in the VSDD. • Training Training provides for up front engineering training followed by training for all users, maintenance staff and engineering staff. • Standards List of standards which governs technical as well as safety requirements are included. 20/07/2020 13

  14. Decommissioning and testing • Decommissioning. As part of the scope the Tenderer is required to decommission existing systems after new diagnostic system have been implemented and commissioned. • Tests The Tenderer is required to perform specific upfront tests such as interfaces, diagnostic solution functionality, vibration monitoring data access and virtualization of software. The test will be performed at Eskom sites as well as the Tenderer’s premises. Testing requirements provide for FAT tests, SIT tests and SAT tests. 20/07/2020 14

  15. Options • Service and Maintenance Contract The Tenderer provides a five year service and maintenance support contract as an option for the equipment and systems included in the Works. • Advanced software solution The Tenderer confirms and price additional option which is available to support the functionality and improve the functionality of the vibration diagnostic system which is offered in the main offer 20/07/2020 15

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend