[Presentation ID#] L2 Overview: 402.8 MIP Timing Detector Chris Neu - - PowerPoint PPT Presentation

presentation id l2 overview 402 8 mip timing detector
SMART_READER_LITE
LIVE PREVIEW

[Presentation ID#] L2 Overview: 402.8 MIP Timing Detector Chris Neu - - PowerPoint PPT Presentation

[Presentation ID#] L2 Overview: 402.8 MIP Timing Detector Chris Neu Fermilab Directors Review April 4, 2018 Outline System Requirements Conceptual Design, Maturity Scope/Deliverables In this talk I am describing US contribuJons to


slide-1
SLIDE 1

[Presentation ID#] L2 Overview: 402.8 MIP Timing Detector

Chris Neu Fermilab Director’s Review April 4, 2018

slide-2
SLIDE 2

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 2

§ System Requirements § Conceptual Design, Maturity § Scope/Deliverables § Resource OpJmizaJon § OrganizaJon § Interfaces § Technical Progress to Date § Plan for CD-2/Preliminary Design § Cost § Schedule § Risk § ESH&Q § Breakout Session topics § Summary

Outline

In this talk I am describing US contribuJons to the MTD as a planning package. Hence the MTD porJon of the project will be at a different level

  • f maturity relaJve to the other

subprojects. The specificity of the contents of this plan (WBS, KPPs, BoEs) will increase as the project evolves.

slide-3
SLIDE 3

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 3

§ Chris Neu

§ Associate Professor, University of Virginia (2008-present) § InsJtuJonal experJse on crystal scinJllators for calorimetry,

radiaJon tolerant photodetectors

§ Co-convener of the MTD SimulaJon and Performance group § Member of the MTD Steering Group § Formerly a member of CDF as a graduate student (OSU, 98-03)

working on the XFT track trigger, and as a postdoc (Penn, 03-08) working on the L2 trigger upgrade for Run IIb

§ Physics interests: top-Higgs coupling, top quark measurements,

dark mader

Biographical Sketch

slide-4
SLIDE 4

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 4

CMS HL-LHC Upgrade Overview

New Tracker

  • Rad. tolerant - increased granularity - lighter
  • 40 MHz selecJve readout (strips) for Trigger
  • Extended coverage to η ≃ 3.8

Trigger/HLT/DAQ

  • Track informaJon in trigger at 40 MHz
  • 12.5 µs latency
  • HLT input/output 750/7.5 kHz

Muon systems

  • New DT & CSC FE/BE electronics
  • New staJon to complete CSC at 1.6 <

η < 2.4

  • Extended coverage to η ≃ 3

New Endcap Calorimeters

  • Rad. tolerant - High granularity transverse and

longitudinal

  • 4D shower measurement including precise

Jming capability

Barrel Calorimeter

  • New FE/BE electronics for full granularity

readout at 40 MHz - with improved Jme resoluJon

  • Lower ECAL operaJng temperature (8∘C)

Beam radiaJon and luminosity Common systems and infrastructure MIP Timing Detector

  • Barrel layer: Crystal + SiPM
  • Endcap layer: Low Gain Avalanche Diodes
slide-5
SLIDE 5

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 5

402.8 Requirements: Science Drivers

Charge #1

§ HL-LHC: large increase in beam intensity – and consequent number of simultaneous pp collisions (pileup, PU)

§ Baseline: Peak L = 5.0E34 cm-2s-1 à 140 PU § UlJmate: Peak L = 7.5E34 cm-2s-1 à 200 PU

§ For comparison:

§ LHC: Peak L = 1.5E34 cm-2s-1 à <PU> ≈30

§ UlJmate total integrated luminosity of HL- LHC era dependent on choice of peak running condiJons for luminosity leveling, which is informed by detector performance at high PU § Significant loss in performance at 200 PU due to influence of tracks from un- interesJng PU interacJons on measurements from ~1 interacJon we really care about in a given beam crossing

average average

slide-6
SLIDE 6

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 6

§ Reduced ability to separate PU interacJons from the hard interacJon at 200 PU § Every object vital to the CMS physics program suffers:

§ AddiJonal jets are associated with the hard interacJon, spoiling VBF-jet triggered and

Njet-categorized analyses

§ MET measurement suffers – affecJng resoluJon and tails, harming NP searches § LifeJme-based SVs become muddled with irrelevant tracks § Charged leptons appear less isolated, reducing efficiency for lepton-based

measurements and searches

402.8 Requirements: Science Drivers

Charge #1

slide-7
SLIDE 7

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 7

§ Although the interacJons significantly overlap in space, they are more separable in space+Jme § With sufficient Jme resoluJon, current 3D PV idenJficaJon can be upgraded to a 4D fit, allowing for more effecJve cleaning of charged parJcle tracks from PU interacJons

402.8 Requirements: Science Drivers

Charge #1

nominal σz = 4.5cm nominal σt = 180ps

slide-8
SLIDE 8

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 8

§ The CMS MIP Timing Detector (MTD) is an apparatus that provides Jme-of- arrival informaJon for minimum ionizing parJcles (MIPs) with a resoluJon of beder than 50ps (KPPs: DocDB-XXXX) § The majority of parJcles produced in pp interacJons at the LHC are classified as MIPs

402.8 Requirements: Science Drivers

Charge #1

§ Other subsystems have limited Jming capabiliJes for MIPs – or none at all § Hence this addiJonal precision Jming informaJon can be used to help miJgate the impact of PU, providing improved performance at high PU and extending the CMS physics program in the HL-LHC era More details in Lindsey Gray’s talk in the auernoon Breakout Session

slide-9
SLIDE 9

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 9

Conceptual Design

Charge #1

  • Timing resoluJon of 30ps
  • RadiaJon tolerance to 4/ab
  • Cost effecJve design over large area
  • Manageable data volume and power

Design constraints:

  • Marginal impact on rest of CMS
  • IntegraJon fits within schedule

“BTL” “ETL”

slide-10
SLIDE 10

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 10

§ Granularity choice is a trade-

  • ff:

§ small sensors are less

suscepJble to Jme spread, leakage current, etc

§ small sensors inflate the total

channel count, increasing the data volume

§ Reasonable occupancy: 2-5%

§ operaJng point that avoids

significant impact from deposiJons in subsequent bunch crossings

§ Reasonable data volume:

§ ~4TB/s when read out upon

trigger w/ zero-suppression scheme

Conceptual Design: Granularity

§ ResulJng channel area:

§ BTL: 11 x 11 mm2 § ETL: 1 x 3 mm2 (x3 ganging for |η|<2.1)

Charge #1

slide-11
SLIDE 11

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 11

§ Tracker support tube will support Al+stainless cooling trays on internal rails § Very compact real estate market in this region § Must accommodate acJve and passive elements, cooling tray § FE readout through TOFHiR boards, to Concentrator Card, all rad-tolerant

Conceptual Design: BTL

Charge #1

slide-12
SLIDE 12

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 12

§ Endcap view: not showing all modules § Wedge view only showing one side

Conceptual Design: ETL

Charge #1

slide-13
SLIDE 13

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 13

§ LYSO:Ce Jle glued to a Silicon PhotomulJplier (SiPM)

§ LYSO:Ce:

§ fast and bright

§ SiPM:

§ small acJve area à low noise § small cell pitch à opJmized choice

for PDE, gain, radiaJon tolerance

Conceptual Design: Sensors

§ Silicon low-gain avalanche detector (LGAD)

§ Ultra-fast device, opJmized for

Jming

§ Low gain achieved through

moderately doped p-implant

§ Low gain à shot noise is small,

below the electronic noise

BTL: ETL:

slide-14
SLIDE 14

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 14

Review History

§ MTD Technical Proposal (DocDB: 13511) submided to the LHCC in late November 2017

§ Seeking step 1 approval from LHCC to include MTD in Phase-2 CMS scope and proceed to preparaJon of

TDR

§ Timeline:

§ 4 December 2017: IniJal presentaJon of scope, definiJon, technical details and performance esJmaJons § 27 February 2018: Followup presentaJons addressing quesJons from review panel § 1 March 2018: RecommendaJons received

§ Response from commidee:

§ “The Jming layer design proposed by CMS is reasonable and is expected to fulfill specificaJons of the HL-

LHC running”

§ “There is experienced and enthusiasJc team of experts interested in developing and then construcJng

and operaJng CMS Jming layer”

§ “Based on the above we recommend CMS to proceed to develop Gming layer TDR with submission in

late 2018.”

§ RecommendaJons (abridged):

§ Extensive and large number of radiaJon hardness tests have to be performed on final elements of the

system, including sensors, electronics, power elements

§ Develop design in close cooperaJon with tracker and endcap calorimeter upgrade groups § Define specs for front-end ASICs and verify ASICs performance § Verify Jming signal stability in detecJon electronics of ~10 ps § Develop a full simulaJon of MTD, verify expected performance, further develop physics case of forward

layer

§ Endorsed by CERN Research Board 7 March 2018

Charge #1

slide-15
SLIDE 15

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 15

US Scope and Deliverables

§ The US will contribute to both the BTL and ETL porJons of the project, matching exisJng R&D efforts and experJse § BTL:

§ Lead the Mechanical Engineering for BTL for TST and interface with Tracker

community

§ Contribute to sensor and SiPM R&D, leading up to system specificaJon § Procure, receive and perform QA tesJng on 15% of the sensors and SiPMs

necessary for the full BTL system

§ Procure, receive and perform QA tesJng on 15% of the Concentrator Cards

necessary for the full BTL system

§ Provide two of three global assembly centers for BTL, where 15% of the

total modules for the BTL system will be assembled, undergo QA and delivered to CERN

§ ETL:

§ Lead the design of the FE readout system, including design of the FE ASIC § Contribute to sensor R&D, leading up to system specificaJon § Procure, receive and perform QA tesJng on 15% of the necessary for the

full ETL system

§ Provide two of three global assembly centers for ETL, where 15% of the

total modules for the ETL system will be assembled, undergo QA and delivered to CERN

Charge #1

slide-16
SLIDE 16

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 16

Resource OpMmizaMon

Charge #3

Several US personnel holding key leaderships posiJons in the internaJonal MTD project

MTD organization

Chris Tully

slide-17
SLIDE 17

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 17

Resource OpMmizaMon

Charge #3

Institute Interests (Coarse) Brown ETL sensor R&D UCSB ETL sensors, modules Caltech BTL sensors, modules ETL sensor R&D Fairfield BTL sensor and module R&D FNAL ETL sensor, FE ASIC UIC ETL backend and trigger Iowa BTL sensor and module R&D Kansas ETL FE ASIC, readout, trigger Kansas State BTL readout electronics MIT BTL mechanics, backend and trigger Northeastern BTL sensor R&D Notre Dame BTL sensors, SiPMs, modules R&D and construction Princeton BTL sensor and module R&D, BTL mechanics Virginia BTL sensor module R&D and construction Wisconsin BTL/ETL backend and trigger

US insJtutes are playing a major role on the MTD project.

slide-18
SLIDE 18

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 18

Resource OpMmizaMon: ConstrucMon

Charge #3

Area InsGtuGon ExperGse, infrastructure BTL modules Caltech

Crystal characterizaJon lab, local engineering and technical staff, pool of qualified students

Virginia

Re-use of mu2e cosmic ray teststand, photodetector lab, local engineering and technical staff, pool of qualified students

ETL modules and wedges FNAL

ExisJng faciliJes for silicon detector assembly, local experJse, engineering

UCSB

ExisJng faciliJes for silicon detector assembly, local experJse, engineering

Assembly / ConstrucGon Centers

slide-19
SLIDE 19

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 19

Work Breakdown Structure

The WBS structure reflects the status as a planning package.

§ Natural separaJon of acJviJes according to the physical regions of the detector, BTL and ETL

§ different technical demands due to the relaJve radiaJon environments § independent technologies § decoupled Jmelines

slide-20
SLIDE 20

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 20

§ BTL: Four main areas of contribuJon

§ Tracker Support Tube

§ Mechanical engineering, liaison with Tracker

engineering

§ Sensors

§ Includes both scinJllator and SiPMs

§ Electronics

§ Concentrator Card

§ Modules

§ Assembly and tesJng of BTL modules, which

will contain sensors, SiPMs and Concentrator Cards

Work Breakdown Structure

slide-21
SLIDE 21

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 21

§ ETL: Three main areas of contribuJon

§ Electronics

§ Design of the FE readout ASIC

§ Sensors

§ Development of LGAD sensors

§ Modules

§ Assembly and tesJng of ETL modules, which

will contain LGAD sensors, Read-Out Chips (ROCs), readout aggregator

Work Breakdown Structure

slide-22
SLIDE 22

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 22

Cost Summary

§ We have developed a plan that accomplishes a significant amount of deliverables to the MTD project building on the exisJng strengths of the US insJtutes involved § The contribuJons fit into two eras (R&D and ConstrucJon), which match the

  • verall Jmeline for the internaJonal MTD project

§ Costs are based off esJmates for M&S from previous experience on CMS, and expectaJons for labor from similar projects within CMS and elsewhere § Costs generated from resource loaded schedule, and EsJmate Uncertainty follows project guidelines

Charge #4

slide-23
SLIDE 23

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 23

Cost Summary

CMS-doc-13215

slide-24
SLIDE 24

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 24

Costs at Levels 2 and 3 CMS-doc-13215

slide-25
SLIDE 25

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 25

Costs at Level 4 CMS-doc-13215

slide-26
SLIDE 26

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 26

26

Costs: Barrel Timing Layer CMS-doc-13215

DOE CD-1 DR || Cost, Schedule and Risk Lucas Taylor, 4-6 April 2017

slide-27
SLIDE 27

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 27

27

Costs: Endcap Timing Layer CMS-doc-13215

DOE CD-1 DR || Cost, Schedule and Risk Lucas Taylor, 4-6 April 2017

slide-28
SLIDE 28

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 28

Cost Drivers: Timing Layer

402.8 Timing Layer

slide-29
SLIDE 29

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 29

EsMmate Maturity

(as a fracGon

  • f base cost)

Updated 13 Mar 2018

slide-30
SLIDE 30

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 30

Schedule

FY26 FY25 FY24 FY23 FY22 FY21 FY20 FY19 FY18 FY17

CD4 CD1 LS 2

LHC

TS Physics Physics Physics TS Physics TS Physics LS 3

Sensors Electronics Modules Mech Integrat’n

Performance ValidaJon Pre-prototype Prototype

ProducJon

Performance ValidaJon

ProducJon

Procedure DefiniJons Assembly

BTL: sensors, SiPMs ETL: LGAD BTL: Concentrator Cards BTL: Assembly sites

Engineering TesJng

BTL: TST Charge #2

Analog Prototype

ROC prototype

Pre-producJon

ETL: FE ASIC ETL: Assembly sites

Procedure DefiniJons

ProducJon and QC

IntegraJon

BTL: InserGon into TST

InserJon

ETL: IntegraGon

Mixed Prototype Digital Prototype

ETL: Flex board

Prototype

ETL: Aggregator

Prototype

ETL: ASIC ROC+flex+aggregator

ProducJon

Outer Tracker assembly start BTL done

slide-31
SLIDE 31

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 31

CriMcal Path: BTL

§ Current BTL schedule has a hard deadline of Q2 CY2023

§ Marks beginning of OT assembly project inside TST § Need to have complete inserJon of all BTL trays into TST before

this date

§ Target complete date end Q2 2022 = 9 months of float § But the schedule leading up is well-packed:

§ CC engineering and prototyping in FY 2018,19 allowing for

producJon quanJty evaluaJon in FY 2020

§ Sensor and SiPM R&D in FY 2018,19 allowing for producJon

quanJty evaluaJon in FY 2020

Charge #2

slide-32
SLIDE 32

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 32

CriMcal Path: ETL

§ CriJcal path for ETL is electronics

§ Long lead Jmes for FE ASIC development § MulJple pieces need to come together in parallel (FE ASIC, flex,

aggregator)

§ There are opJons in the schedule of the final mounJng of ETL, providing addiJonal float

§ Surface integraJon: would take place in FY 2022 § Cavern integraJon: would take place in FY 2024

Charge #2

slide-33
SLIDE 33

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 33

Breakout Sessions

§ This auernoon: Technical consideraJons

§ MTD Performance and simulaCon – L. Gray, FNAL § BTL: Technical overview – A. Bornheim, Caltech § Status of the BTL Concentrator Card – Y. Maravin, Kansas State § ETL: Technical overview – A. Apresyan, FNAL § Status of the FE ASIC – G. Deptuch, FNAL

§ Tomorrow: Cost and schedule

§ BTL C&S – CCN § ETL C&S - A. Apresyan, FNAL

slide-34
SLIDE 34

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 34

Summary

§ Messages:

§ Requirements are defined § Conceptual design is sound and meets the requirements,

validated by design reviews

§ Cost, schedule, and risks are understood § ESH&Q elements addressed § Project team is moJvated, qualified, and ready to deliver § We are ready for CD-1 and look forward to your feedback § Thank you for your adenJon

slide-35
SLIDE 35

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 35

Backup

slide-36
SLIDE 36

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 36

Interfaces

§ Content:

§ List most important interfaces from your Interface Control

Document (reference) and describe the boundaries of this WBS L2 system

§ Point out risk assessment of interfaces § Point out connecJon to internaJonal CMS (e.g. what people

do you have in iCMS posiJons for your subproject?)

§ Message:

§ Interfaces idenJfied and being managed § Seamless connecJon to iCMS

Charge #1

slide-37
SLIDE 37

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 37

ESH&Q

§ Content:

§ Strong statement on importance of safety and analyzing risks § Hazards and miJgaJons associated with L2 work scope. Needs

to be consistent with Preliminary Hazard Analysis Document

§ QA/QC acJvity such as:

§ Following the project quality program § Flowdown to vendors/collaborators § Test protocols in development § Needs to be consistent with Quality Assurance Plan

§ Messages:

§ Safety is the highest priority and all CD-1 requirements have

been met.

§ We are working with the project’s ESH&Q coordinator

Charge #4

slide-38
SLIDE 38

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 38

Cost Profile

§ Content:

§ Time phased spending graph, by FY, annotated with notable

events such as major procurements.

§ This will come from common slide deck (you’ll have to

annotate) (both with and without conAngency)

§ Message:

§ We understand our demands for funds.

Charge #4

slide-39
SLIDE 39

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 39

Labor Profile

§ Content:

§ Bar chart of labor usage over Jme, organized by resource type

(engineer, scienJst, technician) and annotated with major acJviJes such design, producJon, commissioning.

§ Include contributed labor § This will come from common slide deck, provided your

contributed labor is in P6!

§ Message:

§ Labor needs can be supported. § We understand the risk of (not ge|ng all of our) contributed

labor

Charge #4

slide-40
SLIDE 40

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 40

Risk Management

§ Content:

§ List of top risks as described in the risk register. § Notable miJgaJon acJons.

§ Message:

§ Risks are understood and are being managed

§ Risk Register will be a standard slide for each L2

Charge #1,2

slide-41
SLIDE 41

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 41

Progress to Date

§ Content:

§ Technical and/or organizaJonal achievements to date. Could

be prototyping or proof-of-principle successes, design reviews, cost/schedule/management reviews, partnering agreements, etc.

§ Message:

§ Team is already funcJoning effecJvely at this early stage. § Design is on track.

Charge #1

slide-42
SLIDE 42

Chris Neu MIP Timing Detector Fermilab Director’s Review April 4, 2018 42

Next Steps toward CD-2

§ Content:

§ List of major acJviJes/milestones to complete before CD-2:

§ Staffing increases § Procurements § Prototyping § Preliminary Design § Infrastructure construcJon

§ Message:

§ We are execuJng our plan and CD-1 is criJcal to maintaining

  • ur schedule

Charge #1