10/10/2019 1 Predictive Maintenance Part Two: The Application of Condition Monitoring Thursday Oct ober 10, 2019 1:00 3:00 PM ET 2 1 10/10/2019 How to Participate Today Audio Modes Listen using Mic & S peakers Or,


slide-1
SLIDE 1

10/10/2019 1

Predictive Maintenance Part Two: The Application of Condition Monitoring

Thursday Oct ober 10, 2019 1:00 –3:00 PM ET

1 2

slide-2
SLIDE 2

10/10/2019 2

How to Participate Today

  • Audio Modes
  • Listen using Mic &

S peakers

  • Or, select “ Use

Telephone” and dial the conference (please remember long distance phone charges apply).

  • Submit your questions using

the Questions pane.

  • A recording will be available

for replay shortly after this webcast.

Today’s Speakers

  • Fred Edgecomb (moderat or)
  • Matt Blaschke, Allied Reliability
  • Condition Monitoring – Predictive

Maintenance Technologies

  • Eric S

tevens, MS DGC

  • Asset Condition Monitoring at MS

DGC

3 4

slide-3
SLIDE 3

10/10/2019 3

  • Broad focus across a wide

variety of machinery and end-markets

  • Over 1,400 benchmarked sites
  • 16 industry verticals
  • Combined 5,000 years of

experience in maintenance and reliability

  • Led the Reliability Journey for
  • ver 400 clients, including 20

Fortune 500 companies

  • Approximately 350

employees throughout North and S

  • uth America

Matt Blaschke, CMRP , CRL CBM Professional, Trainer Allied Reliability

Our Next Speaker Condition Monitoring

Predictive Maintenance Technologies

5 6

slide-4
SLIDE 4

10/10/2019 4

7 8

slide-5
SLIDE 5

10/10/2019 5

9 10

slide-6
SLIDE 6

10/10/2019 6

11 12

slide-7
SLIDE 7

10/10/2019 7

13 14

slide-8
SLIDE 8

10/10/2019 8

15 16

slide-9
SLIDE 9

10/10/2019 9

17 18

slide-10
SLIDE 10

10/10/2019 10

19 20

slide-11
SLIDE 11

10/10/2019 11

21 22

slide-12
SLIDE 12

10/10/2019 12

23 24

slide-13
SLIDE 13

10/10/2019 13

25 26

slide-14
SLIDE 14

10/10/2019 14

27 28

slide-15
SLIDE 15

10/10/2019 15

29 30

slide-16
SLIDE 16

10/10/2019 16

31 32

slide-17
SLIDE 17

10/10/2019 17

Eric Stevens

33 34

slide-18
SLIDE 18

10/10/2019 18

Asset Condition Monitoring at MSDGC

35 36

slide-19
SLIDE 19

10/10/2019 19

  • Increase Proactive Maintenance
  • Shift from reactive to a more proactive culture
  • Improve System Availability/Reliability
  • Avoid forced outages
  • Reduce Downtime
  • Develop internal predictive maintenance skills
  • Improve planning and scheduling process
  • Improve Safety
  • Reduce Reactive Maintenance Cost

Desired Maintenance and Reliability Outcomes

Asset Condition Monitoring

37 38

slide-20
SLIDE 20

10/10/2019 20

Multi- Tiered ACM/ PdM Program

  • Concept developed when MS

D Decided to enhance our PdM programs performance

  • Right PdM technologies already being Employed
  • Vibration and Infra-red by contractor
  • Ultrasonic analysis, off-line, on-line motor circuit analysis

internally but decentralized.

  • Lubrication & wear particle analysis with commercial

lab support

Conversion to an internal two- Tiered ACM/PdM Program

Done after assessment (including 2-day workshop)the following was determined that there were:

  • Problems with the way the PdM services contract was managed, particularly for Post

Maintenace testing.

  • Problems with PdM data collection, feedback, follow-up and data correlation
  • PDm technologies assigned to an in-house Maintenace personnel not being used to full potential

39 40

slide-21
SLIDE 21

10/10/2019 21

ACM/Pdm Program related issues

  • Rotating machinery alignment was

limited to initial installation only

  • By machine shop or new installation contractors.
  • No in-service checks
  • Lubricant & wear particle analysis program was working well but was

understaffed and not full equipped for best practices.

Conversion to a two- tiered ACM/PdM Program

41 42

slide-22
SLIDE 22

10/10/2019 22

Centralized ACM/PdM Team and Technologies

  • Team Leader
  • 4 –

team members

  • Collect and analyze data with st ate-of-the art technology tools

& technology tools and software:

  • Vibration analysis
  • Infra Red Thermography
  • Ultrasonic Analysis
  • On-line and Off-line Motor Testing
  • Lubricant and Wear particle analysis (Initially organized

decentralized, eventually merged under PdM team leadership

Centralized ACM/PdM Team and Technologies

  • Assignment of technologies
  • Based on prior experience
  • Previously held PdM technology certification
  • Expectations
  • Team Members become certified in more than one and up to three

technologies eventually

  • Progressive process (2-years or more)
  • Level 2 in Vibration and Infra red
  • Level 1 in Ultrasonic
  • Competency in others with no established certification schemes.

43 44

slide-23
SLIDE 23

10/10/2019 23 Decentralized Tier of the ACM/PdM Program and Technologies

  • Local Plant Maintenance Personnel
  • Primary Function is equipment preventive and

corrective maintenance

  • Technologies employed
  • Vibration analysis with “ green, Y

ellow, Red, Readouts”

  • Infra Red Thermography “ guns” with Integrated visual imaging and

digital data transfer capability

  • Ultrasonic testing with Db readout and digital data transfer capability
  • Laser alignment equipment for rotating equipment

Decentralized Tier of the ACM/PdM Program and Technologies

  • Decentralized crew tools
  • Empower maintenance crews to determine, with more data than their five senses, when

equipment condition or performance is normal or abnormal

  • S
  • me cases what defects are developing
  • Post Maintenance testing (PMT)
  • Maintenance crews conduct PMT so equipment can be turned over promptly to operations

for use.

45 46

slide-24
SLIDE 24

10/10/2019 24

Laser Alignment Tools at the Local Maintenance crews

  • Consistent with research findings at the University of Tennessee
  • S

hows shaft coupling (offset) misalignment, even when well within manufacturer allowable specifications is detrimental

  • Maj or contributor to bearing life reduction and premature failure
  • Obj ectives and goals for lser alignment technologies
  • Extend bearing and coupling life and overall asset Reliability
  • Reduce the number of bearing and coupling failures “ finds” reported by the PdM team

Outside support for ACM/PdM Program

  • Advising (S

ubj ect matter Expert)

  • Planning, budgeting and progress monitoring
  • Predictive Maintenance Management ( reporting & Communications)

S

  • ftware PDMMS
  • PdM S

ervices Contractor

  • Acting initially (as before) conducting periodic condition monitoring with vibration and

Infra red

  • PdM team member mentoring, training, and certification
  • PdM hardware and software vendors for specific training

47 48

slide-25
SLIDE 25

10/10/2019 25

Benefits of a two-Tiered Program

  • Local Maintenance crew personnel are empowered and equipmed to

declare an asset ready for return to operational service

  • A PdM capability provides maintenance personnel with their own quality

assurance tools

  • There is a division of labor and responsibilities in employment of

predictive technologies

  • A Two Tiered approach relieves the PdM team of the need to perform this

Post maintenance testing task under time constraints (and pressures) needed to return the asset to service as soon as possible.\

  • PdM team specialists can train novice maintenance crew PdM practitioners
  • n use of their easy to learn instruments

Managing & Communicating ACM/PdM Program information

  • Reasons why a dedicated web based PdM management (&

communications) S

  • ftware (PDMMS

) may be needed:

  • Wide dispersal over the geographic area many actual and potential users
  • Cyber security concerns from IT departments about allowing access by outsiders through

established fierwalls into interal networks

  • Other maintenance upgrade iniatives that are in progress
  • CMMS

(Maximo) Upgrade

  • Planing and S

cheduling

  • RCM & ECM analysis

49 50

slide-26
SLIDE 26

10/10/2019 26

Find of the Week

  • Communication Process
  • S

upports proactive culture

  • Recognizes staff
  • Highlights positive results

Questions?

51 52