ROGELIO L. SINGSON Secretary Department of Public Works and Highways
November 18, 2010
PPP Road Projects
1
PPP Road Projects ROGELIO L. SINGSON Secretary Department of - - PowerPoint PPT Presentation
PPP Road Projects ROGELIO L. SINGSON Secretary Department of Public Works and Highways November 18, 2010 1 PRESENTATION OUTLINE Strategic Directions Expressways in Operation and Under Construction Projects for Bidding in 2011 PPP Pipeline
ROGELIO L. SINGSON Secretary Department of Public Works and Highways
November 18, 2010
1
2
3
Project Name Subic-Clark-Tarlac Expressway (93.77 km) North Luzon Tollway (82.62 km) C-5 Expressway (Segment 8.1, 2.34 km) Metro Manila Skyway, Stage 1 (13.43 km At-grade & 9.30 km Viaduct) Manila-Cavite Toll Expressway (6.75 km) South Luzon Tollway (36.03 km) Southern Tagalog Arterial Road (41.90 km) Total Length = 286.14 km
4
5
Project Name Tarlac- Pangasinan- La Union Toll Expressway (TPLEX) (88.58 km) North Luzon Tollway, C-5 Expressway Segment 8.2 - 10.23 km Segment 9 - 4.06 km Segment 10 - 5.63 km NLEx-SLEx Link Expressway (13.4 km) (Unsolicited proposal for NEDA review and subject to Swiss Challenge) Manila-Cavite Toll Expressway, R-1 Extension (7.00 km) Metro Manila Skyway, Stage 2 (6.88 km) Total Length = 135.78 km
6
7
8
Side (27.5 km)
in Cavite Province and Ninoy Aquino International Airport (NAIA), Metro Manila Ports, Batangas Port and decongest traffic of Cavite roads, particularly Aguinaldo Highway
total length of 27.5 kilometers
11.79 Billion (US$ 262 Million)
9
Particular Date Hiring of financial transaction advisor Dec 2010 Preparation of technical/financial plans and tender documents Aug 2011 Completion of ROW acquisition plan and resettlement plan, if applicable Aug 2011 Submission to NEDA Investment Coordination Committee Aug 2011 Commencement of bidding process Sept 2011 Target Bid date Dec 2011
10
Manila-Cavite Coastal Expressway
1, 2, & 3
total length of 5.19 kilometers
10.59 Billion (US$235.33Million)
11
Particular Date Feasibility Study Completed ROW acquisition plan and resettlement plan To be undertaken by Private Sector Submission to NEDA Investment Coordination Committee Of Implementation Program Jan 2011 Commencement of bidding process Mar 2011 Target Bid date July 2011 12
south Luzon industrial beltway transport axis by connecting NLEx and SLEx
right-of-way.
proposal.
approval.
– 2nd Quarter of 2011.
– 3rd Quarter of 2011 – 2014.
(US$ 467 Million)
13
Length (Km) Cost
1. Cavite-Laguna Expressway – Laguna Side Section 14.3 PhP 7.00 B (US$ 155.56 M)
6.8 PhP 5.64 B (US$ 125.33 M) 3. C-6 Expressway (Global City Link) – South Section 50.0 PhP 40.4 B (US$ 897.78 M) 4. C-6 Expressway (Laguna de Bay Flood Control Dike Expressway) 43.6 PhP 18.59 B (US$ 413.11 M) 5. Central Luzon Expressway (CLEX), Phase 2 (Cabanatuan-San Jose) 35.7 PhP 11.81 B (US$ 262.44 M)
14
Length (Km) Cost
6. SLEX Extension (to Lucena City), 2-lane 47.8 PhP 9.5 B (US$ 211.11 M)
15.5 PhP 5.9 B (US$ 131.11 M)
16.1 PhP 23.98 B (US$ 532.89 M)
103.0 PhP 38.8 B (US$ 862.22 M) Total 332.80 PhP 161.62 B (US $ 3,591.55 M)
15
Long Term Performance Based Road Maintenance Projects This is a contracting methodology which will ensure good roads throughout the contract duration (e.g. 10 years or more) for a specified level of service National Bridge Program This will involve the design, construction and 10-yr maintenance contract for national bridges which are identified as priorities. Weighbridge Operation Aims to privatize the operation of weighbridge to have an efficient control of overloading along the selected pilot service area Metro Cebu and Mindanao Expressway Projects 16
17