port of san francisco
play

Port of San Francisco Public Restroom Project Re-Bid Contract No. - PowerPoint PPT Presentation

Port of San Francisco Public Restroom Project Re-Bid Contract No. 2771R January 11, 2018 AGENDA 1. Welcome & Introductions Andre Antonio 2. Project Overview Wendy Proctor 3. CMD Finbarr Jewell 4. OLSE Anna Liu 5. Bid


  1. Port of San Francisco Public Restroom Project Re-Bid Contract No. 2771R January 11, 2018

  2. AGENDA 1. Welcome & Introductions – Andre Antonio 2. Project Overview – Wendy Proctor 3. CMD – Finbarr Jewell 4. OLSE– Anna Liu 5. Bid Documents – Andre Antonio 6. Questions

  3. • Base Bid work includes construction of a new multi-user Men’s and Women’s public restroom inside Pier 45, minor renovations of existing single user restroom door and reconstruction of an infill wall within an existing roll up door. The work will include selective demolition, structural framing, installation of plumbing fixtures, connection to existing sanitary sewer lines and water lines, electrical infrastructure upgrades, demolition of electrical components, installation of new panels and fixtures, installation of mechanical fans, ducts and vents, and installation of toilet accessories, compartments, finishes, and signage. The area of work inside Pier 45 is over land. • Alternate Bid work includes construction of a pre-engineered single user composting toilet in Islais Creek Park. The work will include selective site clearing, earth moving, excavation and protection, and asphalt concrete paving.

  4. • The area of work inside Pier 45 is used for public parking which remain operational during construction. • There are no known hazardous materials in the areas of demolition. Contractor shall perform work in conformance with CAL/OSHA. Contractor shall use best practices to control and contain fungal growth in areas where demolition occurs. • Work areas shall be secured by the contractor. • Soils in the Islais Creek Park will need to be tested prior to disposal.

  5. Presented By: Finbarr Jewell (415)-274-0511 Bidder must be a CMD Certified Micro-LBE. • LBE Subcontractor Participation goal does • not apply. LBE prime contractor bid discount does not • apply. Refer to Section 00 22 11 for details. •

  6. Presented By: Anna Liu

  7. Employers need to match or exceed the City’s Ordinances for the following: Prevailing Wages • Sick Leave • Health Care • Worker Compensation •

  8. Required per San Francisco Administrative Code Section 6.22(g) and Chapter 82 • See Section 00 73 30 for details • NOT REQUIRED Applies to both Prime Contractor and ALL Subcontractors • For Micro-LBE Projects Local Hire Requirement 30% by trade • At least 50% of Apprentice project work hours within each trade shall be • performed by local residents.

  9. QBD  Addendum

  10. ENSUING SITE VISIT AT PIER 45 - SHED A

  11. Questions?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.