POLARIS MINE CLOSURE and RECLAMATION Bruce Donald, P.Eng., - - PowerPoint PPT Presentation

polaris mine
SMART_READER_LITE
LIVE PREVIEW

POLARIS MINE CLOSURE and RECLAMATION Bruce Donald, P.Eng., - - PowerPoint PPT Presentation

POLARIS MINE CLOSURE and RECLAMATION Bruce Donald, P.Eng., Reclamation Manager, Environment and Corporate Affairs Teck Cominco Limited Presentation Agenda Presentation Agenda Introduction Mine Site Components Site Reclamation


slide-1
SLIDE 1

POLARIS MINE

CLOSURE and RECLAMATION

Bruce Donald, P.Eng., Reclamation Manager, Environment and Corporate Affairs Teck Cominco Limited

slide-2
SLIDE 2

Presentation Agenda Presentation Agenda

Introduction Mine Site Components Site Reclamation

slide-3
SLIDE 3

INTRODUCTION

LOCATION

Approximately 100 km northwest of

Resolute Bay, Nunavut

75oN & 97oW Flying time from Yellowknife approx. 2 hrs

by 737

slide-4
SLIDE 4

Yellowknife Iqaluit

slide-5
SLIDE 5
slide-6
SLIDE 6

INTRODUCTION

MINERALIZATION

ORE – Galena (lead sulphide) – Sphalerite (zinc sulphide) Host Rock – Limestone Important Characteristics of Ore Body – Non-Acid Generating – Enclosed Within Continuous Permafrost

slide-7
SLIDE 7

INTRODUCTION

WEATHER CONDITIONS

Mean annual air temperature -170C Average Precipitation – 250mm of which

200 is snow

Average of 8 frost free days per year Temperatures range from about a high of

15 to a low of -500C

Average wind speed of 20 km/hr Snow melts starting early June, returns

mid August.

slide-8
SLIDE 8

INTRODUCTION

PHYSICAL SETTING

Terrain – Very gently rolling hills Overburden is a thin mantle over

calcareous rocks. Surface material in the area of the mine is classed as a barren gravel

Vegetation – Arctic Tundra in clusters or as

a dense mat and is low lying due to the harsh climate, high winds, and shallow soils.

slide-9
SLIDE 9

INTRODUCTION

HISTORY OF SITE

1960 Discovery of lead-zinc deposit 1973 Resource of 25 million tons grading 14% zinc & 4% lead defined 1981 – Mine started production 2002 – Ore body exhausted 2002 - 2004 Decommissioning & reclamation 2005 - 2011 Site monitoring.

slide-10
SLIDE 10

MINE SITE COMPONENTS

Mine Workings Processing Facilities / Concentrate Storage Deep Sea Dock / Ship Loading Tailings Disposal System Accommodations Complex Fuel Storage / Distribution System Landfills Freshwater System Roads / Other Services

slide-11
SLIDE 11

MINE SITE COMPONENTS

Mine Workings

Underground

4 portals Raisebore Holes Subsidence Area

Open Pits

North Pit – small outcrop mined by open pit LRD Limestone Quarry – rock for CRF New Quarry – overburden for roads, etc.

slide-12
SLIDE 12

MINE WORKINGS

slide-13
SLIDE 13

PROCESSING FACILITIES

BARGE CONTAINS

Concentrator Offices Warehouse Dry

PRODUCT STORAGE BUILDING

slide-14
SLIDE 14

PROCESSING FACILITIES

slide-15
SLIDE 15

PROCESSING FACILITIES Demolition / Re-Grading

slide-16
SLIDE 16

PROCESSING FACILITIES

slide-17
SLIDE 17

DEEP SEA DOCK / LOADING FACILITIES

slide-18
SLIDE 18

DEEP SEA DOCK / LOADING FACILITIES Dock Demolition

slide-19
SLIDE 19

TAILINGS DISPOSAL SYSTEM

Tailings Lines between Mill & Thickener Thickener Building Tailings Lines between Thickener and

Garrow Lake

Garrow Dam

slide-20
SLIDE 20

TAILINGS DISPOSAL SYSTEM

slide-21
SLIDE 21

TAILINGS DISPOSAL SYSTEM

Thickener Building Demolition

slide-22
SLIDE 22

TAILINGS DISPOSAL SYSTEM

Decommissioning of Garrow Lake Dam

slide-23
SLIDE 23

ACCOMMODATIONS

slide-24
SLIDE 24

ACCOMMODATIONS

Accommodation Building Demolition

slide-25
SLIDE 25

FUEL STORAGE FUEL STORAGE

slide-26
SLIDE 26

FUEL STORAGE FUEL STORAGE

Tank Farm Demolition Tank Farm Demolition

slide-27
SLIDE 27

LANDFILLS

slide-28
SLIDE 28

LANDFILLS

Capping Nearing Completion

slide-29
SLIDE 29

FRESH WATER SYSTEM FRESH WATER SYSTEM

slide-30
SLIDE 30

ROADS

slide-31
SLIDE 31

SITE RECLAMATION

CLOSURE PLAN ESTABLISHED CONSIDERING:

  • Requirements in Water Licence and Land

Leases

  • NWT Reclamation Policy
  • Corporate Environmental Policy Guide
  • Feed-back from Consultants, Regulators

& Local Communities

slide-32
SLIDE 32

SITE RECLAMATION

OBJECTIVES OF CLOSURE PLAN

To provide a working document that addresses

the concerns and requirements of the stakeholders

Reclaim the site to a condition that health & safety

  • f the public and the environment are protected.

Reclamation to minimize or eliminate long term

maintenance and monitoring.

To return the site to an aesthetically acceptable

condition.

slide-33
SLIDE 33

SITE RECLAMATION

LIMITATIONS OF TK

  • Area not highly used for hunting so

interest in area limited

  • Nearest resident population not

indigenous to area so knowledge is based

  • n recent history
  • Issues from local community were

primarily economic rather than environmental or hunting issues.

slide-34
SLIDE 34

DETERMINING RECLAMATION STANDARDS

SITE SPECIFIC STANDARDS

Soils quality standards based on southern

conditions that were not applicable to the north.

Used risk based standards based on local

knowledge of site usage

Weather / Climate conditions were key in

developing strategies

slide-35
SLIDE 35

OTHER LIMITATIONS

SCIENTIFIC

Limited baseline studies from before mine

built

Uncertainty of Global warming

REGULATORY

Changing regulatory jurisdiction Changing environmental standards Changing bonding standards

slide-36
SLIDE 36

BIGGEST CHALLENGES

FINANCIAL

Costs in the far north are extremely high.

REGULATORY

Due to climate and costs, there are tight time frames for

completing work. Decisions generally require Board approval rather than staff approvals for even simple changes which creates delays.

WEATHER

Transportation costs and transportation delays were one of the

most significant challenges.

SKILLS

Local manpower was generally less skilled than would utilize in a

southern project. For short duration work having to train on the job is a significant deterrent to local hire.

slide-37
SLIDE 37

TEMPORARY ACCOMMODATIONS

slide-38
SLIDE 38

AUGUST 25, 2004 – ALMOST DONE!