polaris mine
play

POLARIS MINE CLOSURE and RECLAMATION Bruce Donald, P.Eng., - PowerPoint PPT Presentation

POLARIS MINE CLOSURE and RECLAMATION Bruce Donald, P.Eng., Reclamation Manager, Environment and Corporate Affairs Teck Cominco Limited Presentation Agenda Presentation Agenda Introduction Mine Site Components Site Reclamation


  1. POLARIS MINE CLOSURE and RECLAMATION Bruce Donald, P.Eng., Reclamation Manager, Environment and Corporate Affairs Teck Cominco Limited

  2. Presentation Agenda Presentation Agenda � Introduction � Mine Site Components � Site Reclamation

  3. INTRODUCTION LOCATION � Approximately 100 km northwest of Resolute Bay, Nunavut � 75 o N & 97 o W � Flying time from Yellowknife approx. 2 hrs by 737

  4. Iqaluit Yellowknife

  5. INTRODUCTION MINERALIZATION � ORE – Galena (lead sulphide) – Sphalerite (zinc sulphide) � Host Rock – Limestone � Important Characteristics of Ore Body – Non-Acid Generating – Enclosed Within Continuous Permafrost

  6. INTRODUCTION WEATHER CONDITIONS � Mean annual air temperature -17 0 C � Average Precipitation – 250mm of which 200 is snow � Average of 8 frost free days per year � Temperatures range from about a high of 15 to a low of -50 0 C � Average wind speed of 20 km/hr � Snow melts starting early June, returns mid August.

  7. INTRODUCTION PHYSICAL SETTING � Terrain – Very gently rolling hills � Overburden is a thin mantle over calcareous rocks. Surface material in the area of the mine is classed as a barren gravel � Vegetation – Arctic Tundra in clusters or as a dense mat and is low lying due to the harsh climate, high winds, and shallow soils.

  8. INTRODUCTION HISTORY OF SITE � 1960 Discovery of lead-zinc deposit � 1973 Resource of 25 million tons grading 14% zinc & 4% lead defined � 1981 – Mine started production � 2002 – Ore body exhausted � 2002 - 2004 Decommissioning & reclamation � 2005 - 2011 Site monitoring.

  9. MINE SITE COMPONENTS � Mine Workings � Processing Facilities / Concentrate Storage � Deep Sea Dock / Ship Loading � Tailings Disposal System � Accommodations Complex � Fuel Storage / Distribution System � Landfills � Freshwater System � Roads / Other Services

  10. MINE SITE COMPONENTS Mine Workings � Underground � 4 portals � Raisebore Holes � Subsidence Area � Open Pits � North Pit – small outcrop mined by open pit � LRD Limestone Quarry – rock for CRF � New Quarry – overburden for roads, etc.

  11. MINE WORKINGS

  12. PROCESSING FACILITIES � BARGE CONTAINS � Concentrator � Offices � Warehouse � Dry � PRODUCT STORAGE BUILDING

  13. PROCESSING FACILITIES

  14. PROCESSING FACILITIES Demolition / Re-Grading

  15. PROCESSING FACILITIES

  16. DEEP SEA DOCK / LOADING FACILITIES

  17. DEEP SEA DOCK / LOADING FACILITIES Dock Demolition

  18. TAILINGS DISPOSAL SYSTEM � Tailings Lines between Mill & Thickener � Thickener Building � Tailings Lines between Thickener and Garrow Lake � Garrow Dam

  19. TAILINGS DISPOSAL SYSTEM

  20. TAILINGS DISPOSAL SYSTEM Thickener Building Demolition

  21. TAILINGS DISPOSAL SYSTEM Decommissioning of Garrow Lake Dam

  22. ACCOMMODATIONS

  23. ACCOMMODATIONS Accommodation Building Demolition

  24. FUEL STORAGE FUEL STORAGE

  25. FUEL STORAGE FUEL STORAGE Tank Farm Demolition Tank Farm Demolition

  26. LANDFILLS

  27. LANDFILLS Capping Nearing Completion

  28. FRESH WATER SYSTEM FRESH WATER SYSTEM

  29. ROADS

  30. SITE RECLAMATION CLOSURE PLAN ESTABLISHED CONSIDERING: Requirements in Water Licence and Land � Leases NWT Reclamation Policy � Corporate Environmental Policy Guide � Feed-back from Consultants, Regulators � & Local Communities

  31. SITE RECLAMATION OBJECTIVES OF CLOSURE PLAN � To provide a working document that addresses the concerns and requirements of the stakeholders � Reclaim the site to a condition that health & safety of the public and the environment are protected. � Reclamation to minimize or eliminate long term maintenance and monitoring. � To return the site to an aesthetically acceptable condition.

  32. SITE RECLAMATION LIMITATIONS OF TK Area not highly used for hunting so � interest in area limited Nearest resident population not � indigenous to area so knowledge is based on recent history Issues from local community were � primarily economic rather than environmental or hunting issues.

  33. DETERMINING RECLAMATION STANDARDS SITE SPECIFIC STANDARDS � Soils quality standards based on southern conditions that were not applicable to the north. � Used risk based standards based on local knowledge of site usage � Weather / Climate conditions were key in developing strategies

  34. OTHER LIMITATIONS � SCIENTIFIC � Limited baseline studies from before mine built � Uncertainty of Global warming � REGULATORY � Changing regulatory jurisdiction � Changing environmental standards � Changing bonding standards

  35. BIGGEST CHALLENGES FINANCIAL � Costs in the far north are extremely high. REGULATORY � Due to climate and costs, there are tight time frames for completing work. Decisions generally require Board approval rather than staff approvals for even simple changes which creates delays. WEATHER � Transportation costs and transportation delays were one of the most significant challenges. SKILLS � Local manpower was generally less skilled than would utilize in a southern project. For short duration work having to train on the job is a significant deterrent to local hire.

  36. TEMPORARY ACCOMMODATIONS

  37. AUGUST 25, 2004 – ALMOST DONE!

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend