Plymouth Transportation & Visitors Services Center May 6, 2014 Town of Plymouth Board of Selectmen Project Update - Schematic Design Plymouth Transportation & Visitors Services Center Overview PRIMARY PROJECT OBJECTIVES: Help


slide-1
SLIDE 1

Plymouth Transportation & Visitors Services Center

Plymouth Transportation & Visitor’s Services Center May 6, 2014 Town of Plymouth Board of Selectmen Project Update - Schematic Design

slide-2
SLIDE 2

Plymouth Transportation & Visitors Services Center

Overview

PRIMARY PROJECT OBJECTIVES:

  • Help address the downtown/waterfront parking shortage
  • Promote alternative transit modes to, from, and within Plymouth
  • Positive addition to visual character and identity of the area
  • Promote visitor interest & access to both waterfront and downtown
  • Promote expanded use of Memorial Hall and similar venues
slide-3
SLIDE 3

Plymouth Transportation & Visitors Services Center

Exterior design process

Outreach:

  • Steering committee (GATRA, PGDC, Town)
  • Selectman and Building Dept. representatives
  • Chamber, Destination Plymouth, Economic Development, Plymouth 400
  • Fire Dept., Town DPW
  • Antiquarian Society, adjacent development proposals
  • Memorial Hall
  • Economic viability (Mass Dept. Finance Agency)
  • Federal Transit Administration
  • State legislators (house and senate)

Approach includes functional, analytical, experiential, commercial, and historical considerations

slide-4
SLIDE 4

Plymouth Transportation & Visitors Services Center

Agenda

In October 2013 we discussed….

  • Overview of 2012 McMahon site selection study
  • Verification process, changes to McMahon study
  • Program, functional layout, site organization

Tonight we discuss….

  • Refinements to functional layout and program since last Fall
  • Outreach process with local authorities and officials
  • Exterior schematic design
  • Project funding
  • Next steps
slide-5
SLIDE 5

Plymouth Transportation & Visitors Services Center

Preliminary Design process

  • A. Project Verification

Jun-Aug 2013

  • B. Concept Design

Sep-Oct 2013

  • C. Preliminary Design

Nov-Mar 2014 Final Design & Construction Apr 2014- June 2017 What are the project objectives? What limitations / opportunities exist? What is the most appropriate exterior appearance? Where are the needed resources coming from? What permits will be required to proceed? What options exist to achieve the objectives? Which option is best? What resources are needed to be successful?

slide-6
SLIDE 6

Plymouth Transportation & Visitors Services Center

CURRENT DESIGN AND ORGANIZATION

slide-7
SLIDE 7

Plymouth Transportation & Visitors Services Center

Building footprint

  • Includes Visitors Center
slide-8
SLIDE 8

Plymouth Transportation & Visitors Services Center

“People” zone

  • Visitors Center
  • Transit Center
  • Commercial space (3 levels)

Harbor views from level 2 and 3 commercial space

slide-9
SLIDE 9

Plymouth Transportation & Visitors Services Center

“People” zone

  • Visitors Center
  • Transit Center
  • Commercial space

Pedestrian friendly walkway Pedestrian friendly walkway

slide-10
SLIDE 10

Plymouth Transportation & Visitors Services Center

“Auto” zone

  • Meter parking – ground level
slide-11
SLIDE 11

Plymouth Transportation & Visitors Services Center

“Auto” zone

  • Ticket parking – upper 3 levels
slide-12
SLIDE 12

Plymouth Transportation & Visitors Services Center

“Transit” zone

  • 7 bus berths within parking structure
  • Transfers to trolley, pedicab, bike share
  • Adjacent to transit center lobby on water street
slide-13
SLIDE 13

Plymouth Transportation & Visitors Services Center

EXTERIOR DESIGN EXPRESSION

slide-14
SLIDE 14

Plymouth Transportation & Visitors Services Center

xxxxx

slide-15
SLIDE 15

Plymouth Transportation & Visitors Services Center

Memorial Hall cornice line height limitation

Building Massing

slide-16
SLIDE 16

Plymouth Transportation & Visitors Services Center

Parking level adjustment to minimize Water Street height

slide-17
SLIDE 17

Plymouth Transportation & Visitors Services Center

Water Street commercial zone

slide-18
SLIDE 18

Plymouth Transportation & Visitors Services Center

Bus and auto entry/exit conditions

slide-19
SLIDE 19

Plymouth Transportation & Visitors Services Center

Transit center adjacent to busway, visible from Water Street

slide-20
SLIDE 20

Plymouth Transportation & Visitors Services Center

Visitor’s center corner location, first floor, views and orientation

slide-21
SLIDE 21

Plymouth Transportation & Visitors Services Center

Prime corner second floor water view – ‘civic porch’ plus commercial

  • pportunity.
slide-22
SLIDE 22

Plymouth Transportation & Visitors Services Center

slide-23
SLIDE 23

Plymouth Transportation & Visitors Services Center

Transit Center

  • GATRA Bus Station
  • Bicycle Rental/Share

Leasable Space

  • Restaurant or Other Use

Pedestrian Walkway Leasable Space

  • Coffee Shop/Bar
  • Outdoor Cafe

Visitor Center & Cafe

slide-24
SLIDE 24

Plymouth Transportation & Visitors Services Center

Waterfront-downtown connector

slide-25
SLIDE 25

Plymouth Transportation & Visitors Services Center

Waterfront-downtown connector

slide-26
SLIDE 26

Plymouth Transportation & Visitors Services Center

Memorial Drive

slide-27
SLIDE 27

Plymouth Transportation & Visitors Services Center

Town Wharf View

slide-28
SLIDE 28

Plymouth Transportation & Visitors Services Center

Mezzanine Level

slide-29
SLIDE 29

Plymouth Transportation & Visitors Services Center

Water Street

slide-30
SLIDE 30

Plymouth Transportation & Visitors Services Center

Funding

COSTS

Acquisition and site prep $0 Hard $18,977,959 Soft $3,439,193 Financing $240,500 TDC TDC $22,6 ,657,6 7,651

SOURCES

GATR ATRA (TI TIGE GER) $10,000,000 Ma MassDOT T (T-Bond Bill) $8,000,000 PG PGDC--

  • -Equity

$472,528 PG PGDC--

  • -Bond

$3,025,224 Commerc rcial Ar Area ma master r lease $1,159,900 To Total $22,6 ,657,6 7,652

slide-31
SLIDE 31

Plymouth Transportation & Visitors Services Center

  • Develop updated funding scenario
  • Develop schematic design to build support and confirm budgeting

NOW

2013 2014 2015 2016 2017 2018 2019 1. PRELIMINARY DESIGN ( 8-9 mo.) 2. FINAL DESIGN, PERMITTING, FUNDING (12-24 mo.) 3. PROCUREMENT / BIDDING (3 mo.) 4. CONSTRUCTION (16-20 mo.)

Next Steps: Schedule

2020

slide-32
SLIDE 32

Plymouth Transportation & Visitors Services Center

  • Endorsement from PGDC, GATRA, and Board of Selectmen to proceed

with final design and permitting

  • Update the existing MOU for final design and permitting
  • Initiate local project review process
  • Detailed design and permitting approvals
  • Secure full funding authorization and financing

Next Steps: Process