Plug & Abandonment Forum (PAF) Desired P&A direction - - - PowerPoint PPT Presentation

plug abandonment forum paf
SMART_READER_LITE
LIVE PREVIEW

Plug & Abandonment Forum (PAF) Desired P&A direction - - - PowerPoint PPT Presentation

Plug & Abandonment Forum (PAF) Desired P&A direction - P&A Technology Roadmap Martin Straume, chairman PAF P&A Engineering Manager, AkerBP Topics - History of Technology Roadmap 2015 - 2018 - Technology Roadmap 2017 2020


slide-1
SLIDE 1

Plug & Abandonment Forum (PAF)

Desired P&A direction - P&A Technology Roadmap

Martin Straume, chairman PAF P&A Engineering Manager, AkerBP

slide-2
SLIDE 2

2

Topics

  • History of Technology Roadmap 2015 - 2018
  • Technology Roadmap 2017 – 2020
  • what technologies is our industry working on?
  • Way forward
slide-3
SLIDE 3

Roadmap for New P&A Technologies

3

Optimize Perf Wash & Cement Optimize Milling Rigless P&A:

  • High Capacity CT System
  • High Energy Solutions

(Melt/Burn)/Extreme Concept Alternatives to cement:

  • Creeping shale/Formation

effects

  • Sand/Rock/Natural

materials

  • Chemical materials
  • Steel

Improved Verification / Logging methods Wireless technology (subsea wellheads) Tubing left in hole Ctrl line left in hole Dual string: Cement bond logging Perf, Wash & Cement, Milling Well Intervention technology for P&A Tender Support P&A rigs/Modular Rigs LIV CT Pilothole drilling/cementing Rig/Process optimization

Drill Pipe Coil Tubing Through Tubing Wireline Rigless

2015 2016 2017 2018

Focus areas for 2017 - 2018 Futuristic Technologies xxxxxxxxxx

slide-4
SLIDE 4

Looking back to June 2013

4

Who pays the largest part? Exactly - We - 78%

slide-5
SLIDE 5

Roadmap for New P&A Technologies

5

Drill Pipe Coil Tubing Through Tubing Wireline Rigless

slide-6
SLIDE 6

Roadmap for New P&A Technologies

6

Optimize Perf Wash & Cement Optimize Milling Rigless P&A:

  • High Capacity CT System
  • High Energy Solutions

(Melt/Burn)/Extreme Concept Alternatives to cement:

  • Creeping shale/Formation

effects

  • Sand/Rock/Natural

materials

  • Chemical materials
  • Steel

Improved Verification / Logging methods Wireless technology (subsea wellheads) Tubing left in hole Ctrl line left in hole Dual string: Cement bond logging Perf, Wash & Cement, Milling Well Intervention technology for P&A Tender Support P&A rigs/Modular Rigs LIV CT Pilothole drilling/cementing Rig/Process optimization

Drill Pipe Coil Tubing Through Tubing Wireline Rigless

2017 2018 2019 2020

Focus areas for 2017 – 2020 Many projects - ongoing Focus areas for 2017 – 2020 Work started

slide-7
SLIDE 7

7

Summary

  • Rigless technology is being developed. See here today.
  • Moving P&A from rig to rigless scope has shown up to

50 % savings compared to conventional techniques.

  • Operators are the energizers to new P&A technology.

Enthusiastic sponsors is "a must". - Ildsjel -

  • P&A Roadmap shows operators & authorities intention

to cont. focus on P&A cost savings via new technology .

  • OG21, Education, Design of new wells for future P&A.
  • Continue on our path