plans for mice at ral
play

Plans for MICE at RAL Paul Drumm WG3 Fact03 paul drumm, mutac jan - PowerPoint PPT Presentation

Plans for MICE at RAL Paul Drumm WG3 Fact03 paul drumm, mutac jan 2003 1 MICE MICE Status - Yagmur Toruns Talk Scientific approval given Collaboration (incl. host lab) seeking funds Demands on Host Laboratory: Muon


  1. Plans for MICE at RAL Paul Drumm WG3 ν Fact03 paul drumm, mutac jan 2003 1

  2. MICE • MICE Status - Yagmur Torun’s Talk – Scientific approval given – Collaboration (incl. host lab) seeking funds • Demands on Host Laboratory: – Muon Beam – Experiment Area • existing test beam facility – Infrastructure….substantial paul drumm, mutac jan 2003 2

  3. ISIS RAL RAL & ISIS Harwell paul drumm, mutac jan 2003 3

  4. ISIS Linac ~600 keV C-W H-Injector 70 MeV DTL Linac paul drumm, mutac jan 2003 4

  5. ISIS Ring 50 Hz Rapid Cycling Synchrotron Charge-Exchange (foil) injection Fill ~10 ms Accelerate ~10 ms 200 µ A, 800 MeV Beam (160 kW) 1.5 MHz, dual harmonic - two bunches ~ 1.5×10 13 protons total paul drumm, mutac jan 2003 5

  6. Existing Facility • Insertion (dipping) Target in synchrotron • Beam line Based on ex NIMROD magnets (1950s) – multi – GeV beams (!) • Beam (p/ π ) Used for Detector Testing • Low rate • Low use • Upgrade for MICE paul drumm, mutac jan 2003 6

  7. Existing Target Internal Target catches edge of beam Replacement Target System Needed -Reliability -Reproducibility paul drumm, mutac jan 2003 7

  8. paul drumm, mutac jan 2003 8

  9. paul drumm, mutac jan 2003 Mice Hall Hall: L = 47 m W = 12 m H = 8 m S = 564 m 2 V = 4512 m 3 Two overhead cranes (8 tonnes each) 9

  10. Mice Hall .. paul drumm, mutac jan 2003 10

  11. New Beam Line • Reuse existing beam elements • PSI SC magnet from µ E4 beam line (5m, 5T) – Production Target & Capture - quads – π momentum selection (dipole) – Decay (Solenoid) – µ momentum selection / π rejection (dipole) paul drumm, mutac jan 2003 11

  12. Beam Purity (quad doublet Example) paul drumm, mutac jan 2003 12

  13. Beam Line • P µ < 400 MeV/c • Rejection of protons and pions <10% • few muons per µ s • Two solutions possible: – PSI solenoid – cryogenics available – release by PSI – quadrupoles • Preferred solution - Solenoid paul drumm, mutac jan 2003 13

  14. Front End Options paul drumm, mutac jan 2003 14

  15. MICE Experiment paul drumm, mutac jan 2003 15

  16. MICE Layout… & Infrastructure paul drumm, mutac jan 2003 16

  17. RF System 8 ×201 MHz Cavities Solenoid Magnet Cooling Channel Envelope RF Cavity 1 MW per cavity Cavities Low Duty Factor Raft 1-2 ms Absorber Tuning 1-10 Hz Bellows average power ~1kW/Hz paul drumm, mutac jan 2003 17

  18. RF Drive - One Chain drives 1 Cavity TH571or ex Solid State TH116 SPS AMP Driver 70db COUPLER 10mW 1.2MW 60 kW 2 kW 40 kV 20 kV LEVEL & PHASE CONTROL - proposed scheme ~ SOURCE OTHER DRIVE R.A. Church RAL CHAINS paul drumm, mutac jan 2003 18

  19. RF System paul drumm, mutac jan 2003 19

  20. RAL RF Tube Tests • Stock of ~ 12 retired tubes 260 µ s • trial tube operated I A comfortably at 1.25 ~110 A Field MW (~300 µ s pulse at 50/32 Hz) • (peaks at ~1.6 MW) paul drumm, mutac jan 2003 20

  21. Liquid Hydrogen Absorber • Liquid Hydrogen – Major safety issue – ISIS Liquid Hydrogen Moderator paul drumm, mutac jan 2003 21

  22. “ Detector 1 Absorber 1 RF 1 Absorber 2 RF 2 Absorber 3 Detector 2 -beam Absorber .. Vacuum LH 2 He Detector gas “ Absorber 2 Absorber 1 Absorber 3 Detector 1 RF 1 RF 2 Detector 2 -beam “ Detector 2 Detector 1 Absorber 2 RF 2 Absorber 3 Absorber 1 RF 1 -beam paul drumm, mutac jan 2003 22

  23. Absorber Evolution … paul drumm, mutac jan 2003 23

  24. Absorber Integration . paul drumm, mutac jan 2003 24

  25. Absorber Integration .. paul drumm, mutac jan 2003 25

  26. Safety Loop paul drumm, mutac jan 2003 26

  27. Magnets & Cryogenics Principle Issues – Fringe Fields – Cryogenic Requirements - 380W @4K = 500W Unit Blue contours: 10 mT Orange: 0.5 mT paul drumm, mutac jan 2003 27

  28. Other Magnetic Configurations Fields in same direction - Still needs to be evaluated - affect on the linac - impact on machine instrumentation & operation - impact on working environment paul drumm, mutac jan 2003 28

  29. Detectors Spectrometer: Technology Choices: Issues: SiFi - Large cyro cooling needed for VLPCs TPG – HV & flamable gas (next to Lig.H cell) paul drumm, mutac jan 2003 29

  30. Basic Infrastructure Plant: Electrical Power ~ 400 kW Cooling Power ~ 500 kW plant Cryogenic System ~ 500 W system small system for µ Sol Hydrogen Delivery - condensation cooling & Handling - ventilation system & safety Control Room - local rack space Installation phased build of the experiment - support & alignment system paul drumm, mutac jan 2003 30

  31. Location ������� ������������� ������������� paul drumm, mutac jan 2003 31

  32. Cryogenics • Muon Solenoid • MICE Solenoids • SciFi detectors • Cryogenic Absorbers • est. ~500W of cooling @4K (incl. margin) • complicated system – design work in progress paul drumm, mutac jan 2003 32

  33. ISIS Perspective Critical Issues: Beam Line Long Shutdown Break into ISIS Synchrotron from MICE Hall Have Shielding available - Next Spring (2004) Competes with other ISIS projects 300 µ A upgrade* • • Second Target Station* • RFQ Installation • delivery of contracted neutron amp.hours * work in synch. vault paul drumm, mutac jan 2003 33

  34. Expected Progress • Proposal submitted start 2003 • Positive reviews from - international review panel - UK funding agency panel • MICE is part of the UK’s Science road map - funds not yet allocated to MICE-UK - budget funding originally foreseen 2004… - negotiations taking place for 2003 • Collaborators requesting funds paul drumm, mutac jan 2003 34

  35. Programme…. • Now till … – clear hall in preparation for • 2004 Shutdown – Start breaking into concrete • Proceed to install infrastructure – Electrical Power, cryogenics, cooling power – Beam Line Solenoid installation & tests • Beam line completed in 2005/6 Shutdown • MICE Installation follows – Expect mice staged operation in 2006…. paul drumm, mutac jan 2003 35

  36. Technical Issues • RF Drivers - need clarification - cost issue • Absorber & Coils Group - design & safety case developing • Absorber Safety Review • Coil Field Configurations - need evaluation/shielding • Integration ….. paul drumm, mutac jan 2003 36

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend