- K. Long,
13 November, 2013
Management
- f the MICE construction effort
and interface to
- perations and analysis
operations and analysis Evolution of management of MICE project: - - PowerPoint PPT Presentation
K. Long, 13 November, 2013 Management of the MICE construction effort and interface to operations and analysis Evolution of management of MICE project: MICE construction project: Host laboratory: Substantial construction project
13 November, 2013
– Project Engineer; full time job;
– Project Manager; full time job
– Updated to address needs of the construction project
– Construction project the responsibility of the MIPO, experimental collaboration “freed up” to ensure proper development of experimental/scientific side of project
– Being discussed within the collaboration; work in progress » Reviewed by MICE Executive Board at its last meeting (08Nov13)
MICE International Project Office
MICE Project Manager
MICE-UK Capital Project
Responsibility Consultation
MICE International Project Team
MICE-US Construction Project
Draft: 02/2013 Rev. E
RAL PPD Director
MICE-International Project Contributions
Mechanical Integration Electrical Integration US MAP Dir
Focus Coil Liquid Hydrogen Delivery RF Power MICE-UK PI
MICE-UK PMO US MAP PMO RF Magnets Detector Magnetic Shielding Component Integration Beam Line Integration Scientist
MICE Collaboration
Experimental Integration Scientist
US Reporting Line UK Reporting Line Collaboration Interface
– Route to multi-TeV lepton-antilepton collissions
464 m
Muon Decay Ring Linac option Ring option Proton Driver: Neutrino Beam Target Buncher Phase Rotation Cooling
2.8–10 GeV RLA 0.8–2.8 GeV RLA Linac to 0.8 GeV
To Accel. To Decay Ring From Acceleration From Cooling
IDS-NF/2012 4.0
Coloma,'Huber,'Kopp,'Winter' arXiv:1209.5973'
Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê
IDS- NF L=2000 km
2 4 6 8 500 1000 1500 2000 2500 0.2 0.4 0.6 0.8 1.0
EnH GeVL Eventsê 500 MeV Efficiency
IDS$ NF'
– Route to multi-TeV lepton-antilepton collissions
464 m
Muon Decay Ring Linac option Ring option Proton Driver: Neutrino Beam Target Buncher Phase Rotation Cooling
2.8–10 GeV RLA 0.8–2.8 GeV RLA Linac to 0.8 GeV
To Accel. To Decay Ring From Acceleration From Cooling
IDS-NF/2012 4.0
arXiv:1301.7727-
Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê Ê
NuMAX L=1290 km
1 2 3 4 5 5 10 15 20 0.2 0.4 0.6 0.8 1.0
EnH GeVL Eventsê 125 MeV Efficiency
NuMAX
464 m
Muon Decay Ring Linac option Ring option Proton Driver: Neutrino Beam Target Buncher Phase Rotation Cooling
2.8–10 GeV RLA 0.8–2.8 GeV RLA Linac to 0.8 GeV
To Accel. To Decay Ring From Acceleration From Cooling
IDS-NF/2012 4.0
– Changes delivery dates for some components; – Includes contingency and appropriate float;
– Principal issue: » Impact and management of R&D risks
– Document(s) [cost, schedule, risk] in preparation:
– Principal issue: » Management of contingency
– But, more advanced on both sides than in May13; – Now seek to rebaseline full project (Step IV; Step V or VI) by ~March 2014