Responsibility and Resource Sharing Ken Long Mark Palmer May 8, - - PowerPoint PPT Presentation

responsibility and resource sharing
SMART_READER_LITE
LIVE PREVIEW

Responsibility and Resource Sharing Ken Long Mark Palmer May 8, - - PowerPoint PPT Presentation

MICE Construction: Responsibility and Resource Sharing Ken Long Mark Palmer May 8, 2013 MIPO Draft: 02/2013 Rev. E MICE International Project Team RAL PPD Director MICE Collaboration D. Wark A. Blondel (Spokesperson) MICE International


slide-1
SLIDE 1

MICE Construction: Responsibility and Resource Sharing

Ken Long Mark Palmer May 8, 2013

slide-2
SLIDE 2

MIPO

May 7-8, 2013 MICE RLS Review (RAL) 2

MICE International Project Office

MICE Project Manager

  • A. Nichols

MICE-UK Capital Project

  • R. Preece

Responsibility Consultation

MICE International Project Team

MICE-US Construction Project

  • A. Bross

Draft: 02/2013 Rev. E

RAL PPD Director

  • D. Wark

MICE-International Project Contributions

Mechanical Integration Electrical Integration US MAP Dir

  • M. Palmer

Focus Coil Liquid Hydrogen Delivery RF Power MICE-UK PI

  • K. Long

MICE-UK PMO US MAP PMO RF Magnets Detector Magnetic Shielding Component Integration Beam Line Integration Scientist

MICE Collaboration

  • A. Blondel (Spokesperson)

Experimental Integration Scientist

US Reporting Line UK Reporting Line Collaboration Interface

slide-3
SLIDE 3

MIPO

  • Provides a mechanism for:

– Detailed and integrated scheduling – Assessing realistic budget constraints with contingency – A management chain integrated with the funding paths, thus providing a clear chain of responsibility

  • Comments:
  • A realistic and robust schedule cannot be achieved on the basis of a

simplistic model of components being delivered to RAL for modular integration into a beam line

– Risks and potential for contingencies are simply too great – Systems integration issues are significant – These issues have major budget and manpower impacts for the primary members of the construction effort

  • Construction and integration of a muon cooling channel requires a

more holistic approach

May 7-8, 2013 MICE RLS Review (RAL) 3

slide-4
SLIDE 4

Near Term MIPO Priorities

  • Detailed analysis of contingency issues

– Requires integrated team – Requires integrated tools – Requires an agreed upon model for managing a project with significant technical risks still active

  • Thus providing a schedule which

– Realistically assesses the budget and contingency constraints – Can specify the expected dates for experimental capabilities with a high degree of reliability

  • And also budget assumptions to complete each

experimental step which are believable

May 7-8, 2013 MICE RLS Review (RAL) 4

slide-5
SLIDE 5

MIPO Challenges

  • Have already discussed integrated scheduling and a

mutually agreed upon model for assessing budget and contingency

  • Management of contingency across international

funding boundaries remains challenging

– Potential bias in the solutions chosen – Potential inefficient use of resources

  • Need a clear funding profile among all major

participants that accounts for contingency so as to enable proper execution a Would like to negotiate with funding agencies how to implement this

May 7-8, 2013 MICE RLS Review (RAL) 5

slide-6
SLIDE 6

MIPO: in operation

  • Many discussions on implementation of MIPO, how it
  • perates, interface with MICE collaboration etc.

– Realised when asked at RLSR that we were not clear amongst ourselves about the details of its operation

  • Propose to produce a one-page specification for the
  • peration of MIPO in time for the MICE collaboration

meeting at FNAL/IIT in 17—19 June 2013

– Andy Nichols has agreed to produce this document on this timescale

May 7-8, 2013 MICE RLS Review (RAL) 6