PLANING CRITERIA TO LOCATE SWITCHES IN DISTRIBUTION SYSTEMS Juan M. - - PowerPoint PPT Presentation
PLANING CRITERIA TO LOCATE SWITCHES IN DISTRIBUTION SYSTEMS Juan M. - - PowerPoint PPT Presentation
PLANING CRITERIA TO LOCATE SWITCHES IN DISTRIBUTION SYSTEMS Juan M. Gers, PhD Cuernavaca, Mexico September 19 th , 2018 Content Introduction to Smart Grids and SGMM Optimal Topology Switch Location Feeder Reconfiguration
- Introduction to Smart Grids and SGMM
- Optimal Topology
- Switch Location
- Feeder Reconfiguration
- Conclusions
Content
The smart grid concept penetrates throughout the entire organization:
- Smart meters
- Smart feeders (Distribution Automation)
- Smart substations
- Smart transmission
- Smart centralized generation (and
distributed generation)
Electrical Components of Smart Grids
Smart Grid
Smart Meters Smart Generation Smart Feeders Smart Substation Smart Transmission
A major power grid transformation is underway
How can utilities
- Develop effective roadmaps?
- Track progress?
- Understand their posture in comparison
to peers?
The Smart Grid Maturity Model was developed by utilities to address these concerns
4
5 4 3 2 1
SGMM at a glance
SMR
Strategy, Management, & Regulatory
OS
Organization & Structure
GO
Grid Operations
WAM
Work & Asset Management
TECH
Technology
CUST
Customer
VCI
Value Chain Integration
SE
Societal & Environmental
8 Domains: Logical groupings of smart grid related characteristics 6 Maturity Levels: Defined sets of characteristics and outcomes 175 Characteristics: Features you would expect to see at each stage of the smart grid journey
5
Compass results: maturity profile
example results 2 3 2 2 3 2 1
SGMM maturity profile includes a maturity score for each domain
6
Navigation results: consensus aspirations
example results 2 3 2 2 3 2 1
This is where we are today
3 3 4 4 4 3 2 2
This is where we aspire to be in X years
NOTE: There is no “correct” target profile implied in the model; the optimal profile will vary by utility.
7
Partners were licensed to provide official SEI services, delivered by SEI-Certified SGMM Navigators, until the SGMM Partner and Navigator programs ended in mid-2018. At that time, the SGMM Partners were
Cognizant Technologies
8
SGMM Partners
Electrical Components of Smart Grids
Smart Grids/Distribution Automation Benefits AMI & Improve reliability Fault Location, Isolation and System Restoration
- Metering management
- Reduce outage
duration.
- Reduce number of
- utages.
- Improve quality indices
Improve system efficiency Volt/Var Control
- Reduce line losses
- Fulfill voltage profile
regulation Effective DG integration Inverters, numerical protection, SCADA, and others technology
- ptions
- Improve impact from
ER
- Improve Power Quality
- Improve Reliability
Advanced asset management Sensors to determine maintenance program according to condition-based status
- Reduce maintenance
expenses
- Reduce associated
failure expenses
- Deferral of replacement
- Under normal operating conditions, feeder
reconfiguration aims for a more efficient
- perating condition of the network.
- Under
faulty conditions, feeder reconfiguration aims to restore the service to the maximum number of users in the shortest time.
- Prior
to determining the location
- f
switches to allow changes in configuration, it is highly recommended to find the best topology for a distribution system.
Introduction
The optimal topology normally represents the lowest losses of the system. To determine it, specialized software packages are used, which assume that all the poles, in particular the double deadends, are potential open points.
This allows the software to determine the best boundaries among feeders to reduce the overall losses.
Optimal Topology
Potential Opening Points
Feeder 1
DOUBLE DEADEND SINGLE SUPPORT ON CROSSARM
Feeder 2 SUB A SUB B a1 a2 ai an b1 b2 bj bm bjx
Case Study
EMCALI is an utility that has around 110 feeders at 13.2 kV that register a total loss figure above 15% which requires the application of several methods among them the feeder reconfiguration
S/E SOUTH S/E SAINT ANTHONY
Prototype of the distribution system before reconfiguration
COLOR CIRCUIT CODE
Crystals
- St. Anthony
10th Street Lido Britain Cedar 0106 0010 0109 0517 0513 0518
Summary of Results
100 200 300 400 500 600 700 800 kW BEFORE AND AFTER RECONFIGURATION LOSSES IN kW OF RESIDENTIAL CIRCUITS
Link Current Location Recommended Location Initial Losses (kW) Final Losses (kW) Reduction (kW) Volt Min # Link Circuits Link Circuits CLR CTL Total CRL CTL Total Opt. Topology Load Flow (p.u) 1 100483A-100483B 0110 0517 1003445-1192621 0517 9.11 292.36 301.47 46.58 163.26 209.84 90.45 91.63 0.970302 12 106023A-106023B 0106 0518 1008536-1201573 0518 61.08 99.98 161.06 82.34 73.40 155.74 5.37 5.32 0.958584 15 106202A-106202B 0109 0513 1061321-1184474 0513 10.99 226.72 237.71 56.66 118.02 174.68 62.63 63.03 0.968333 TOTAL 81.18 619.06 700.24 185.58 354.68 540.26 158.45 159.98
Case Study
14 13 11 9 7 3 20 21 18 17 16 15 12 4 1 2 6 5 8 19 10
14 13 11 9' 7 3 20 21 18 17 16' 12 4 1' 2 6 5 8 19 10 1 16 15 18' 20' 13' 19' 12' 8' 10' 14' 4'
Case Study
Cost Savings Illustration
If the prototype represents 5% of the overall system, the total savings amount is $ 2,803,200
0.10 $/kWh
kWh Cost
160 kW
Losses saving
Data
160 kW 8760 h 0.10 $/kWh
$ 140,160
Annual Saving
Location of switches controlled remotely
- The placement of switches is
carried out in such a way that the reliability and flexibility criteria
- f
the network are increased.
- The reliability of distribution
networks can be greatly improved by adding switches along the feeders.
- The
benefit
- f
adding the switches can be measured by examining the improvement in reliability performance.
N1
F=25,988 1/yr T=0,536 h Q=836,269 min/yr
N3 N2 N8 N6 N7 N4 N13 N10 N11 N12
F=0,960 1/yr T=0,450 h Q=25,920 min/yr F=1,400 1/yr T=0,500 h Q=42,000 min/yr F=2,000 1/yr T=0,750 h Q=90,000 min/yr F=5,119 1/yr T=0,567 h Q=174,226 min/yr F=2,860 1/yr T=0,649 h Q=111,416 min/yr F=10,335 1/yr T=0,543 h Q=336,523 min/yr F=4,939 1/yr T=0,601 h Q=178,185 min/yr F=10,335 1/yr T=0,543 h Q=336,523 min/yr
N9 N5
F=5,199 1/yr T=0,544 h Q=169,782 min/yr F=3,060 1/yr T=0,484 h Q=88,917 min/yr F=3,780 1/yr T=0,500 h Q=113,394 min/yr F=2,800 1/yr T=0,625 h Q=104,995 min/yr
Location of switches controlled remotely
Some of the most common reliability parameters are the following:
- Failure
Rate, λ, describes the number of times per year that a component can expected to experience a failure.
- Mean Time to Repair (MTTR), r,
represents the expected time it will take for a failure to be repaired.
- Probability of being available, P,
and a probability of not being available, Q. These parameters are found with a proper network modeling
1 2 3 4 5
1 2 3 4 5 Original Network Step 1: Reduces Series Components Step 2: Reduces Parallel Components Step 3: Reduces Series Components
RELIABILITY
Location of switches controlled remotely
N1
F=25,988 1/yr T=0,536 h Q=836,269 min/yr
N3 N2 N8 N6 N7 N4 N13 N10 N11 N12
F=0,960 1/yr T=0,450 h Q=25,920 min/yr F=1,400 1/yr T=0,500 h Q=42,000 min/yr F=2,000 1/yr T=0,750 h Q=90,000 min/yr F=5,119 1/yr T=0,567 h Q=174,226 min/yr F=2,860 1/yr T=0,649 h Q=111,416 min/yr F=10,335 1/yr T=0,543 h Q=336,523 min/yr F=4,939 1/yr T=0,601 h Q=178,185 min/yr F=10,335 1/yr T=0,543 h Q=336,523 min/yr
N9 N5
F=5,199 1/yr T=0,544 h Q=169,782 min/yr F=3,060 1/yr T=0,484 h Q=88,917 min/yr F=3,780 1/yr T=0,500 h Q=113,394 min/yr F=2,800 1/yr T=0,625 h Q=104,995 min/yr
F [1/yr] T [h] Q [min/yr] P [MW/yr] W [MWh/yr] Scenario a 9,137 0,555 304,142 45,683 25,345 Scenario b 10,335 0,543 336,523 51,676 28,044 Scenario c 9,137 0,555 304,142 45,683 25,345 Scenario d 12,253 0,528 388,333 61,266 32,361 Scenario e 10,096 0,545 330,047 50,478 27,504
Location of switches controlled remotely
Switches can be breakers, reclosers and sectionalizers and should have means for remote operation to guarantee a fast reconfiguration when required. The location of switches is carried out based on two flexibility criteria:
FLEXIBILITY
- The feeders are sectionalized into equally loaded portions
as far as it is possible.
- The possibility of transferring one or more load sections
through the flexibility switches at the boundaries
Location of switches controlled remotely
I II III
F3 2 F 1 F
6 5 7 10 8 9 1 11
T1 T2 T3
2 3 4 12 14 13
Location of NC and NO Switches in a DS
Case Example – Initial Configuration
Feeder in studio
Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section
B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13
Case Example – Fault Clearing
Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section
B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13
Case Example – Fault Location and Isolation
Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section
B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13
Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section
B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13
Case Example – Feeder Reenergization
Case Example – System Restoration
Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section
B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13
Case Example – Return to Original Configuration
Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section
B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13
Case Example – Initial Configuration
Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section
B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13
F2 Load = 3p.u. F1 Load = 7p.u. F3 Load = 2p.u. F4 Load = 2p.u. Total Load = 14p.u.
Case Example – System Reconfigured
Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section
B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13
F2 Load = 5p.u. F1 Load = 1p.u. F3 Load = 4p.u. F4 Load = 3p.u. Total Load = 13p.u.
- 1. Planning
criteria should be carefully considered prior to implementing an overall Smart Grid program which is made up by many options. Distribution Automation is one of them that includes optimal topology and FLISR.
- 2. Optimal topology should be a priority in Distribution Systems.
This can be achieved by analyzing the best location of double dead end poles that establish the boundaries among different feeders.
- 3. The location of Section and Tie Switches in DS, should be
accomplished by considering both reliability and flexibility criteria.
- 4. The operation of Tie and Section Switches allow to implement