PLANING CRITERIA TO LOCATE SWITCHES IN DISTRIBUTION SYSTEMS Juan M. - - PowerPoint PPT Presentation

planing criteria to locate switches in distribution
SMART_READER_LITE
LIVE PREVIEW

PLANING CRITERIA TO LOCATE SWITCHES IN DISTRIBUTION SYSTEMS Juan M. - - PowerPoint PPT Presentation

PLANING CRITERIA TO LOCATE SWITCHES IN DISTRIBUTION SYSTEMS Juan M. Gers, PhD Cuernavaca, Mexico September 19 th , 2018 Content Introduction to Smart Grids and SGMM Optimal Topology Switch Location Feeder Reconfiguration


slide-1
SLIDE 1

Juan M. Gers, PhD PLANING CRITERIA TO LOCATE SWITCHES IN DISTRIBUTION SYSTEMS Cuernavaca, Mexico September 19th, 2018

slide-2
SLIDE 2
  • Introduction to Smart Grids and SGMM
  • Optimal Topology
  • Switch Location
  • Feeder Reconfiguration
  • Conclusions

Content

slide-3
SLIDE 3

The smart grid concept penetrates throughout the entire organization:

  • Smart meters
  • Smart feeders (Distribution Automation)
  • Smart substations
  • Smart transmission
  • Smart centralized generation (and

distributed generation)

Electrical Components of Smart Grids

Smart Grid

Smart Meters Smart Generation Smart Feeders Smart Substation Smart Transmission

slide-4
SLIDE 4

A major power grid transformation is underway

How can utilities

  • Develop effective roadmaps?
  • Track progress?
  • Understand their posture in comparison

to peers?

The Smart Grid Maturity Model was developed by utilities to address these concerns

4

slide-5
SLIDE 5

5 4 3 2 1

SGMM at a glance

SMR

Strategy, Management, & Regulatory

OS

Organization & Structure

GO

Grid Operations

WAM

Work & Asset Management

TECH

Technology

CUST

Customer

VCI

Value Chain Integration

SE

Societal & Environmental

8 Domains: Logical groupings of smart grid related characteristics 6 Maturity Levels: Defined sets of characteristics and outcomes 175 Characteristics: Features you would expect to see at each stage of the smart grid journey

5

slide-6
SLIDE 6

Compass results: maturity profile

example results 2 3 2 2 3 2 1

SGMM maturity profile includes a maturity score for each domain

6

slide-7
SLIDE 7

Navigation results: consensus aspirations

example results 2 3 2 2 3 2 1

This is where we are today

3 3 4 4 4 3 2 2

This is where we aspire to be in X years

NOTE: There is no “correct” target profile implied in the model; the optimal profile will vary by utility.

7

slide-8
SLIDE 8

Partners were licensed to provide official SEI services, delivered by SEI-Certified SGMM Navigators, until the SGMM Partner and Navigator programs ended in mid-2018. At that time, the SGMM Partners were

Cognizant Technologies

8

SGMM Partners

slide-9
SLIDE 9

Electrical Components of Smart Grids

Smart Grids/Distribution Automation Benefits AMI & Improve reliability Fault Location, Isolation and System Restoration

  • Metering management
  • Reduce outage

duration.

  • Reduce number of
  • utages.
  • Improve quality indices

Improve system efficiency Volt/Var Control

  • Reduce line losses
  • Fulfill voltage profile

regulation Effective DG integration Inverters, numerical protection, SCADA, and others technology

  • ptions
  • Improve impact from

ER

  • Improve Power Quality
  • Improve Reliability

Advanced asset management Sensors to determine maintenance program according to condition-based status

  • Reduce maintenance

expenses

  • Reduce associated

failure expenses

  • Deferral of replacement
slide-10
SLIDE 10
  • Under normal operating conditions, feeder

reconfiguration aims for a more efficient

  • perating condition of the network.
  • Under

faulty conditions, feeder reconfiguration aims to restore the service to the maximum number of users in the shortest time.

  • Prior

to determining the location

  • f

switches to allow changes in configuration, it is highly recommended to find the best topology for a distribution system.

Introduction

slide-11
SLIDE 11

The optimal topology normally represents the lowest losses of the system. To determine it, specialized software packages are used, which assume that all the poles, in particular the double deadends, are potential open points.

This allows the software to determine the best boundaries among feeders to reduce the overall losses.

Optimal Topology

slide-12
SLIDE 12

Potential Opening Points

Feeder 1

DOUBLE DEADEND SINGLE SUPPORT ON CROSSARM

Feeder 2 SUB A SUB B a1 a2 ai an b1 b2 bj bm bjx

slide-13
SLIDE 13

Case Study

EMCALI is an utility that has around 110 feeders at 13.2 kV that register a total loss figure above 15% which requires the application of several methods among them the feeder reconfiguration

slide-14
SLIDE 14

S/E SOUTH S/E SAINT ANTHONY

Prototype of the distribution system before reconfiguration

COLOR CIRCUIT CODE

Crystals

  • St. Anthony

10th Street Lido Britain Cedar 0106 0010 0109 0517 0513 0518

slide-15
SLIDE 15

Summary of Results

100 200 300 400 500 600 700 800 kW BEFORE AND AFTER RECONFIGURATION LOSSES IN kW OF RESIDENTIAL CIRCUITS

Link Current Location Recommended Location Initial Losses (kW) Final Losses (kW) Reduction (kW) Volt Min # Link Circuits Link Circuits CLR CTL Total CRL CTL Total Opt. Topology Load Flow (p.u) 1 100483A-100483B 0110 0517 1003445-1192621 0517 9.11 292.36 301.47 46.58 163.26 209.84 90.45 91.63 0.970302 12 106023A-106023B 0106 0518 1008536-1201573 0518 61.08 99.98 161.06 82.34 73.40 155.74 5.37 5.32 0.958584 15 106202A-106202B 0109 0513 1061321-1184474 0513 10.99 226.72 237.71 56.66 118.02 174.68 62.63 63.03 0.968333 TOTAL 81.18 619.06 700.24 185.58 354.68 540.26 158.45 159.98

slide-16
SLIDE 16

Case Study

14 13 11 9 7 3 20 21 18 17 16 15 12 4 1 2 6 5 8 19 10

slide-17
SLIDE 17

14 13 11 9' 7 3 20 21 18 17 16' 12 4 1' 2 6 5 8 19 10 1 16 15 18' 20' 13' 19' 12' 8' 10' 14' 4'

Case Study

slide-18
SLIDE 18

Cost Savings Illustration

If the prototype represents 5% of the overall system, the total savings amount is $ 2,803,200

0.10 $/kWh

kWh Cost

160 kW

Losses saving

Data

160 kW 8760 h 0.10 $/kWh

$ 140,160

Annual Saving

slide-19
SLIDE 19

Location of switches controlled remotely

  • The placement of switches is

carried out in such a way that the reliability and flexibility criteria

  • f

the network are increased.

  • The reliability of distribution

networks can be greatly improved by adding switches along the feeders.

  • The

benefit

  • f

adding the switches can be measured by examining the improvement in reliability performance.

N1

F=25,988 1/yr T=0,536 h Q=836,269 min/yr

N3 N2 N8 N6 N7 N4 N13 N10 N11 N12

F=0,960 1/yr T=0,450 h Q=25,920 min/yr F=1,400 1/yr T=0,500 h Q=42,000 min/yr F=2,000 1/yr T=0,750 h Q=90,000 min/yr F=5,119 1/yr T=0,567 h Q=174,226 min/yr F=2,860 1/yr T=0,649 h Q=111,416 min/yr F=10,335 1/yr T=0,543 h Q=336,523 min/yr F=4,939 1/yr T=0,601 h Q=178,185 min/yr F=10,335 1/yr T=0,543 h Q=336,523 min/yr

N9 N5

F=5,199 1/yr T=0,544 h Q=169,782 min/yr F=3,060 1/yr T=0,484 h Q=88,917 min/yr F=3,780 1/yr T=0,500 h Q=113,394 min/yr F=2,800 1/yr T=0,625 h Q=104,995 min/yr

slide-20
SLIDE 20

Location of switches controlled remotely

Some of the most common reliability parameters are the following:

  • Failure

Rate, λ, describes the number of times per year that a component can expected to experience a failure.

  • Mean Time to Repair (MTTR), r,

represents the expected time it will take for a failure to be repaired.

  • Probability of being available, P,

and a probability of not being available, Q. These parameters are found with a proper network modeling

1 2 3 4 5

1 2 3 4 5 Original Network Step 1: Reduces Series Components Step 2: Reduces Parallel Components Step 3: Reduces Series Components

RELIABILITY

slide-21
SLIDE 21

Location of switches controlled remotely

N1

F=25,988 1/yr T=0,536 h Q=836,269 min/yr

N3 N2 N8 N6 N7 N4 N13 N10 N11 N12

F=0,960 1/yr T=0,450 h Q=25,920 min/yr F=1,400 1/yr T=0,500 h Q=42,000 min/yr F=2,000 1/yr T=0,750 h Q=90,000 min/yr F=5,119 1/yr T=0,567 h Q=174,226 min/yr F=2,860 1/yr T=0,649 h Q=111,416 min/yr F=10,335 1/yr T=0,543 h Q=336,523 min/yr F=4,939 1/yr T=0,601 h Q=178,185 min/yr F=10,335 1/yr T=0,543 h Q=336,523 min/yr

N9 N5

F=5,199 1/yr T=0,544 h Q=169,782 min/yr F=3,060 1/yr T=0,484 h Q=88,917 min/yr F=3,780 1/yr T=0,500 h Q=113,394 min/yr F=2,800 1/yr T=0,625 h Q=104,995 min/yr

F [1/yr] T [h] Q [min/yr] P [MW/yr] W [MWh/yr] Scenario a 9,137 0,555 304,142 45,683 25,345 Scenario b 10,335 0,543 336,523 51,676 28,044 Scenario c 9,137 0,555 304,142 45,683 25,345 Scenario d 12,253 0,528 388,333 61,266 32,361 Scenario e 10,096 0,545 330,047 50,478 27,504

slide-22
SLIDE 22

Location of switches controlled remotely

Switches can be breakers, reclosers and sectionalizers and should have means for remote operation to guarantee a fast reconfiguration when required. The location of switches is carried out based on two flexibility criteria:

FLEXIBILITY

  • The feeders are sectionalized into equally loaded portions

as far as it is possible.

  • The possibility of transferring one or more load sections

through the flexibility switches at the boundaries

slide-23
SLIDE 23

Location of switches controlled remotely

slide-24
SLIDE 24

I II III

F3 2 F 1 F

6 5 7 10 8 9 1 11

T1 T2 T3

2 3 4 12 14 13

Location of NC and NO Switches in a DS

slide-25
SLIDE 25

Case Example – Initial Configuration

Feeder in studio

Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section

B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13

slide-26
SLIDE 26

Case Example – Fault Clearing

Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section

B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13

slide-27
SLIDE 27

Case Example – Fault Location and Isolation

Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section

B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13

slide-28
SLIDE 28

Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section

B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13

Case Example – Feeder Reenergization

slide-29
SLIDE 29

Case Example – System Restoration

Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section

B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13

slide-30
SLIDE 30

Case Example – Return to Original Configuration

Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section

B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13

slide-31
SLIDE 31

Case Example – Initial Configuration

Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section

B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13

F2 Load = 3p.u. F1 Load = 7p.u. F3 Load = 2p.u. F4 Load = 2p.u. Total Load = 14p.u.

slide-32
SLIDE 32

Case Example – System Reconfigured

Circuit Breaker Section switch normally closed Tie switch normally open Zi Feeder section

B1 Z1 Z3 Z4 Z5 Z2 Z6 Z7 B3 B4 B2 Z8 Z9 Z10 Z11 Z12 Z13 Z14 S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13

F2 Load = 5p.u. F1 Load = 1p.u. F3 Load = 4p.u. F4 Load = 3p.u. Total Load = 13p.u.

slide-33
SLIDE 33
  • 1. Planning

criteria should be carefully considered prior to implementing an overall Smart Grid program which is made up by many options. Distribution Automation is one of them that includes optimal topology and FLISR.

  • 2. Optimal topology should be a priority in Distribution Systems.

This can be achieved by analyzing the best location of double dead end poles that establish the boundaries among different feeders.

  • 3. The location of Section and Tie Switches in DS, should be

accomplished by considering both reliability and flexibility criteria.

  • 4. The operation of Tie and Section Switches allow to implement

FLISR features. However, care has to be exercised to avoid further nuisance relay tripping .

Conclusions

slide-34
SLIDE 34

Questions?