PINS Briefing 12 August 2015 Robert Powell, Judith Vokes, Richard - - PowerPoint PPT Presentation

pins briefing
SMART_READER_LITE
LIVE PREVIEW

PINS Briefing 12 August 2015 Robert Powell, Judith Vokes, Richard - - PowerPoint PPT Presentation

North West Coast Connections Project PINS Briefing 12 August 2015 Robert Powell, Judith Vokes, Richard Gwilliam The North West Coast Connections Project Moorside 2 What do we need to build? An electrical connection for Moorside needs four


slide-1
SLIDE 1

North West Coast Connections Project PINS Briefing

12 August 2015 Robert Powell, Judith Vokes, Richard Gwilliam

slide-2
SLIDE 2

The North West Coast Connections Project

Moorside 2

slide-3
SLIDE 3

What do we need to build?

An electrical connection for Moorside needs four transmission circuits – two double circuits Double circuit 1 Double circuit 2

3

slide-4
SLIDE 4

Technologies

How Do We Do It?

slide-5
SLIDE 5

Technologies for Connection 400kV AC Overhead Line

132kV Conventional lattice 300-400 MW Height typically 27.5m 400kV Conventional lattice 6,900 MW Height typically 46-50m 400kV T Pylon 6,900 MW Height typically 35-38m 132kV Trident wood pole 120-150 MW Height typically 13m 400kV Low height lattice 6,900 MW Height typically 38- 41m

slide-6
SLIDE 6

Technologies for Connection 400kV AC Overhead Line

400kV Conventional lattice

slide-7
SLIDE 7

7

400kV Low height lattice

Technologies for Connection 400kV AC Overhead Line

slide-8
SLIDE 8

8

400kV T Pylon

Technologies for Connection 400kV AC Overhead Line

slide-9
SLIDE 9

9

132kV Conventional lattice

Technologies for Connection 400kV AC Overhead Line

slide-10
SLIDE 10

10

Minimising the impact

Sensitive routeing of overhead lines Screening and landscaping Rationalisation of existing lines Alternative pylon designs Placing new line underground

slide-11
SLIDE 11

11

Technologies for Connection Underground 400kV AC Cable

This site width 40m 5000A circuit site width 70m

slide-12
SLIDE 12

12

Technologies for Connection Tunnelling

Head house diameter approx 16 metres & 7 metres high Tunnel is about 25- 30 metres below ground Longer tunnels require ventilation points and emergency access along route

slide-13
SLIDE 13

13

Technologies for Connection Tunnelling

slide-14
SLIDE 14

14

Technologies for Connection High Voltage Direct Current (HVDC)

  • An alternative solution to AC for bulk transmission of electricity
  • NG would expect this to be undersea / underground
  • Much narrower cable route than AC
  • The type of HVDC needed does not exist today at required power levels
  • Technology has not yet been used to connect a nuclear power station
slide-15
SLIDE 15

Technology: the options

Overhead line Cable (direct burial XLPE) Cable (gas insulated (GIL)) Cable (tunnel) HVDC

typical

£

£2.5m to £3.0m per km £13m to £32m per km Similar to Cable Cost of tunnel + cable £2m per km plus up to £332m per pair of convertor stations

PROS

Limited disturbance; quick build; operational flexibility together with rapid repair and restoration times Improved visual amenity No reactors or above ground installations; narrower working width. Use in highly constrained areas Advantages over AC transmission over long distance (e.g. interconnectors)

CONS

Visual impact Lengthy construction and disturbance; fault detection and repair; above ground infrastructure; above ground reactive compensation New technology, use

  • f SF6

Difficult to alter/expand Lack of flexibility – difficult to transform voltage; large converter stations required

slide-16
SLIDE 16

Development Programme

slide-17
SLIDE 17

Regional Stakeholder Engagement

 Started in 2005 with drive to see new nuclear development in Cumbria  National Grid involved since 2009  30 local planning authorities  Range of environmental, business and community organisations including; Natural England, English Heritage, the Marine Management Organisation, Morecambe Bay Partnership, CALC, LALC

17

slide-18
SLIDE 18
  • Initial work and

studies looking at the ways to connect Moorside

2013 - 2014 2009 -2011 2012

18

Project Timeline

  • Technical consultation
  • n six broad connection
  • ptions
  • 23 Oct 2012

announced decision to take two strategic

  • ptions forward for

further study

  • Identified route

corridors in which a new connection could be built.

  • 12 week outline

routeing consultation.

  • Landowners contacted.
  • EIA wildlife studies

started.

slide-19
SLIDE 19

2013 - 2014 2009 -2011

19

Project Timeline

2015 2016

  • Review 2014

consultation feedback

  • Announce proposed

route corridor being progressed

  • Ongoing studies to

determine detailed route of new connection and how it will be built

  • Continue working

with stakeholders to shape proposals

  • detailed route
  • construction
  • Mitigation
  • further EIA surveys
  • DCO submission to the

Planning Inspectorate

2017

  • Formal public

consultation on route alignment and construction technologies

  • Complete EIA
slide-20
SLIDE 20

2013 - 2014 2009 -2011 2012

20

Project Timeline

2015 2016 2017

  • Decision on

application made by the Secretary of State for Energy and Climate Change

2018 2019 2024

  • Subject to consent

being granted start construction new connection

  • Complete connection

to meet Moorside first generation in 2024.

slide-21
SLIDE 21

Strategic Options Consultation 11 May 2012 -19 July 2012

slide-22
SLIDE 22

Strategic Options Consultation

slide-23
SLIDE 23

Strategic Options Consultation

slide-24
SLIDE 24

Outline Routeing Public Consultation 4 Sept – 28 Nov 2014

slide-25
SLIDE 25

25

Publicising the Consultation

slide-26
SLIDE 26

26

Publicising the Consultation

slide-27
SLIDE 27

27

Consultation Responses

slide-28
SLIDE 28

What you told us – most common themes

28

The Lake District National Park Rationalisation (removal of existing ENW 132kV towers) Designing a route to minimise landscape impacts Minimising disruption to and impacts on communities The possibility of an offshore

  • ption
slide-29
SLIDE 29

What you told us - Onshore North

29

Preferences mostly for the green route Tends to be seen as sensible, as long as it results in an existing line coming down Some specific areas of concern

slide-30
SLIDE 30

What you told us - Onshore South

30

 Wide opposition to Onshore South  People said running a line through the South Lakes would be unacceptable  The main reason for supporting this route was cost

slide-31
SLIDE 31

What you told us - Offshore South

 People generally supported this option on landscape grounds  But many noted that it was technically challenging  Greatest problem is connecting HVDC  NuGen said this would not work for the nuclear power station

31

slide-32
SLIDE 32

What you told us - Onshore South with Tunnel

 Qualified support from many members of the public  Broad support from stakeholders  People said that if an offshore connection wasn’t possible, then they liked the idea of a tunnel

32

slide-33
SLIDE 33

Consultation Feedback

 Rationalisation of existing

  • verhead lines is important

both north and south of Moorside  Future development south of Whitehaven  Feedback reaffirmed visually sensitive areas, particularly:

  • Lake District National Park
  • Ravenglass
  • Duddon estuary

33

slide-34
SLIDE 34

Consultation Feedback

 All feedback redacted and published on our website for 2012 and 2014 consultations  Propose to repeat this for formal consultation in 2016

34

slide-35
SLIDE 35

Next Steps We will work with: Local Authorities Landowners Parish Councils Community

Agricultural shows Information events Special interest groups

35

slide-36
SLIDE 36

Next Steps

 Which pylons we are going to use and where to put them?  132kV lines to take down?  New substations?  Temporary 132kV lines  415V, 11kV and 33kV crossings  Is there a need for more mitigation?  What landscaping should we do?  EIA Scoping  SOCC

36

slide-37
SLIDE 37

Development Programme

37

2017 2019 2024 2016 Public Consultation on Detailed Proposal Submit DCO Application Start build? Ready for power station

slide-38
SLIDE 38

 GIS  4Projects

Issues and Opportunities

38

slide-39
SLIDE 39

Any Questions?