Place your chosen image here. The four
PINS Update - September 2013 Consultation
image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.
PINS Update - September 2013 Consultation Place your chosen image - - PowerPoint PPT Presentation
PINS Update - September 2013 Consultation Place your chosen image here. The four image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Hinkley Point C
Place your chosen image here. The four
image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.
2
3
Community forums
Information Information Consultation vehicle
4
points hubs
5
6
7
8
9
new transmission pylons VQ 43R and VQ 44R, the installation of new 400kV electricity conductors between pylons VQ 42, VQ 43R, VQ 44R and connections into the new CSE compounds.
Horsey Level near Bridgwater to allow the circuit to pass beneath existing overhead lines.
Horsey Level to the existing 400kV overhead line north of Woolavington. The route is approximately 4.5km in length.
cable sealing end (CSE) compound south of the Mendip Hills adjacent to the M5. The route is approximately 12.5km in length.
proposed CSE compound south of the Mendip Hills to a proposed 400/132kV substation constructed on land adjacent to Nye Road, Sandford, North Somerset (Sandford Substation).
Substation).
connection consists of approximately 600m of underground cable from Sandford 132kV Substation and 2.3km of
132kV overhead line.
section of the existing N Route overhead line.
Routes into Churchill 132/33kV Substation.
G there are two options for the overhead line: a proposed route via Portbury (Option A); and an alternative via Portishead (Option B). The route is approximately 29.6km (Option A) or 30.5km (Option B) in length.
between Portishead 132kV Substation and Avonmouth 132kV Substation.
Substation.
(CSEPP) south west of Nailsea and Portishead 132kV Substation.
its place together with connections to cable sealing end platform pylons.
132kV pylon G31 and installation of approximately 2km of 132kV underground cables in its place together with connections to a cable sealing end platform pylon (CSEPP) and installation of single overhead line span from CSEPP G31R to existing pylon G32.
Seabank Substation and installation of 132kV underground cables in their place together with connections to a CSEPP on the G, DA and BW Routes.
22 Submit application to Planning Inspectorate – early 2014
23