SLIDE 1
Pier 31 Shed Window & Wall Repair Project Contract No. 2806 - - PowerPoint PPT Presentation
Pier 31 Shed Window & Wall Repair Project Contract No. 2806 - - PowerPoint PPT Presentation
Pier 31 Shed Window & Wall Repair Project Contract No. 2806 November 6, 2018 1 AGENDA 1. Welcome, Introductions, & General Information Andre Antonio 2. Project Overview Wendy Proctor 3. CMD Finbarr Jewell 4. OLSE Anna
SLIDE 2
SLIDE 3
AGENDA
- 1. Welcome, Introductions, & General Information – Andre Antonio
- 2. Project Overview – Wendy Proctor
- 3. CMD – Finbarr Jewell
- 4. OLSE– Anna Liu
- 5. OEWD – Joyce Wong
- 6. Environmental – Soko Made
- 7. Bid Documents – Andre Antonio
- 8. Questions
SLIDE 4
, Unit Bid Items
SLIDE 5
SLIDE 6
SLIDE 7
SLIDE 8
Pier 31 AREA OF WORK LOCATION MAP Presented by: Wendy Proctor wendy.proctor@sfport.com
SLIDE 9
Base Bid
- Repair cracks & holes in concrete
shed walls from Col. 16 to end of Pier
- Repair steel windows
- Hazardous abatement
- Paint
Alternate Bids
- Repair cracks & holes in concrete
shed walls from Col. 3 to 16
- Paint interior side of windows
- Replace shed windows with new in lieu
- f repair from Col. 16 to end of shed
SLIDE 10
- Bid Opening
November 15, 2018
- Award of Contract
December 11, 2018
- NTP, Construction Start
February 2019
- Milestone 1
120 Consecutive Calendar Days after NTP
- Milestone 2
180 Consecutive Calendar Days after NTP
- Substantial Completion 1
May 2019
- Substantial Completion 2
July 2019
- Final Completion
September 2019
SLIDE 11
- Project Coordination (Section 01 31 13)
- Pier 31 is an active construction site occupied by other Port Contractors and Tenant
Contractors per Section 01 31 13.
- Perform the work in a manner to minimize the generation of dust and dirt, to prevent dust and
dirt from interfering with the progress of the Work, equipment stored in building, and to keep dust and dirt from accumulating in work areas and adjacent areas.
- Critical Submittals
- Health and Safety Plan per Section 01 35 45.
- Historic Treatment Program per Section 01 35 91.
- Site-Specific Dust Control Plan (DCP) per Section 01 57 19.
- Hazardous Materials Management Plan (HMMP) per Section 02 41 31.
- Handling of asbestos and lead based materials
- Project is a no-discharge site
- All water from pressure washing activities must be collected and properly disposed
SLIDE 12
SLIDE 13
SLIDE 14
SLIDE 15
Replaces Bid Item #2
SLIDE 16
Presented By: Finbarr Jewell finbarr.jewell@sfgov.org
- Local Business Enterprise (LBE)
Subcontracting Goal = 20.0% 11.2% MBE 2.4% WBE 6.4% OBE
- Good Faith Efforts Exception, LBE = 27.0%
- Refer to Section 00 22 11 for details.
SLIDE 17
SLIDE 18
18
SLIDE 19
SLIDE 20
Presented by: Anna Liu anna.liu@sfgov.org
SLIDE 21
SLIDE 22
SLIDE 23
SLIDE 24
Presented by: Joyce Wong joyce.s.wong@sfgov.org
- Required per San Francisco Administrative Code Section 6.22(g) and Chapter 82
- See Section 00 73 30 for details
- Applies to both Prime Contractor and ALL Subcontractors
- Local Hire Requirement 30% by trade
- At least 50% of Apprentice project work hours within each trade shall be
performed by local residents.
SLIDE 25
Presented by: Soko Made rusununguko.made@sfgov.org Construction & Demolition (C&D) Debris Management Requirements
- See Section 01 74 50 for details
- Minimum Diversion Rate of 75% Required
- Source‐separated C&D debris material must be taken to a facility that reuses
and/or recycles that material
- MIXED C&D debris material must be taken to a REGISTERED FACILITY by a
REGISTERED TRANSPORTER
- Diversion Reporting – Use Form C for initial, monthly, and final reports
- Weight Tags are required for monthly reporting
- Contractor MUST include materials from ALL Subcontractors in reports
- City Representative is responsible for reviewing, signing, and approving all
reports submitted by the Contractor.
SLIDE 26
QBD Addendum
SLIDE 27
Ensuing Site Visit at Pier 31
SLIDE 28