Physical Design Challenges in the Chip Power Distribution Network - - PowerPoint PPT Presentation
Physical Design Challenges in the Chip Power Distribution Network - - PowerPoint PPT Presentation
Physical Design Challenges in the Chip Power Distribution Network Farid N. Najm Professor & Chair ECE Dept, University of Toronto f.najm@utoronto.ca Outline Introduction Power grid topology Physical design challenges Power
Outline
■ Introduction
- Power grid topology
- Physical design challenges
■ Power grid verification
- EDA: simulation, vectorless verification
- Engineering solution: over-design, and over-kill
■ Constraints-based verification
- Voltage variations
- Electromigration
■ Constraints generation ■ Conclusion
- F. N. Najm
Challenges in Power Grid 2
Power Grid Topology
■ ~ a Billion nodes ■ ~ 2,000 C4 pads
- 1,000 Vdd, 1,000 Vss
■ All levels of metal stack ■ Hundreds of millions of
instances of logic cells
- F. N. Najm
Challenges in Power Grid 3
RLC RLC RLC RC Layer RC Layer RC Layer
Vdd Pads Circuit current sources Pkg, PCB
Power Grid Topology
■ Package, motherboard, and VRM model; inductance!
- F. N. Najm
Challenges in Power Grid 4
Power-Managed Chip Grid
■ Gated
supplies
■ Voltage
islands
■ Active
devices!
- F. N. Najm
Challenges in Power Grid 5
RLC RLC RLC M7 (RC Layer) M6 (RC Layer) M1 (RC Layer)
Vdd Pads Circuit current sources Pkg, PCB
M5 (RC Layer) M4 (RC Layer) M4 M3 (RC Layer) M3 M2 (RC Layer) M2 M1 Gate FET M1 (RC Layer)
Circuit current sources
M4 (RC Layer) M4 M3 (RC Layer) M3 M2 (RC Layer) M2 M1 Gate FET RLC RLC RLC
Vdd Pads Pkg, PCB
Global (un-gated) Grid Local (gated) Grid
Mesh Layer Structure
■ In every layer, the grid is mostly a regular mesh.
- F. N. Najm
Challenges in Power Grid 6
M e t a l 3 Metal 4
Vdd
Vdd
Vdd
Gnd
Gnd
Gnd
■ Note:
- Many variations on this central theme
- Top layer C4 pads typically on a ~200µm grid
- Local non-uniformities make room for signal routing
Physical Design
■ With hundreds of millions of instances on die and
clocks running at GHz rates, the total power is high
- High performance SOCs might consume over 150 Watts
- Very hard to keep supply regulated under such conditions
■ Physical design of the grid can have big impact:
- Voltage variations in bottom layers impact circuit timing
- Voltage overshoot (inductive kick) impact I/O signal noise
- Electromigration damage can be catastrophic throughout
■ Nightmare: ensure circuit is safe from all this while
distributing over 150 Amps to >400 million instances
- F. N. Najm
Challenges in Power Grid 7
Power Grid Verification
- F. N. Najm
Challenges in Power Grid 8
Power Grid Verification
■ Verification is needed to check the grid design:
- Early high-level grid verification and planning
- Incremental verification during redesign cycles
- Detailed grid verification at sign-off time
■ Key problem:
- The circuit currents are unknown or highly uncertain!
■ Need reliable verification in the face of uncertainty.
- F. N. Najm
Challenges in Power Grid 9
Existing Commercial Solutions
■ Simulation
- Decouple grid from underlying circuit
- Simulate the grid for given current source stimulus
- Expensive and incomplete; inconclusive
■ Existing solutions for vectorless verification
- Voltage variations: timing windows, random scenarios
- Electromigration: Black’s model, current density check
- Questionable results
■ Engineering solution: over-design, but also over-kill ■ Problem: running out of metal area for signal routing!
- F. N. Najm
Challenges in Power Grid 10
Constraints-Based Verification
- F. N. Najm
Challenges in Power Grid 11
Constraints-Based Verification
■ Given:
- Power Grid (DC, RC, or RLC netlist)
- Tolerance for grid node voltage fluctuations (Vth)
- Tolerance for grid branch current densities (EM)
- Peak budgets (current constraints) for block currents
■ Find:
- Worst-case voltage variations for every grid node
- Worst-case current variations in every grid branch
■ Features:
- Based on user-provided current constraints (budgets)
- Search/optimization (LP) approach for verification
- Allows vectorless early high-level power grid verification
- F. N. Najm
Challenges in Power Grid 12
Current Constraints - Example
■ Local Constraints ■ Global Constraints
- F. N. Najm
Challenges in Power Grid 13
1 2 4 5 3 6 9 7 8 +
- I3
I5 I2 I7 I9 Vdd Global Constraint 1 Global Constraint 2
Voltage Drop: The RC Case
■ Define as the vector of worst-case voltage drops, at
all nodes, over all transient currents in space
■ Define: shorthand notation for element-wise max: ■ Use upper-bound:
- F. N. Najm
Challenges in Power Grid 14
emax
i∈F [v(i)] =
max
i∈F [v1(i)]
max
i∈F [v2(i)]
. . . max
i∈F [vn(i)]
Performance
- F. N. Najm
Challenges in Power Grid 15
Voltage Drop/Rise: The RLC Case
- F. N. Najm
Challenges in Power Grid 16
Electromigration: The Mesh Model
■
Traditional EM model is “series”
- But power grid has
much redundancy
■
Vector-based mesh model approach
- 3-4X lifetime!
- Can be 30-40X
■
Vectorless Mesh model approach
- F. N. Najm
Challenges in Power Grid 17 Chatterjee 2013, Fawaz 2013
Progress Towards Failure
- F. N. Najm
Challenges in Power Grid 18
Progress towards failure
- F. N. Najm
Challenges in Power Grid 19
Series ¡
Progress towards failure
- F. N. Najm
Challenges in Power Grid 20
Series ¡
Progress towards failure
- F. N. Najm
Challenges in Power Grid 21
Series ¡
Progress towards failure
- F. N. Najm
Challenges in Power Grid 22
Series ¡
Failure when v(t) > vth
- F. N. Najm
Challenges in Power Grid 23
Series ¡ Mesh ¡
Results: MTF Comparisons
- F. N. Najm
Challenges in Power Grid 24
■ MTF estimation for the largest grid, with 1M nodes
required 97 Monte Carlo iterations and 13.5 hrs.
But … there is a Problem
■ Ongoing development:
- Electromigration verification
◆ Physical models to further reduce pessimism
- Fast hierarchical/modular verification
◆ Boundary conditions to ensure sub-grid safety
■ But there is a fundamental issue with usability of the
constraints-based approach:
- F. N. Najm
Challenges in Power Grid 25
The constraints are hard to specify
Constraints Generation
- F. N. Najm
Challenges in Power Grid 26
Alternative Approach
■ Constraints Generation (the “inverse” problem):
- Generate circuit current constraints which, if satisfied by the
underlying circuitry, would guarantee grid safety
■ Applications:
- Encapsulate much useful information about the grid,
captured in useful quality metrics (peak power, other)
- Provides power budgets to drive design process, allowing
rebudgeting, or early hints for grid redesign or new floorplan
- During low level physical design, allow local checks for block
compliance with grid safety constraints w/o grid simulation
- Local checks in safety “islands” may be enough
- F. N. Najm
Challenges in Power Grid 27
Voltage Islands (RC case)
■ Typically, we find
the constraints decoupled into “islands”
■ Checking of the
local regions, independently
■ Parallel flow for
verification
- F. N. Najm
Challenges in Power Grid 28
Container
■ Definition:
- F. N. Najm
Challenges in Power Grid 29
Safe Container
■ Rewriting the upper-bound on the exact worst-case
voltage drop: where and
■ We want to generate such that , from
which and the grid is safe!
■ Definition: A container is said to be safe if:
- F. N. Najm
Challenges in Power Grid 30
All Safe Containers
■ Let and define the two sets: ■ Lemma: is safe for any , and:
- All possible safe containers may be found as either specific
instances of , or as subsets of such instances.
- F. N. Najm
Challenges in Power Grid 31
Vth
Maximal Container
■ It’s enough to look at the set of all safe containers: ■ Define a safe container to be maximal if it’s not a
subset of any other safe container.
- F. N. Najm
Challenges in Power Grid 32
■ We are interested in
maximal containers!
All Maximal Containers
■ Theorem:
- F. N. Najm
Challenges in Power Grid 33
Maximal Irreducible Safe Vth
Desirable Maximal Containers
■ The space of maximal safe containers represents a
quality assessment for a power grid
- What levels of current will this grid safely distribute?
■ Example: suppose the chip is expected to draw a peak
power of 150W at 1V supply
- A grid may be deemed unacceptable if no safe container for it
can be found that allows a peak total supply current of 150A
■ Design objectives must drive the choice of container!
- F. N. Najm
Challenges in Power Grid 34
Container Generation Algorithms
■ Peak Power Problem (P1):
- Generate a container that
allows the largest possible peak power dissipation (instantaneous, total)
■ Uniform Current Problem (P2):
- Generate a container that does
not severely limit the allowed supply current anywhere on the die
- F. N. Najm
Challenges in Power Grid 35
Algorithms
■ P1: peak power
- One LP
■ P2: uniform budgets
- One LP
- F. N. Najm
Challenges in Power Grid 36
■ We can prove that both resulting are maximal!
Performance (P1)
- F. N. Najm
Challenges in Power Grid 37
(Based on 65nm technology parameters and 1.1 Volt supply)
Grid ¡ Nodes ¡ Sources ¡ CPU ¡Time ¡ Peak ¡Power ¡ (mW) ¡ M' ¡ LP ¡ G1 ¡ 8K ¡ 500 ¡ 2 ¡sec ¡ 0.4 ¡sec ¡ 1.7 ¡ G2 ¡ 19K ¡ 1K ¡ 7 ¡sec ¡ 1 ¡sec ¡ 3.7 ¡ G3 ¡ 33K ¡ 2K ¡ 17 ¡sec ¡ 2 ¡sec ¡ 6.8 ¡ G4 ¡ 50K ¡ 3K ¡ 37 ¡sec ¡ 5 ¡sec ¡ 10 ¡ G5 ¡ 113K ¡ 7K ¡ 3 ¡min ¡ 10 ¡sec ¡ 22 ¡ G6 ¡ 201K ¡ 13K ¡ 9 ¡min ¡ 28 ¡sec ¡ 41 ¡ G7 ¡ 312K ¡ 19K ¡ 22 ¡min ¡ 57 ¡sec ¡ 60 ¡ G8 ¡ 449K ¡ 28K ¡ 44 ¡min ¡ 2 ¡min ¡ 85 ¡ G9 ¡ 1M ¡ 63K ¡ 3.6 ¡hr ¡ 9 ¡min ¡ 198 ¡
Power Density (P1)
- F. N. Najm
Challenges in Power Grid 38
25 50 75 100 125 Number of Windows 0.5 1 1.5 2 2.5 3 3.5 4 4.5
µ = 1.73 mA/cm2 σ = 0.8 mA/cm2
(G4)
Performance (P2)
- F. N. Najm
Challenges in Power Grid 39
Grid ¡ Nodes ¡ Sources ¡ CPU ¡Time ¡ Radius ¡(uA) ¡ M' ¡ LP ¡ G1 ¡ 8K ¡ 500 ¡ 2 ¡sec ¡ 0.7 ¡sec ¡ 1.8 ¡ G2 ¡ 19K ¡ 1K ¡ 7 ¡sec ¡ 2 ¡sec ¡ 2.1 ¡ G3 ¡ 33K ¡ 2K ¡ 17 ¡sec ¡ 3 ¡sec ¡ 1.5 ¡ G4 ¡ 50K ¡ 3K ¡ 37 ¡sec ¡ 6 ¡sec ¡ 1.8 ¡ G5 ¡ 113K ¡ 7K ¡ 3 ¡min ¡ 20 ¡sec ¡ 1.4 ¡ G6 ¡ 201K ¡ 13K ¡ 9 ¡min ¡ 40 ¡sec ¡ 2.1 ¡ G7 ¡ 312K ¡ 19K ¡ 22 ¡min ¡ 1 ¡min ¡ 2.0 ¡ G8 ¡ 449K ¡ 28K ¡ 44 ¡min ¡ 2 ¡min ¡ 1.6 ¡ G9 ¡ 1M ¡ 63K ¡ 3.6 ¡hr ¡ 5 ¡min ¡ 1.9 ¡
Power Density (P2)
- F. N. Najm
Challenges in Power Grid 40
25 50 75 100 125 Number of Windows 0.5 1 1.5 2 2.5 3 3.5 4 4.5
µ = 1.3 mA/cm2 σ = 0.2 mA/cm2
(G4)
Combined Objective (P3)
■ A combined objective gives the best of both worlds: ■ We can prove that the resulting is maximal!
- F. N. Najm
Challenges in Power Grid 41
5 10 15 I1 (mA) 5 10 15 I2 (mA)
Performance (P3)
- F. N. Najm
Challenges in Power Grid 42
Grid ¡ Nodes ¡ Sources ¡ CPU ¡Time ¡ Peak ¡Power ¡(mW) ¡Radius ¡(uA) ¡ M' ¡ LP ¡ G1 ¡ 8K ¡ 500 ¡ 2 ¡sec ¡ 2 ¡sec ¡ 1.7 ¡ 1.7 ¡ G2 ¡ 19K ¡ 1K ¡ 7 ¡sec ¡ 8 ¡sec ¡ 3.4 ¡ 2.0 ¡ G3 ¡ 33K ¡ 2K ¡ 17 ¡sec ¡ 17 ¡sec ¡ 6.4 ¡ 1.4 ¡ G4 ¡ 50K ¡ 3K ¡ 37 ¡sec ¡ 29 ¡sec ¡ 5.6 ¡ 1.8 ¡ G5 ¡ 113K ¡ 7K ¡ 3 ¡min ¡ 2 ¡min ¡ 22 ¡ 1.4 ¡ G6 ¡ 201K ¡ 13K ¡ 9 ¡min ¡ 5 ¡min ¡ 37 ¡ 2.0 ¡ G7 ¡ 312K ¡ 19K ¡ 22 ¡min ¡ 8 ¡min ¡ 55 ¡ 2.0 ¡ G8 ¡ 449K ¡ 28K ¡ 44 ¡min ¡ 15 ¡min ¡ 84 ¡ 1.6 ¡ G9 ¡ 1M ¡ 63K ¡ 3.6 ¡hr ¡ 56 ¡min ¡ 184 ¡ 1.9 ¡
Power Density (P3)
- F. N. Najm
Challenges in Power Grid 43
25 50 75 100 125 Number of Windows 0.5 1 1.5 2 2.5 3 3.5 4 4.5
µ = 1.56 mA/cm2 σ = 0.46 mA/cm2
(G4)
Conclusion
■ Physical design challenges in the power grid relate to
impact on voltage drop/rise and electromigration
- Predicting these effects is hard, due to stimulus uncertainty
- Given budgets (constraints), there are ways to overcome the
uncertainty, but still expensive and under development
■ Constraints generation is possible and practical, and
is a rich area of study, previously unexplored
- Quality metrics for the power grid provide a rigorous
approach for early grid design/planning
- Voltage drop-aware placement and routing?
■ Future work:
- Automatic safe grid generation, along with constraints?
- F. N. Najm
Challenges in Power Grid 44