parker hill branch improvements city of boston
play

Parker Hill Branch Improvements City of Boston Martin J. Walsh, - PowerPoint PPT Presentation

Parker Hill Branch Improvements City of Boston Martin J. Walsh, Mayor Boston Public Library and Public Facility Department June 13, 2017 Meeting Agenda: -Introductions - Recap of May 17 th Meeting - Project Overview - Schedule - Review of


  1. Parker Hill Branch Improvements City of Boston Martin J. Walsh, Mayor Boston Public Library and Public Facility Department June 13, 2017

  2. Meeting Agenda: -Introductions - Recap of May 17 th Meeting - Project Overview - Schedule - Review of services and resources available during closure - Questions

  3. Project Team: Public Facilities Department: Director, Tricia Lyons Brian McLaughlin, Tom Leahy, James Sessum Boston Public Library: President, David Leonard Eamon Shelton, Priscilla Foley, Alison Ford Architect: Bargmann Hendrie + Archetype, Inc.

  4. 1931 Building constructed. 1989 Mission Hill Triangle Historic District added to National Register MHC review required. 2003 Petition to Boston Landmarks Commission for listing as an individual landmark accepted. Petition still ‘Pending’. BLC review required. 2005 Accessibility upgrades (exterior ramp, interior elevator) interior and exterior repairs.

  5. Water damage in main reading room.

  6. Water damage at east wall

  7. Exterior Masonry - open joints and cracks instone.

  8. Patched treads and open joints at frontsteps. Stone veneer not secured at sidewall.

  9. Project Overview - Window Replacement - Interior Painting - Plaster Repair - Masonry Repairs - Stair Repair - Waterproofing

  10. LIMESTONE INTERIOR SURROUND STEEL FRAME EXTERIOR INTERIOR EXISTING STEEL 7 1/2" 1 1/2" HOPPER WINDOW (ORIGINALLY) OPERABLE . HOPPER WINDOW IN MASONRY LEAD OPENING CAMING HOPPER WINDOWS ARE SET IN BACKWARDS RELATIVE TO CASEMENT WINDOWS AT BOTTOM ROWS EXTERIOR (ORIGINALLY) OPERABLE* PLAN DETAIL @ OPERABLE HOPPER WINDOW CASEMENT WINDOW, EXISTING STEEL FULL SCALE FRAME AND SASH . HOPPER WINDOW * ONLY ONEWINDOW IS CURRENTLY OPERABLE LIMESTONE INTERIOR SURROUND STEEL FRAME EXISTING STEEL CASEMENT WINDOW 1 1/2" LEAD CAMING 5" 1 1/4" 1/2" (ORIGINALLY) 1 3/4" OPERABLE . HOPPER CAULK EXTERIOR WINDOW AT Hill_R2015_2_ryoung.rvt BASEMENT ELEVATION OF EXISTING STEEL WINDOWS SECTION THROUGH EXISTING STEEL WINDOWS PLAN DETAIL @ OPERABLE CASEMENT WINDOW 3/8" = 1'-0" 1 1/2" = 1'-0" FULL SCALE

  11. Schedule: - Bid Release: May 2017 - Bid Award: June 2017 - Close branch/pack up collection: July 2017 - Start construction July 2017 - Complete construction May 2018 - BPL move in May – June 2018 - Open to the public – June 2018

  12. Survey Results: -Collection (Books) -Computers/ Printing -Adult Lectures and Programs -Museum Pass Pick up -Homework Help -

  13. Services: - Self Pick up of Holds - Roxbury Community College or closest BPL location - Family Storytime – will be offered weekly - Homework Help - Computer Classes – 1 time per month - Computer Use – Northeastern University – NE Crossing and Tobin Community Center - Book club - Bibliocycle - Museum Passes - Egleston - Community Outreach

  14. Where to Find Service Updates: - Facebook - BPL.org - Libguide - Flyers at the branch - Email distribution list

  15. Community Resources: - All BPL locations - Tobin Community Center - Mission Hill Health Movement - Roxbury Community College - Reggie Lewis Center - Partners Health Shuttle

  16. BPL Branches

  17. Roxbury Community College Library

  18. Partners Healthcare Shuttle

  19. Questions?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.