1
Parker-Davis and Intertie Prepayment Funding Meeting
Dec 03, 2018 Desert Southwest Region
BLM National Training Center 9828 N 31st Avenue, Phoenix AZ 85051
FY2019-2028
Parker-Davis and Intertie Prepayment Funding Meeting FY2019-2028 - - PowerPoint PPT Presentation
Parker-Davis and Intertie Prepayment Funding Meeting FY2019-2028 Dec 03, 2018 Desert Southwest Region BLM National Training Center 9828 N 31 st Avenue, Phoenix AZ 85051 1 Welcome! Today we will hold the Prepayment Vote for this years
1
Dec 03, 2018 Desert Southwest Region
BLM National Training Center 9828 N 31st Avenue, Phoenix AZ 85051
FY2019-2028
2
Desert Southwest Region - 10-Year Plan
3
Desert Southwest Region - 10-Year Plan
4
Desert Southwest Region - 10-Year Plan
5
Desert Southwest Region - 10-Year Plan
6
Desert Southwest Region - 10-Year Plan
7
Desert Southwest Region - 10-Year Plan
8
Desert Southwest Region - Ten Year Capital Plan
Project Description
(including associated site work)
115-kV bays spaced to 230-kV standards
Project Updates
removal from the soil will be funded separately from this project
Project Manager: Mike Garcia
9
Desert Southwest Region - Ten Year Capital Plan
Project Manager: Mike Garcia
10
Desert Southwest Region - Ten Year Capital Plan
concrete foundations, and underground oil piping that were left in place have now been fully removed from the site.
Environmental Quality (ADEQ) on the remedial completion report
public response period has ended.
Project Manager: Roger Wright
11
Desert Southwest Region - Ten Year Capital Plan
Project Manager: Roger Wright
and will continue to seek a land disposal option that maximizes the benefit to the Parker-Davis Project
the GSA process with the Parker Davis Project receiving any resulting revenues
depend upon the purchasing entity and provisions provided to them by GSA
12
Desert Southwest Region - Ten Year Capital Plan
Project Manager: Roger Wright
13
Desert Southwest Region - Ten Year Capital Plan
pole structures and contractor furnished hardware, conductor, and OPGW.
structures #4/7 to #4/9 due to crossing conflicts
Project Manager: Tony Gagajewski
14
Desert Southwest Region - Ten Year Capital Plan
Project Manager: Tony Gagajewski
15
Desert Southwest Region - 10-Year Plan
16
Desert Southwest Region - 10-Year Plan
17
Desert Southwest Region - 10-Year Plan
18
19
Desert Southwest Region - 10-Year Plan
20
Desert Southwest Region - 10-Year Plan
AOA Study Phase: September 2016 Study Financial Revalidated: September 2018 Prepayment Vote: December 2018
21
Desert Southwest Region - 10-Year Plan
Project Justification
corrective action
wood structures
copper conductor experiencing significant sag
require rehabilitation
replacement immediately
is required via fiber optic ground wire to meet current and future protection, control, communication, and security requirements
Checking / Heart Rot Lineman Climbing Safety Concerns
22
Desert Southwest Region - 10-Year Plan
sag, eliminating the majority of the NERC/NESC violations
estimated salvage value of ~$1.7M, which was taken into account in the estimate
light duty steel H-frames
structures
to correct any remaining NERC/NESC clearance issues
23
Desert Southwest Region - 10-Year Plan
and Phase 2
each project will be determined and the individual project phasing budgets will be adjusted accordingly
24
Desert Southwest Region - 10-Year Plan
Seed Funding Phase: September 2018 Prepayment Vote: December 2018
25
Dome Tap
duty steel
336.4-kcmil ACSS
taller structures to rectify NESC/NERC clearance issues
line, one on KOF-DME) support each other. Replacing both at same time would be more efficient and less costly.
Desert Southwest Region - 10-Year Plan
26
Desert Southwest Region - 10-Year Plan
27
Desert Southwest Region - 10-Year Plan
Seed Funding Phase: September 2018 Prepayment Vote: December 2018
28
Desert Southwest Region - 10-Year Plan
29
Desert Southwest Region - 10-Year Plan
30
Desert Southwest Region - 10-Year Plan
Seed Funding Phase: September 2018 Prepayment Vote: December 2018
31
from Coolidge Substation to the Valley Farms Substation, along with possible minor substation work
kind
part of this effort will require steel angles to mount the new insulators
MVA) to Cardinal 954 kcmil ACSR and add OPGW
installed in the same location to avoid environmental and access challenges
modified scope and construction footprint of project
and has been accounted for in the estimate
Desert Southwest Region - 10-Year Plan
Design not Firm
32
Desert Southwest Region - 10-Year Plan
33
Desert Southwest Region - 10-Year Plan
34
Desert Southwest Region - 10-Year Plan
There are two “types” of projects proposed for prepayment funding
reached a 50%-75% design
December
budget formulation
was completed in 2016
accuracy improves and will be shared in detail with the customers
35
Desert Southwest Region - 10-Year Plan
36
Desert Southwest Region - 10-Year Plan
Per the voting procedures in the Memorandum of Understanding:
proposed are voted on as a package. In the event the package is voted down, a subsequent vote will take place on each individual project.
than fifty 50 percent of votes received by the close
by proxy)
37
Desert Southwest Region - 10-Year Plan
38
39
Desert Southwest Region - 10-Year Plan
40
Desert Southwest Region - Ten Year Capital Plan
– Q1 Active Construction Update – Q2 Draft 10-Year Plan – Q3 Formal 10-Year Plan – Q4 Customer Vote – Conclusion of Pivot Year 2 – The dates identified for each Quarterly Customer Meeting will be provided in January
– Performed as required based on events
– Bouse Upgrade Project
– Parker-Blythe #2 Rebuild Project
2019
41
Desert Southwest Region - Ten Year Capital Plan
42
Desert Southwest Region - Ten Year Capital Plan