1
Parker Davis and Intertie Formal 10-Year Plan Meeting
Oct 04, 2018 Desert Southwest Region
BLM National Training Center 9828 N 31st Avenue, Phoenix AZ 85051
FY2019-2028
Parker Davis and Intertie Formal 10-Year Plan Meeting FY2019-2028 - - PowerPoint PPT Presentation
Parker Davis and Intertie Formal 10-Year Plan Meeting FY2019-2028 Oct 04, 2018 Desert Southwest Region BLM National Training Center 9828 N 31 st Avenue, Phoenix AZ 85051 1 WELCOME & INTRODUCTION Desert Southwest Region 10-Year Plan
1
Oct 04, 2018 Desert Southwest Region
BLM National Training Center 9828 N 31st Avenue, Phoenix AZ 85051
FY2019-2028
2
Desert Southwest Region – 10-Year Plan
3
Desert Southwest Region - 10-Year Plan
a) Bouse-Kofa 161kV (Phase I and Phase II) b) FY2018 Seed Project – Gila – Dome T ap c) FY2018 Seed Project – Kofa – Dome T ap d) FY2018 Seed Project – Coolidge-Valley Farms
4
Desert Southwest Region – 10-Year Plan
5
Desert Southwest Region - 10-Year Plan
See Page 7 of Handout Book
6
advance of the current year
schedule, which involved voting on projects for the current fiscal year
Desert Southwest Region - 10-Year Plan
7
Desert Southwest Region - 10-Year Plan
8
Desert Southwest Region - 10-Year Plan
9
Desert Southwest Region - 10-Year Plan
See Page 8 and 9 of Handout Book
10
Desert Southwest Region - 10-Year Plan
Phase
and preliminary environmental/geological assessments
Produce a design package to 50%-75% completion Fund the project through the first year of preconstruction Refine the scope, schedule and estimate from the AOA Study Phase Advance an AOA Study Phase design through preliminary design
11
Desert Southwest Region - 10-Year Plan
12
Desert Southwest Region - 10-Year Plan
13
Desert Southwest Region - 10-Year Plan
14
Desert Southwest Region - 10-Year Plan
15
Desert Southwest Region - 10-Year Plan
AOA Study Phase: September 2018 Seed Funding Phase: October 2018 See Page 11 of Handout Book
16
Desert Southwest Region - 10-Year Plan
concludes in September 2019
2019
Funding Phase for preliminary design
previous 10-Year Plan Meetings
issues encountered on the Parker-Headgate/Parker-Bouse Project (PAD-HDR/PAD-BSE)
handbook on page11
https://www.wapa.gov/regions/DSW/Pages/10-year-capital- program.aspx
17
Desert Southwest Region - 10-Year Plan
See Page 19 of Handout Book
18
Desert Southwest Region - 10-Year Plan
19
Desert Southwest Region - 10-Year Plan
There are two “types” of projects proposed for prepayment funding this December
reached a 50%-75% design
December
formulation
was completed in 2016
accuracy improves and will be shared in detail with the customers
20
Desert Southwest Region - 10-Year Plan
AOA Study Phase: September 2016 Prepayment Vote: December 2018 See Page 19 of Handout Book
21
Desert Southwest Region - 10-Year Plan
Project Overview
upcoming prepayment vote
the Parker-Gila transmission line, which was built in 1943
structures and 211 light duty steel H-frame structures
around the town of Quartzite with 954 ACSR on steel monopoles
22
Desert Southwest Region - 10-Year Plan
Project Justification
corrective action
wood structures
copper conductor experiencing significant sag
require rehabilitation
replacement immediately
is required via fiber optic ground wire to meet current and future protection, control, communication, and security requirements
Checking / Heart Rot Lineman Climbing Safety Concerns
23
Desert Southwest Region - 10-Year Plan
assumption that the project would be pursued as a single construction project
to split the project into 2 separate phases
impacts are moderated
heading north
Substation heading south
24
Desert Southwest Region - 10-Year Plan
the majority of the NERC/NESC violations
value of ~$1.7M, which was taken into account in the estimate
H-frames
remaining NERC/NESC clearance issues
25
Desert Southwest Region - 10-Year Plan
and Phase II
each project will be determined and the individual project phasing budgets will be adjusted accordingly
26
Desert Southwest Region - 10-Year Plan
27
Desert Southwest Region - 10-Year Plan
Seed Funding Phase: September 2018 Prepayment Vote: December 2018 See Page 26 of Handout Book
28
Dome Tap
duty steel
336.4-kcmil ACSS
taller structures to rectify NESC/NERC clearance issues
line, one on KOF-DME) support each other. Replacing both at same time would be more efficient and less costly.
Desert Southwest Region - 10-Year Plan
29
Desert Southwest Region - 10-Year Plan
30
Desert Southwest Region - 10-Year Plan
31
Desert Southwest Region - 10-Year Plan
Seed Funding Phase: September 2018 Prepayment Vote: December 2018 See Page 28 of Handout Book
32
Desert Southwest Region - 10-Year Plan
33
Desert Southwest Region - 10-Year Plan
34
Desert Southwest Region - 10-Year Plan
35
Desert Southwest Region - 10-Year Plan
Seed Funding Phase: September 2018 Prepayment Vote: December 2018 See Page 29 of Handout Book
36
prepayment vote to in September 2017
all structures on the line with light-duty steel, restring with new conductor and install OPGW
WAPA proceeded to seed fund the project to explore a less costly alternative
rated structures on the line like-for-like with wooden structures, restring with new conductor and install OPGW
Desert Southwest Region - 10-Year Plan
37
Coolidge Substation to the Valley Farms Substation, along with possible minor substation work
crossarms to be installed
Cardinal 954 kcmil ACSR and add OPGW
the same location to avoid environmental and access challenges
modified scope and construction footprint of project
has been accounted for in the estimate
Desert Southwest Region - 10-Year Plan
38
Desert Southwest Region - 10-Year Plan
39
Desert Southwest Region - 10-Year Plan
40
Desert Southwest Region - 10-Year Plan
41
Desert Southwest Region - 10-Year Plan
1. Cost in Thousands of Dollars 2. Cost to Date 08/01/2018
See Page 33 of Handout Book
42
Desert Southwest Region - 10-Year Plan
improvements made to the AOA and seed funding
into the estimates
~$9.75M from the Draft Presentation shared July 31
changes
executed as two individual projects
43
Desert Southwest Region - 10-Year Plan
44
Desert Southwest Region - 10-Year Plan
45
Desert Southwest Region - 10-Year Plan
forward looking, meaning they are determined based
investments (assets) as well as projections of future investments
investments were or will be funded
appropriations or alternatively financed
46
Desert Southwest Region – 10-Year Plan
See Page 31 of Handout Book
47
Desert Southwest Region – 10-Year Plan
average of future capital costs
year of costs)
48
Desert Southwest Region – 10-Year Plan
See Page 34 of Handout Book
49
Desert Southwest Region – 10-Year Plan
See Page 35 of Handout Book
50
Desert Southwest Region - 10-Year Plan
51
Desert Southwest Region - 10-Year Plan
52
Desert Southwest Region - 10-Year Plan
53
Desert Southwest Region - 10-Year Plan
Parker-Davis Project Customer Update
October 4, 2018
Desert Southwest Region Phoenix, Arizona
55
Southline Project October 4, 2018
56
Two segments, totaling 370 miles
– New Build — 345-kV double-circuit Afton-Apache, 250 miles – Upgrade — 230-kV double-circuit Apache-Saguaro/Tortolita, 120 miles
Southline Project October 4, 2018
57
1,037 MW
1,000 MW
430 MW
971 MW
environmental impacts *Assumes full project build out in service
Southline Project October 4, 2018
58
Southline Project October 4, 2018
WAPA Upgrade Segment New Build Segment Assets included
Rebuild of existing Apache-Tucson and Tucson-Saguaro 115kV lines to 230kV DCTL Improvements to currently interconnected stations New Build Segment: ~250 miles of 345kV DCTL Upgrade Segment: New interconnection lines (~5 miles) to interconnect additional stations to existing WAPA line
Ownership
WAPA continues ownership Southline owns
Funding
Southline funds Southline funds
Capacity Rights
WAPA retains existing rights WAPA and Southline obtain capacity rights commensurate with contributions WAPA and Southline obtain capacity rights commensurate with contributions
Construction
WAPA constructs Southline or designee constructs
Operation & Maintenance
WAPA continues to operate Expenses shared in proportion to capacity rights Southline or designee operates Expenses shared in proportion to capacity rights
Lands
WAPA manages WAPA Co-manages
Note: Ownership exceptions for new interconnections and facilities within the Upgrade Segment; non
facilities within Upgrade Segment included within “New Build Segment “ above.
commercial support
configurations, operational assumptions, and joint access as necessary
59
Southline Project October 4, 2018
capability as soon as possible. Anchor tenant demand focused on 2021 delivery.
in the desired timeframe at the lowest cost.
timing for the rest of the project, “Phase B,” will be contingent upon Southline sufficiently advancing further commercial interest, which will continue to be developed in parallel with Phase A execution.
60
Southline Project October 4, 2018
*Subject to minor changes prior to construction Phase A generally consists of:
standards; operated at 115-kV out of existing Apache with connections to the existing 115-kV substations.
connections to Vail, SLT-Pantano, and Tortolita.
interconnection.
Upgrades to the existing Afton substation and an interconnection line between these substations.
substation.
61
Southline Project October 4, 2018
*Subject to minor changes prior to construction
62
Southline Project October 4, 2018
*Subject to minor changes prior to construction Phase B generally consists of:
connection into the SLT-Apache substation.
substations to 230-kV.
existing Hidalgo substation and the Southline circuit.
*If needed, potential for decommissioning Nogales and Del Bac substations
63
Southline Project October 4, 2018
*Subject to minor changes prior to construction
64
Southline Project October 4, 2018
Since execution of the Participation Agreement in January 2018, WAPA and Southline have been negotiating the following Key Agreements:
the project.
equipment, structures and hold rights to specified amounts of capacity or capacity rights.
associated to the project and which entity owns, operates, maintains, replaces, and has financial responsibility of the equipment.
between Western, Southline, and any sub-leases to include data security and compliance.
Targeting final drafts ready for execution by Spring 2019
65
Southline Project October 4, 2018
November 2018 – Finalize scope of work per phase March 2019 – Executable contractual drafts Q3 2019 – Phase A Funding Q3-Q4 2019 – Commence Phase A construction 2021 – Initial transfer capabilities 2022 – Complete Phase A construction TBD – Complete Phase B construction
66
Southline Project October 4, 2018
67
Southline Project website www.southlinetransmissionproject.com
Doug Patterson (415) 787-4209 doug@blackforestpartners.com Project Manager Bill Kipp (415) 787-4211 bill@blackforestpartners.com Project Manager Matt Virant (214) 978-8926 mvirant@huntpower.com Project Manager Josh Johnston (602) 605-2662 JJohnston@wapa.com DSW System Planning Mike Simonton (602) 605-2675 Simonton@wapa.gov DSW Power Marketing Matt Schmehl (602) 605-2784 schmehl@wapa.gov WAPA Project Manager Mark Wieringa (720) 962-7448 wieringa@wapa.gov HQ Environment
Southline Project October 4, 2018
68
Southline Project October 4, 2018