PARETO BASED METERING STRATEGIC FRAMEWORK PRESENTER : Wilfred - - PowerPoint PPT Presentation

pareto based metering
SMART_READER_LITE
LIVE PREVIEW

PARETO BASED METERING STRATEGIC FRAMEWORK PRESENTER : Wilfred - - PowerPoint PPT Presentation

TOPIC PARETO BASED METERING STRATEGIC FRAMEWORK PRESENTER : Wilfred Shereni Metering & Revenue Assurance Expert, Zimbabwe PRESENTATION OVERVIEW Objective of Presentation Pareto based Metering Strategic framework Meter To Cash


slide-1
SLIDE 1

TOPIC PARETO BASED METERING STRATEGIC FRAMEWORK

PRESENTER : Wilfred Shereni

Metering & Revenue Assurance Expert, Zimbabwe

slide-2
SLIDE 2

PRESENTATION OVERVIEW

① Objective of Presentation ② Pareto based Metering Strategic framework ③ Meter To Cash (M2C) Value Chain ④ Key Changes to the Meter To Cash (M2C) Value Chain ⑤ Examples of Pareto cases in the M2C value chain ⑥ Steps to follow when using Pareto based metering strategic formulation approach ⑦ Potential Challenges in the Meter to Cash Value Chain ⑧ Problem mapping for the Metering Value Chain ⑨ Keys issues to consider when using Pareto based metering strategy formulation approach

slide-3
SLIDE 3

PRESENTATION OVERVIEW

① Objective of Presentation ② Pareto based Metering Strategic framework ③ Examples of Pareto cases in the M2C value chain ④ Meter To Cash (M2C) Value Chain ⑤ Changes in the Meter To Cash (M2C) Value Chain ⑥ Steps to follow when using Pareto based metering strategic formulation approach ⑦ Potential Challenges in the Meter to Cash Value Chain ⑧ Problem mapping for the Metering Value Chain ⑨ Keys issues to consider when using Pareto based metering strategy formulation approach

slide-4
SLIDE 4

OBJECTIVE OF PRESENTATION

To share information on the Pareto based Metering Strategy formulation approach to enhance efficiency and effectiveness of the “Meter to Cash (M2C) Value Chain”

slide-5
SLIDE 5

PARETO BASED METERING STRATEGIC FORMULATION FRAMEWORK

A “Pareto based Metering Strategic Framework” is an enhanced strategy formulation approach that focuses and prioritizes on key/mission critical issues based on the 80/20 rule. It is a decision-making technique that statistically separates a limited number of input factors as having the greatest impact on an outcome, either desirable

  • r undesirable.
slide-6
SLIDE 6

PARETO BASED METERING STRATEGIC FORMULATION FRAMEWORK

NOTE, the figures 80 and 20 are illustrative – the Pareto Principle illustrates the lack of symmetry that

  • ften appears between work put in and results
  • achieved. For example, 13 percent of work could

generate 87 percent of returns. Or 70 percent of problems could be resolved by dealing with 30 percent of the causes.

slide-7
SLIDE 7

EXAMPLES OF PARETO CASES IN THE METER TO CASH VALUE CHAIN

10% of customers contribute 90% of revenue 20% of customers account for 80% of Non Technical Losses(NTL) Metering faults constitutes 20% of utility faults but account for 80% of revenue loss 10% of customers owing account for 90% of debt 10% of the technical specification cover 90% of meter requirements 10% of processes in a project impact on 90% of the

  • utcome
slide-8
SLIDE 8

METER TO CASH (M2C) VALUE CHAIN The Meter to Cash (M2C) value chain includes Metering, Billing & Collection functions which traditionally were handled separately but because of technological advancements are now merging

slide-9
SLIDE 9

CHANGES IN THE METER TO CASH (M2C) VALUE CHAIN

Traditionally Metering, Billing & Collection were distinct processes but are now merging into one end to end process

METERING, BILLING & COLLECTION (MBC)

METERING

BILLING COLLECTION

TRADITIONAL APPROACH CURRENT APPROACH

slide-10
SLIDE 10

STEPS TO FOLLOW WHEN USING THE PARETO BASED STRATEGY FORMULATION APPROACH

Identify & List problems for each phase

  • f the M2C

Value Chain Group Problems together by Root Cause Add up the scores for each group & Rank Take Action Score Problems All Root Causes for Each M2C Phase Identified Root Causes No Yes

slide-11
SLIDE 11

POTENTIAL CHALLENGES IN THE METER TO CASH VALUE CHAIN

For any metering program, there will be challenges that arise in: Planning/Design, Equipment Specification, Purchasing, Installation & Maintenance and replacement Using Pareto Based Metering Strategic framework will assist focus on key issues, avoid pitfalls and optimise on resource usage The next slide shows problems that exist in the Meter to Cash value chain of a typical Sub Saharan African Utility referenced to best practice

slide-12
SLIDE 12

PROBLEM MAPPING FOR THE METERING VALUE CHAIN FOR A TYPICAL SSA UTILITY

Note: Problematic phases are highlighted in red

Planning/ Business Case FAT (End to End Testing) Technical Specification Drafting/Review Acceptance Testing on Delivery Meter Installation Design Fault Maintenance & Performance Monitoring Replacement at End of Guaranteed life span Meter Installation & Commissioning 15% 11% 12% 11% 13% 8% 5% 5% 12% 15% 10% 20% 10% 10% 5% 5% 18%

SPUs MPUs

15% 20% 11% 11%

LPUs

12% 13% 8% 5% 5% 20% Tender Process

Note: SPUs – Small Power Users, MPUs – Medium Power Users, LPUs – Large Power Users

slide-13
SLIDE 13

PROBLEM MAPPING USING PIE CHART – MPUS & LPUS

Planning/Business Case Technical Spec Tendering FAT Acceptance Testing Meter Installation Design Meter Installation & Comissioning Fault Maintenance & Performance Monitoring Replacement @ End of Lifesapn

20% 11% 8% 11% 5% 13% 12% 11% 15%

slide-14
SLIDE 14

TECHNICAL SPECIFICATION

PURCHASING

METER INSTALLATION

METER O&M

  • Gorvenance
  • Budget
  • Technology

selection

  • Resource

Allocation

  • Feasibility

Analysis

  • Risks

Analysis

  • Project

Financing

  • Implementati
  • n timeframe

& Road map

  • Business

requirements

  • Functionality

required

  • BI Required
  • Standards
  • Statutory/Le

gal requirements

  • Feedback

from meter performance analysis

  • Technical

due diligence

  • Customer

numbers

  • Maturity of

Technology

  • Project

financing

  • Tender

Evaluation & Award

  • FAT issues
  • Acceptance

testing

  • Warranty &

Guarantee issues

  • After sales

support

  • Complexity of

Installations

  • In-house or
  • utsource
  • Skills

required

  • Project scope
  • Installation

processes & procedures

  • Level of NTL
  • Post

implementati

  • n support

model

  • Skills

required

  • Reliability/A

vailability

  • Cost of

Support

  • Customer

queries

  • Tools &

Equipment

  • Resources –

vehicle, manpower

REPLAEMENT @ END OF LIFESPAN

  • Replaceme

nt programme @ end of life span

  • Meter

failure statistics

  • Budget
  • Accuracy

required

  • Big Data

Analytics

PLANNING /DESIGN

KEY ISSUES TO CONSIDER WHEN FORMULATING A PARETO BASED METERING STRATEGY

slide-15
SLIDE 15

END THANK YOU

Cell Number: +263 774668303 Email: shereniw@gmail.com