overview of dpu order on three year plan for 2016 2018
play

OVERVIEW OF DPU ORDER ON THREE-YEAR PLAN FOR 2016-2018 February - PowerPoint PPT Presentation

OVERVIEW OF DPU ORDER ON THREE-YEAR PLAN FOR 2016-2018 February 17, 2016 APPROVAL OF SAVINGS LEVELS AND BUDGETS With minor adjustments, final savings approved: 2.94% of sales in electric compared to 2.93% in the plan 1.24% of


  1. OVERVIEW OF DPU ORDER ON THREE-YEAR PLAN FOR 2016-2018 ► February 17, 2016

  2. APPROVAL OF SAVINGS LEVELS AND BUDGETS ► With minor adjustments, final savings approved: − 2.94% of sales in electric compared to 2.93% in the plan − 1.24% of sales in gas ► Overall budget approved − DPU will review budget items for sponsorships and administrative costs in final Three-Year Term Report www.ma-eeac.org Overview of DPU 3YP Order | 2

  3. ITEMS MOVED TO OTHER DOCKETS ► Did not rule on Mass Save Data as statewide database − Will be covered in 14-141 ► DPU has decided that it will conduct annual EES adjustment and reconciliation (pp.112-116 Order) ► EES returns to annual calculation rather than 3-year ► Changes to the Mid Term Modification thresholds will be discussed in a subsequent proceeding − Thresholds under consideration – 2% bill impact and 20% sector budget +/- − Not a statutory consideration − Will be part of DPU procedure to update EE Guidelines www.ma-eeac.org Overview of DPU 3YP Order | 3

  4. KEY DECISIONS ► Performance Incentive will not be split by sector ► PAs approved to evaluate DR programs − No targets set − CLC and Grid budgets approved except EV charging − Non-wires EE approved for Nantucket − Any demand offerings will have detailed plans − March 31 th report to DPU ► DOER and PAs will work together to develop appropriate C&I measure level data ► PAs need to review administrative costs − Keep current cost categories for comparison − Review best practice from around the country − Submit review report before next 3YP www.ma-eeac.org Overview of DPU 3YP Order | 4

  5. ITEMS TO BE TRACKED FOR EEAC ► Cost-effectiveness determined at the core initiative rather than program level in 2016-2018 Three-Year Plan ► DPU directs each PA to conduct a service territory- specific energy efficiency potential study − Must be completed before next planning period − Consultants believe this should be directed through the EM&V process, which it was not last time − Lack of coordination resulted in disputed results of previous potential studies and limited coverage of program penetration ► Approval of weatherization of multi-family oil buildings www.ma-eeac.org Overview of DPU 3YP Order | 5

  6. QUESTIONS? Thank You ► February 17, 2016

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.