origins of the project building condition survey plan for
play

Origins of the project building condition survey Plan for funding - PowerPoint PPT Presentation

Address elements of the project over next several Board of Education workshops Origins of the project building condition survey Plan for funding and timing of the project Nov 1st Dec 6th High school and middle school maintenance


  1. Address elements of the project over next several Board of Education workshops • Origins of the project ‐ building condition survey • Plan for funding and timing of the project Nov 1st Dec 6th • High school and middle school maintenance issues* Jan 3rd • All elementary buildings maintenance issues* • Athletic fields, FEC, and transportation maintenance issues* Feb 7 th • Review entire proposition to go to the March 21st business meeting Mar 7 th *Actual pictures will be used to highlight specific concerns

  2. Big Tree Elementary

  3. Proposed Project by Building BIG TREE ELEMENTARY 1079 Roof replacement $ 2,009,500 1009 Replace catch basins $ 40,000 Gym wall pad replacement $ 16,900 1133 BIG TREE ELEMENTARY TOTAL $ 2,066,400

  4. Big Tree Roof replacement (roof flashing) – record #1079

  5. Big Tree Roof replacement – record #1079 Roof expansion joint

  6. Big Tree Catch basin replacement – record #1009

  7. Blasdell Elementary

  8. Proposed Project by Building BLASDELL ELEMENTARY 2132 Air handling unit replacement $ 105,000 Ceramic wall tile removals $ 307,800 2169 Auditorium renovations $ 113,960 2018 Sidewalk replacements $ 17,010 2009 Replace catch basins $ 13,200 Gym wall pad replacement $ 20,150 2157 BLASDELL ELEMENTARY TOTAL $ 577,120

  9. Blasdell Auditorium Air Handling Unit - record #2132

  10. Blasdell Cafeteria Air Handling Unit – record #2132

  11. Gym Air Handling Unit – record #2132 Blasdell

  12. Auditorium Seating- record #2169 Blasdell

  13. Blasdell Auditorium A.D.A. Seating- record #2169

  14. Sidewalks - record #2018 Blasdell

  15. Catch Basin - record #2009 Blasdell

  16. Cloverbank Elementary

  17. Proposed Project by Building CLOVERBANK ELEMENTARY 4131 Air handling unit replacement $ 105,000 Ceramic wall tile removals $ 248,800 4175 Auditorium renovations $ 113,960 4016 Parking lot replacements $ 825,000 4018 Sidewalk replacements $ 231,000 Replace catch basins $ 10,500 4009 CLOVERBANK ELEMENTARY TOTAL $ 1,534,260

  18. Cloverbank Auditorium Air Handling Unit – record #4131

  19. Cloverbank Gym Air Handling Unit – record #4131

  20. Cloverbank Cafeteria Air Handling Unit - record #4131

  21. Auditorium Seating – record #4175 Cloverbank

  22. Parking lot – record #4016 Cloverbank

  23. Sidewalks – record #4018 Cloverbank

  24. Catch Basins– record #4009 Cloverbank

  25. Pinehurst Elementary

  26. Proposed Project by Building PINEHURST ELEMENTARY 8151 Emergency generator $ 86,000 8146 Update pneumatic controls $ 300,000 8171 Auditorium renovations $ 96,089 8172 Stage curtain and rigging replacements $ 25,000 8173 Theatrical lighting replacements $ 75,000 8009 Replace catch basins $ 3,000 PINEHURST ELEMENTARY TOTAL $ 585,089

  27. Pneumatics - record #8146 Pinehurst

  28. D.D.C. Controls - record #8146 Pinehurst

  29. Auditorium Seating - record #8171 Pinehurst

  30. Pinehurst Auditorium A.D.A. Seating - record #8171

  31. Theatrical Lighting - record #8173 Pinehurst

  32. Theatrical Lighting - record #8173 Pinehurst

  33. Pinehurst Theatrical Lighting Board - record #8173

  34. Catch Basin - record #8009 Pinehurst

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend