2018 PROPOSED CAPITAL PROJECT September 27, 2017 Pro j ect - PowerPoint PPT Presentation

DeRuyter CSD 2018 PROPOSED CAPITAL PROJECT September 27, 2017 Pro j ect Element s BUILDING CONDITION SURVEY ITEMS: MAIN BUILDING SITEWORK Masonry pointing. Repave the Elementary parking lot. Reroof 3 rd and 5 th grade and gym


  1. DeRuyter CSD 2018 PROPOSED CAPITAL PROJECT September 27, 2017

  2. Pro j ect Element s BUILDING CONDITION SURVEY ITEMS: MAIN BUILDING SITEWORK • Masonry pointing. • Repave the Elementary parking lot. • Reroof 3 rd and 5 th grade and gym roof. • Sidewalk replacement. • Loading dock reconstruction. • Provide additional parking. • Paint cornice. • Terrazzo replacement (stair treads). ANNEX / BUS GARAGE • Locker replacement. • Upgrade / replace Bus Garage lighting side-wall mounting. • Upgrade food service equipment. • Bus lift replacement. • Plumbing fixture replacement. • Ventilation upgrades. • Lighting upgrades / replacement exit lights. • Hot water system upgrades. • Remove abandoned boilers. September 27, 2017

  3. Pro g ra m Element s & Obj ect ives • Enhance security & safety • Auditorium addition • Maintain & upgrade facilities • All weather track • Athletic field improvements • Upgraded shared fuel facilities September 27, 2017

  4. Pro po sed Sit e Pla n September 27, 2017

  5. Pro po sed Audit o rium Pla n September 27, 2017

  6. Pro po sed A udit o rium M a ssing September 27, 2017

  7. Po t ent ia l Pro j ect C o st BCS items $ 2,150,000 Athletic field improvements $ 2,400,000 Auditorium addition $ 4,400,000 *Possible referendum total $ 8,950,000 * The above cost includes 10% for contingency & escalation and 20% for incidental “soft” costs as defined by SED September 27, 2017

  8. Po ssible Pro j ect Schedule TASK DATE / DURATION September 27, 2017 – November 1, 2017 Seek staff & public input SEQRA review period, 30 days December 1, 2017 - January 3, 2018 September 27, 2017 – January 3 2018 Finalize scope & budget B.O.E. Address SEQRA & finalize budget January 10, 2018 January 15, 2018 – February 28, 2018 Advertisement period, 45 days Vote date February 28, 2018 March 2018 – September 2018 Design phase September 2018 – March 2019 SED review period April 2019 – August 2020 Construction September 2020 – October 2020 Post construction September 27, 2017

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.