SEAFCO PUBLIC COMPANY LIMITED
Oppo portun tunity ty Day y
4th
th June
Oppo portun tunity ty Day y th June 4 th e 2015 SEAFCO s bored - - PowerPoint PPT Presentation
SEAFCO PUBLIC COMPANY LIMITED Oppo portun tunity ty Day y th June 4 th e 2015 SEAFCO s bored piles and diaphragm walls: Foundation of modernization of Bangkok AGENDA BUSINESS OVERVIEW INDUSTRY OVERVIEW FINANCIAL HILIGHT MAIN
th June
BASEMENT SUPERSTRUCTURE DIAPHRAGM WALL BARRETTE BORED PILE
Ground Level
Barrettes supporting Purple Line MRT pier Bored piles supporting BTS pier
SCB Park Project Contiguous pile wall Southern Outer Ring Road Project Typical pile head condition
Barrette construction T-Shape barrette Barrette construction under limited height X-Shape barrette
Diaphragm Wall
Diaphragm wall construction Diaphragm wall for shaft Diaphragm wall for basement
Underground Car Park at Srinakarinwiroj University Project Central Hospital Project Terminal 21Project
Lamkonmuang Project 72nd Anniversary Stadium Project Kuekarun Nursing College Project
Road Construction, Prayasuren Road
Onnut-Prawet Flyover Project Phatthanakarn Road U-turn Project Srinakarin Underpass Project Prayasuren Road Project
Cement column Deep Mixing Method
Typical section of soil-cement column Eastern Outer Ring Road Project
Darland Pranburi Project Central Chaeng Wattana Project Prinsiri Pattaya Project Soil improvement for sea wall
Trench/ borehole monitoring Inclinometer reading Borehole monitoring results Sonic integrity testing
Instrument installation in bored pile Loading system and settlement reading Pile load testing
SEAFCO PLC
Project Completed and in a process of warrantee period Project Completed and in a process of warrantee period
Seafco (Myanmar) Co.,Ltd. 90% Srinakarindhra JV 30% Seafco Construction Co.,Ltd. 50% Seafco Intertrade Co.,Ltd. 99.99% Seafco and Prayunchai (1984) JV 45%
Project Completed and in a process of warrantee period
NO. PRODUCT Income as of Q1-2013 Q1-2014 Q1-2015 Unit : MB % Unit : MB % Unit : MB %
1 BORED PILE, BARRETTE AND DIAPHRAGM WALL 279.50 87 289.46 90 460.71 96 1.1
Bored Pile, Barrette and Diaphragm Wall (Labor Only)
204.63 64 272.66 85 118.59 25 1.2
Bored Pile, Barrette and Diaphragm Wall (Labor and materials)
74.87 23 16.80 5 342.12 71 2 BUILDING AND CIVIL WORKS 40.25 13 17.05 5 3.31 1 3 OVERSEAS 14.63 5 16.72 3 TOTAL 319.75 100 321.14 100 480.74 100
1.Government Sector 24%
Sector 73%
3%
Direct Contract from Client Subcontract From Main Contractor
Source of Backlog
10% 20% 70%
Awarded Awarded to other players Under review by project owner 6 Projects, Awarded 12 Projects, Awarded to
42 Projects, Underreview by project owner Total 60 Projects
Tender project ratio Project value ratio
450 675 2,328
Awarded Awarded to other players Under review by project owner Unit : Million Baht(MB) Total value 3,453 MB
Icon Siam Project Rama 9 Square Project
Example of SEAFCO’s paper published in International Conference Proceedings
Marina Bay Sands, Singapore Kabar Aye Executive Residence, Yangon
Unit : MB
CORE BUSINESS INCOME (SEAFCO ONLY) CORE BUSINESS INCOME (CONSOLIDATED)
320 321 481 100 200 300 400 500 600 Q1 MB
320 321 465 100 200 300 400 500 Q1 MB
Core Business income (Seafco Only)
CORE BUSINESS INCOME (SEAFCO ONLY) CORE BUSINESS INCOME (CONSOLIDATED)
CORE BUSINESS INCOME (SEAFCO ONLY) CORE BUSINESS INCOME (CONSOLIDATED)
GROSS PROFIT (SEAFCO ONLY) GROSS PROFIT (CONSOLIDATED)
GROSS PROFIT (SEAFCO ONLY) GROSS PROFIT (CONSOLIDATED)
NET PROFIT (SEAFCO ONLY) NET PROFIT (CONSOLIDATED)
NET PROFIT (SEAFCO ONLY) NET PROFIT (CONSOLIDATED)
ADMINISTRATIVE EXPENSES (SEAFCO ONLY) ADMINISTRATIVE EXPENSES (CONSOLIDATED)
ADMINISTRATIVE EXPENSES (SEAFCO ONLY) ADMINISTRATIVE EXPENSES (CONSOLIDATED)
BALANCE SHEET (SEAFCO ONLY) BALANCE SHEET (CONSOLIDATED)
NET PROFIT
DIVIDEND