Op Oppo portuni tunity ty Da Day
25 March 2019 Construction A to Z
1
Op Oppo portuni tunity ty Da Day 25 March 2019 FY FY20 2018 - - PowerPoint PPT Presentation
Op Oppo portuni tunity ty Da Day 25 March 2019 FY FY20 2018 18 Construction A to Z 1 About Construction A to Z Introduction Scope of Services CAZ Strategy Financial Performance Outlook 2 About Construction A to Z Introduction
25 March 2019 Construction A to Z
1
Introduction
About
Construction A to Z Financial Performance Scope of Services CAZ Strategy
2
Outlook
Introduction
About
Construction A to Z Financial Performance Scope of Services CAZ Strategy
3
Outlook
Structure & Management
CAZ (Thail ailand) nd) PLC
EPC service for customer in energy business
JKEC C Co., Ltd. .
Civil Construction service
Taku kuni ni (Thailand) and) Co., Ltd.
LPG system construction
36.6% 27.3% 38.1%
73.2%
4
St Strategi gic c Sharehold eholders s (Manageme nagement) nt)
Company Structure
Mino nor r Shareho ehold lders (CAZ staffs s 8%)
Introduction
Background and Vision
Vision
A most competitive construction contractor who creates sustainable prosperity in Thailand.
Mission
fabricator.
market.
Proje
cts
As of February 2014, CAZ has established from executives and managerial staffs who has extensive experiences and has completed numerous project as a well recognized EPC contractor in Oil & Gas, Petrochemical, Chemical, Energy, Power plants segments. CAZ‘s major business range is Construction Total Service & Management System (Procurement, Construction, and Shop Fabrication) to provide clients with the best possible service in all phases of project from A to Z including Civil & Architectural, Structural, Tank & Vessel, and Heaters Fabrication work, Piping & Mechanical erection, Electrical, Instrument work regardless of project amount.
15 40
5
2,516
As of 28 February 2019
Finished On-going Backlog
Introduction
Milestone
2014
Es Establi blish shed d in Febru ebruar ary
Control System program to improve project cost management
2015
Stron
g Par Partne nersh ship
listed company in MAI stock market
ASAHI SAR
System & Spool Tracking Management System to improve our quality
2016
New w office ice and d Worksh kshop
MB
Co., Ltd as subsidiary
Land and Factory
Spherical Tank project, PTT Tank’s Propylene tank, 332 MB as EPC
2018
Solid id Growth wth
Project, 643 MB as EPC project
for Pressure Vessel, Tank Fabrication
2017
Sus ustai ainabi nability lity
JKEC to be 73% of total shares
MB
Enclosure Ground Flare Project, 272 MB as EPC project
SMP Project 1,570 MB and PTT GC PO Civil Project 451 MB
6
2019
IPO O & & First st Trading ding
the public for the first time at a price
mai on Jan 22nd , 19
Quality Standards and Certificates
7
Safe Man Hours on PTTGC Aromatics Debottlenecking Project Safe Man Hours on TOP SPP Project
ASME Certificate of Authorization
ISO 9001:2015 Certificate
Introduction
Introduction
About
Construction A to Z Financial Performance Scope of Services CAZ Strategy
8
Outlook
Scope of Services
Business Unit
EP EPC
Engineer neering ing Pro rocureme rement nt Cons nstruc truction tion
SMP P & E& & E&I Civ ivil il Other ers
St Steel Str Structu ture re Mechanical nical Piping ing Electrical rical & & Instru rument ment
Cylindrical Tank (CRT, DRT, FRT) Spherical Tank
Civil vil and nd Bu Building ding Sho hop Fabri rication ation Tank nk Fabri rication ation Pressur ssure e Vessel sel Fabricat atio ion
E P C
En Enginee ineeri ring ng Pro rocure curemen ent
Exec ecuti ution
Const stru ruct ction ion
Scope of Services
EPC Work
PTT Tank Terminal
4,000 Tons Spherical Tank, Transfer Pump, Ground Flare & Etc.
Contract Amount : 345 MB December 2016 – October 2018
BCP EGF
Enclosed Ground Flare
Contract Amount : 272 MB April 2018 – June 2019
EPC Eng ngin inee eerin ing Procureme rocurement nt Cons nstruction truction
40.7%
PTT LNG Cold Water
NG Vaporizer, NG Heater, Tanks, Pumps & etc.
Contract Amount : 733 MB July 2017– July 2018
Scope of Services
SMP / E&I
PTT Midline Compressor Station
800 tons for Equip, Compressor 4 sets
Contract Amount : 508 MB April 2016 – April 2017
PTT LPG Terminal Khao Bo Ya PJT E&I Work
E&I : 310,000 M
Contract Amount : 200 MB September 2014 – January 2016
PTT LNG Receiving Terminal Expansion
Process Structure. Equip. Foundation, Pipe Rack Pre-casting
Contract Amount : 382 MB November 2014 – March 2016
St Stee eel l St Structure ructure Mechanica ical Piping ping Elect ectrical ical & Ins nstrum ument nt
e Tray & C Condui uit, t, Cabling, ng, Electr tric Equipm pment nt Instal
/MCC CC
tform m & La Ladde der
er
pment Erection n fo for C Compr press essor, , Pump mp, Column mn, Vessel, sel, et etc.
rication n & F Field d Erecti tion
for Gener eral al, , Dissimilar milar, special al
Exec ecuti ution
pment St Structur cture
24.8%
trum ument nt Calibr brat ation
ction Test
SMP P / E&I
Scope of Services
Civil & Arch. Work
IRPC PPE
Civil and Electric Work
Contract Amount : 83 MB February 2016 – December 2016
Samsung TSE ATV
Civil and Structure Work
Contract Amount : 113 MB February 2016 – April 2016
PTT PO Civil
Civil Work & quip. Foundation
Contract Amount : 452 MB January 2018 – January 2020
Civil vil & & Build ilding ing. Civil vil
Pililing ng (Bored d / Drive iven n / N Non-Pollution tion Pil ile)
Tanknk Foundat dation
ncrete Type)
Pre-Casasting ng Concrete Pip ipe Rack
Centralal Control Buil ilding
Compressssor Buil ilding ng
Build ilding ing Exec ecuti ution
Equipmepment nt Foundat dation
nk Foundat dation
Earth h Type)
Concrete Firire Proofin ing
Pellelletizi zing ng Buil ilding ng
Sub-Statation
ilding
24.7%
Scope of Services
Shop Fabrication Capability
Vessel/Heat Exchanger/SKID Tank Stack/Fired Heater
Shop p Fabricat rication ion
Structure Fabrication Production Capability : 1,500 Tons / Month Pipe rack, Equipment & Shelter Structure Work Furnace & Heater Fabrication Work Platform & Ladder Fabrication Work Flare Stack Fabrication Work
Tank nk Fabrica icati tion
Tank Fabrication FRT Tank DRT / CRT Tank Spherical Tank Vessel Fabrication Thickness : Max. 75 m/m Handling Weight : Max. 120 Ton/unit Handling Length : Max. 50 m Max Capability : 200 Tons / Month (Pressure Vessel)
Pressu ssure re Vessel sel Fabri ricatio ation
9.9%
Office and Fabrication shops
Scope of Services
14
CAZ
Maptaphud U-Tapao Laem m Chabang ng 10 KM
Introduction
About
Construction A to Z Financial Performance Scope of Services CAZ Strategy
15
Outlook
Cost t Control
CAZ Strategy
Operation Strategy
Quality of service – No subcontract Tight control of budget by Risk Management Gate and set procurement policy Develop IT System and maximize automation for shop fabrication to increase productivities Participate the bidding with partner and/or Main Contractor Award project as Main Contractor Expand new client and projects
Main Contractor
40.2
59.8 Subcontractor
Customer
Rel elat ation ionship ship
CAZ Strategy
Risk Management Gate
Bidding ing Price Decis ision ion Altern ernati ative Propos
al Cost Estimati tion
Risk Analy alysis is
ject Close
ject Exec ecution tion
ject Prepar aratio ation
tract Negotia iatio ion
Final al Decision ision for Bidding ing Eva valuat luation ion for Bidding ing or not
Projec ect Inform
ation
ject Biddin dding Decisio ision
Site Survey
sal Developm lopment
Review of Contrac ract t Doc. Result t of Negoti tiati ation
Preparat aration ion of Negoti tiati ation
Analy alysis is For Bidding ding Result Early ly Start Projec ect ITC Projec ect Executio ution n Plan Internal rnal Kick-of
Meeti ting ng Projec ect t Launch nch Meeti ting ng ITC of Changed ged Plan Early ly Construct ruction ion Exclus lusiv ive Contrac ract Reque uest Urgen gent Money Ove verr rrun un Report Monthly hly Pe Perfor
ance e Review Report t of Projec ect t Comple letion ion Review Contrac ract t Condit ition ion Internal rnal Kick-of
Meeti ting ng 17
6 Steps
IT Man anag agem emen ent System em
System is based on Bar-Code & GPS System
St Structure ucture Producti
Control
Syst stem em (SPCM (SPCM) and nd Spoo Spool Tracki acking ng Man anageme agement nt Sy Syst stem(S em(STM TMS) S)
STMS 3D Map STMS Google Map Tracking by PDA with GPS PDA 18
Log-In Screen Daily Welding Inspection Report Shop & Field Welding Progress Report Spool Fabrication Status Report List
Welding ing Contr trol
em (CWCS) - System is based on Web Version
IT Manage gemen ent System em
Test Package Report Status for Welder Efficiency NDE Request Report RT Shooting Status Report
19
Tools, s, Asset & Consu nsuma mable Management agement System em (TCM CMS) S)
Base on Bar-Code System
IT Management System m
20
Introduction
About
Construction A to Z Financial Performance Scope of Services CAZ Strategy
21
Outlook
Financial Performance
Overall Highlight
22
272 742 651 1,019
2017 2016 2015 2014 2018
1,387
Revenue enue
(Million Baht)
2015 2016 2017
Pro rofit fitabilit bility
(Percentage)
2018 11.1 8.3 53.0 22.9 2015 2016 2017 2018 10.11 11.55 9.98 10.52 1.12 1.69 2.24 3.81
Gross Profit Net Profit Net et Pro rofit fit
(Million Baht)
Financial Performance
Revenue Breakdown
23
53.0% 61.4% 35.3% 24.8% 37.1% 25.4% 8.5% 24.6% 54.0% 40.7% 9.9% 13.1% 2.2% 9.9%
200 400 600 800 1,000 1,200 1,400 1,600 2015 2016 2017 2018
SMP and E&I Service Civil & Building Service EPC Service Fabrication and Other Service
1,019 MB 651 MB 742 MB 1,387 MB
Assets ts
Financial Position
19.41% 1% Cash 13% Account Receivable 23% Unbilled Income PPE 43% 9% 9% 12% 12% Account Receivable 18% Unbilled Income 24%
PPE 32%
Inventory 12% Other assets 14%
729.1 1 MB (Dec’17) 1, 1,149 49.8 .8 MB (Dec’18)
period.
Baht
period.
Liab abili ilities ties and d Equity ity
729.1 1 MB (Dec’17)
Account Payable 24% Unearned Income 23% Bank Loan 30% Equity 19%
1, 1,149 49.8 .8 MB (Dec’18)
Account Payable 25% Unearned Income 37%
Bank Loan 21%
Equity 14% 24
Financial Performance
Leverage erage Ratio io
2.59 4.73 4.15 6.11 0.64 3.48 1.58 1.52
4.00 6.00 8.00 FY2 FY2015 FY2 FY2016 FY2 FY2017 FY2 FY2018
Debt to Equity Interest Bearing Debt
Efficiency iciency Ratio tio
14.6 .63 12.9 .94 19.7 .78 35.8 .88 7.38 6.94 7.11 8.80
10.00 15.00 20.00 25.00 30.00 35.00 40.00 FY2 FY2015 FY2 FY2016 FY2 FY2017 FY2 FY2018
Return on Equity Return on Asset
Financial Performance
Financial Ratio
25 * After IPO, Interest bearing debt to equity will reduce to be 0.60
Introduction
About
Construction A to Z Financial Performance Scope of Services CAZ Strategy
26
Outlook
Business Outlook
Eastern Economic Corridor Development
27
Source: Ministry of Industry’s presentation of “Eastern Economic Corridor Development Project” Driving Forward, 15 February 2017
Combined Public and Private Investments at least
1.5 Trillion baht ($43Billion USD) in the first 5 years
U-Tapao international airport New Cities / Hospitals
200,000 mil baht ($5.7 Bill USD) 400,000 mil baht ($11.5 Bill USD)
Tourism
200,000 mil baht ($5.7 Bill USD)
Industry
500,000 mil baht ($14 Bill USD)
Motorway
350,300 mil baht ($1 Bill USD)
Dual-track railway
640,300 mil baht ($1.8 Bill USD)
High-speed train
158,000 mil baht ($4.5 Bill USD)
Laem Chabang port
88,000 mil baht ($2.5 Bill USD)
Map Ta Phut port
10,150 mil baht ($0.3 Bill USD)
Target
Note : Estimated investment amount shown
* As PTT Group
up (PTT LNG, Thai Oil, , PTT GC, IRPC) invest ested ed for MEGA Project, ct, Down Stre ream m project ct also shall ll be c conti tinuous nuously ly invest sted d (HM HMC PP, B BST, Dow Chemica cal & et etc)
PTT TTGC C – Awar
ward d 2,021 1 M. Baht t fro rom 53,600 00 M. Baht t (3.8%)
2018 Propylene Oxide Project (11,200 M.Baht) 2018 Polyols Project (20,000 M.Baht) 2018 Olefins Reconfiguration Project (22,400 M.Baht)
IRPC
2019 Paraxylene Plant Project (30,000 M.Baht) 2019 Olefins Expansion Project (20,000 M.Baht)
Business Outlook
Customer Investment
28
2018 Terminal 27.5 MTPA (30,000 M.Baht) 2020 EGAT 5 MTPA 2026 Terminal 35 MTPA 2031 Terminal 45 MTPA
Term rminal inal
LNG Inf nfrast rastru ructure cture Thai ai Oi Oil
2019 Clean Fuel Project (140,000 M.Baht) 2019 Improvement (4,000 M.Baht) *Annual Maintenance (1,320 M.Baht)
BCP – Awa
ward rd 314 14 M. Baht ht fro rom 8,400 0 M. Baht t (3.7%) %)
2018 Continuous Catalyst Regeneration Unit (8,400 M.Baht)
Key Success Factor
CAZ Highlight
1 2 5 4 3
Solid backlog secured Cost management Experienced management team Good relationship with renowned owners and main contractors Strong financial status
30