operations committee meeting
play

Operations Committee Meeting North Carolina Turnpike Authority July - PowerPoint PPT Presentation

Board of Directors Operations Committee Meeting North Carolina Turnpike Authority July 19, 2018 Volvo Trucks/FedEx Platooning Demonstration Dennis Jernigan, P.E. Director of Highway Operations 2 Volvo Trucks/FedEx Platooning Demonstration


  1. Board of Directors Operations Committee Meeting North Carolina Turnpike Authority July 19, 2018

  2. Volvo Trucks/FedEx Platooning Demonstration Dennis Jernigan, P.E. Director of Highway Operations 2

  3. Volvo Trucks/FedEx Platooning Demonstration AVPG Designation - Triangle Expressway designated as a USDOT Autonomous Vehicle Proving Ground in January 2017 - First meeting with Volvo Trucks team in March 2017 - Collaborated with Volvo team, NCDOT and NCDMV on platooning legislation that was passed in July 2017 - Volvo submitted a plan for demonstration in March 2018 - Ordinances issued by NCDOT March 29, 2018 - Demonstration began in early April 2018 3

  4. Volvo Trucks/FedEx Platooning Demonstration Details of Demonstration • Veridea Parkway served as the proving ground and southern terminus of route • Davis/Hopson interchange was used as northern terminus of route • Salt barn location at Green Level was used to store tractors/trailers overnight • Demonstration occurred outside a.m. and p.m. peak periods • Trucks were spaced 75 to 100 feet apart as they traveled at 62 miles per hour • All tractors had licensed drivers, each with 15+ years driving experience Safety Was Paramount In All Demonstrations 4

  5. Volvo Trucks/FedEx Platooning Demonstration 5 Photo courtesy of The Associated Press

  6. Volvo Trucks/FedEx Platooning Demonstration Drivers: Ulysses, Justin, Cindy Technical Team: Franklin, Bob, George 6

  7. Volvo Trucks/FedEx Platooning Demonstration 7

  8. Volvo Trucks/FedEx Platooning Demonstration Media Outlets 8

  9. I-485 & U.S. 74 Project Update Rodger Rochelle, P.E. Chief Engineer 9

  10. I-485 & U.S. 74 Project Update Discussion Items • Project Overview • T&R Analysis Update • Recent Activities • Upcoming Public Open Houses • Next Steps 10

  11. I-485 & U.S. 74 Project Update I-485 and U.S. 74 Express Lanes Network U.S. 74 Phase I: Convert Bus Lane to Express Lane (STIP Project U-5526A) U.S. 74 Phase II: Add One Express Lane and Widen to Three General Purpose Lanes in Each Direction (STIP Project U-2509) NOTE: Existing Lanes Will Not Be Tolled I-485: Add One Express Lane in Each Direction (STIP Project I-5507) Monroe Expressway 11

  12. I-485 Express Lanes STIP Project I-5507

  13. I-485 & U.S. 74 Project Update I-485 Express Lanes (I-5507) • Add One Express Lane in Each Direction Between I-77 and U.S. 74 • Extend Third General Purpose Lane from Rea Road to Providence Road (Both Directions) – No tolls will be added to the existing and new general purpose lanes • Combine Three Other Area Projects with I-485 Project Widen Ballantyne Commons Parkway Bridge I-485: Add One Express (STIP Project U-6030) Lane in Each Direction Improve John (STIP Project I-5507) Street Interchange (STIP Project U-4714AB) GP New Interchange at Weddington Road (STIP Project R-0211EC) 13

  14. I-485 & U.S. 74 Project Update I-485 Express Lanes (I-5507) • Proposed Express Lanes Direct Connectors and Access Points Westinghouse Blvd Direct Connector Johnston Rd Direct Connector Proposed Direct Connector Proposed Access Point 14

  15. U.S. 74 Express Lanes Phase I STIP Project U-5526A

  16. I-485 & U.S. 74 Project Update U.S. 74 Express Lanes Phase I (U-5526A) • Convert the Bus Lane Along U.S. 74 to Express Lane Albemarle Rd DC U.S. 74 Phase I: Convert Bus Lane to Express Lane – Approximately 6 miles (STIP Project U-5526A) – Reversible express lane between I-277 and Albemarle Road LEGEND DC Direct Connector Ingress/Egress Point – One express lane in each direction between Albemarle Road and Wallace Lane 16

  17. I-485 & U.S. 74 Project Update U.S. 74 Express Lanes Phase I (U-5526A) I-277 to Albemarle Road Albemarle Road to Wallace Lane Express Lane Express Lanes General Purpose General Purpose Lanes Lanes 17

  18. U.S. 74 Express Lanes Phase II STIP Project U-2509

  19. I-485 & U.S. 74 Project Update U.S. 74 Express Lanes Phase II (U-2509) • One Express Lane in Each Direction Between U.S. 74 Phase II: Add One Express Conference Dr and I-485 DC Lane and Widen to Three General Purpose Lanes in Each Direction – Approximately 6 miles (STIP Project U-2509) • Other Improvements DC – Upgrade U.S. 74 to expressway (remove at-grade intersections) – Convert multiple at-grade DC intersections into grade separations or interchanges LEGEND DC Direct Connector Entrance/Exit Point – Several parallel road connections to improve connectivity 19

  20. I-485 & U.S. 74 Project Update U.S. 74 Express Lanes Phase II (U-2509) Conference Drive to I-485 Express Lanes General Purpose Lanes 20

  21. I-485 & U.S. 74 Project Update Recent Activities • Project Update to CRTPO Board on March 21, 2018 • Feedback from CRTPO – Continue T&R analysis and provide updates to CRTPO – Work with CRTPO staff to form a toll operations advisory group – Conduct additional outreach to local jurisdictions and the public 21

  22. I-485 & U.S. 74 Project Update Registered Carpool Scenario T&R Analysis $14M $14M $12M $14M CURRENT DATA $12M PREVIOUSLY PRESENTED DATA $10M $16M $16M $12M $10M Revenue Toll Capital Toll Operations $8M Toll Operations $10M $12M $12M Toll Capital $8M $6M Toll Operations Revenue Toll Capital $8M $6M Revenue Toll Operations $8M $8M $4M Toll Capital $6M Revenue $4M $2M $4M $4M $4M $2M $0M 2022 2027 2032 2037 2042 2047 2052 2057 $2M $0M $0M $0M 2022 2027 2032 2037 2042 2047 2052 2057 2022 2027 2034 2039 2044 2022 2027 2034 2039 2044 204 204 9 9 $0M Total Shortfall: ̴ $(20M) | Years of Shortfall: ̴ 16 Total Shortfall: ̴ $(6M) | Years of Shortfall: ̴ 7 2022 2027 2032 2037 2042 2047 2052 2057 Sources: Source: I-485: Stantec February 2018 Draft Memo I-485 and U.S. 74: Stantec May 2018 Level II Draft Submittal U.S. 74: Stantec August 2015 Screening Level Memo 22

  23. I-485 & U.S. 74 Project Update Key Differences in Assumptions • Previously Presented Data – Screening Level Traffic & Revenue for U.S. 74 – 50% Revenue downside • Current Data – Level II Draft Traffic & Revenue for U.S. 74 – 35% Revenue and 15% Transaction downside 23

  24. I-485 & U.S. 74 Project Update CRTPO Toll Operations Advisory Group • Membership – CRTPO representatives – NCTA representatives • Rodger Rochelle – NCTA Chief Engineer • Warren Cooksey – NCTA Director of Community Affairs • Greg Boulanger – Consultant to NCTA • Radha Krishna Swayampakala – Consultant to NCTA • First Meeting: July 16, 2018 24

  25. I-485 & US 74 Project Update Methods for Public Outreach publicinput.com/I-485_US- 74_Charlotte 25

  26. I-485 & U.S. 74 Project Update Methods for Public Outreach @NCTurnpike @NCDOT_Charlotte Public Open Houses: July 25 & 26, 2018 26

  27. I-485 & U.S. 74 Project Update Next Steps Task I-485 (I-5507) U.S. 74 Phase I (U-5526A) U.S. 74 Phase II (U-2509) Public Meetings July 25 & 26, 2018 Summer 2018 Summer & Fall 2018 Completion of Summer 2018 Summer 2018 2019 Environmental Studies Summer 2018 Already in Progress Late 2019 Begin Final Designs Start Construction Summer 2019 TBD TBD Open to Traffic 2022 TBD TBD (Anticipated) 27

  28. I-485 & U.S. 74 Project Update I-485 Express Lanes (I-5507) 28

  29. 29

  30. Questions? 30

  31. Complete 540 Procurement Update Rodger Rochelle, P.E. Chief Engineer 31

  32. Complete 540 Procurement Update Complete 540 • R-2721A • 4.6 mile new location • ~ 190 parcels • R-2721B • 4.9 mile new location • ~ 210 parcels • R-2828 • 8.6 mile new location • ~ 250 parcels 32

  33. Complete 540 Procurement Update Current Project Schedule • Record of Decision: June 6, 2018 • Corridor Permit Application: Summer 2018 • Right of Way Plans for R-2721A & R-2721B: Fall 2018 • Anticipate Permits: Late 2018/Early 2019 (phased for R-2828 & construction for R-2721A and R-2721B) • Design-Build Contract Letting – R-2828: November 2018 – R-2721B: February 2019 – R-2721A: April 2019 – R-2829: Future (2027) • Complete Project Finance Early 2019 33

  34. Complete 540 Procurement Update Status and Next Steps R-2828 R-2721B R-2721A Advertisement  April 16  July 2 September 4 SOQ Due Date  May 11 July 31 October 2 Shortlist Date  May 24 August 14 October 18 Issue 1 st Draft RFP  May 24 August 14 October 18 Debrief Teams  Week of June 4 Week of Aug. 27 Week of Oct. 29 1 st Meeting with Teams  June 7 August 28 November 1 Issue 2 nd Draft RFP  June 26 September 11 November 20 2 nd Meeting with Teams  July 10 September 25 December 6 Issue 3 rd Draft RFP July 24 October 9 December 20 3 rd Meeting with Teams August 7 October 23 January 8 34

  35. Thank you!

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend