CONTRACTUAL IMPLICATIONS OF COVID-19 FOR BRAND MARKETERS
BRENT J. ARNOLD
ACA, April 14, 2020
OF COVID-19 FOR BRAND MARKETERS BRENT J. ARNOLD ACA, April 14, - - PowerPoint PPT Presentation
CONTRACTUAL IMPLICATIONS OF COVID-19 FOR BRAND MARKETERS BRENT J. ARNOLD ACA, April 14, 2020 AGENDA Topic Force Majeure in Marketing Contracts Frustration of Contract Protecting Your Interests Questions 2 FORCE MAJEURE IN MARKETING
BRENT J. ARNOLD
ACA, April 14, 2020
Topic Force Majeure in Marketing Contracts Frustration of Contract Protecting Your Interests Questions
2
consequences of breach of contract
control”)
3
performance
pandemic / epidemic / quarantine / government-ordered social distancing. Were any of these unforeseeable, post-SARS?
4
5
“Force Majeure” means unforeseeable reasons or causes beyond a Party's reasonable control, which may include without limitation, war (whether or not declared), sabotage, insurrection, rebellion, riot or other act of civil disobedience, act of a public enemy, act of any government or any agency or subdivision thereof, fire, accident, explosion, epidemic, quarantine, restrictions, storm, flood, earthquake, or other act of God, which could not be reasonably expected to be avoided, or new laws or regulations forbidding or limiting the execution of this Agreement.
6
If at any time Agency becomes aware that it may not be able to perform the Services or deliver any Deliverables by any date set out in the applicable Scope of Work (or any other deadline agreed by the Parties in writing), Agency will promptly notify Advertiser and give details of the reasons for the delay. Unless the delay is caused by Force Majeure, in which case the provisions of Section 27 will apply, Agency’s failure to perform the Services would represent a material breach of this Agreement entitling Advertiser to terminate this Agreement if the breach is not remedied in accordance with Section 25.5.2.
7
Section 27: In the event that either Party will be rendered wholly or partially unable to carry
Party or both Parties, as they are affected by such cause, will be excused during the continuance of any inability so caused, but such inability will be remedied with all reasonable
(30) days, the Party not subject to the Force Majeure may terminate this Agreement. During the period of a Force Majeure, Advertiser will be entitled to seek an alternative service provider at its own cost with respect to the Services affected. Advertiser will be relieved of the
throughout the duration of such Force Majeure. Notwithstanding the foregoing, in no event will any delay caused by a strike or other labor dispute within Agency excuse Agency’s obligation to perform as required under this Agreement.
8
9
contract
as in force majeure)
10
Frustrated Contracts Act, RSO 1990, c F.34
(unlike frustration at common law, which terminates the contract entirely)
11
Frustrated Contracts Act, RSO 1990, c F.34 Application of the Act 2 (1) This Act applies to any contract that is governed by the law of Ontario and that has become impossible of performance or been otherwise frustrated and to the parties which for that reason have been discharged. R.S.O. 1990, c. F.34, s. 2 (1); 1993, c. 27, Sched.
12
Frustrated Contracts Act, RSO 1990, c F.34 Adjustment of rights and liabilities 3 (1) The sums paid or payable to a party in pursuance of a contract before the parties were discharged, (a) in the case of sums paid, are recoverable from the party as money received for the use of the party by whom the sums were paid; and (b) in the case of sums payable, cease to be payable. R.S.O. 1990, c. F.34, s. 3 (1).
13
Frustrated Contracts Act, RSO 1990, c F.34 Expenses (2) If, before the parties were discharged, the party to whom the sums were paid or payable incurred expenses in connection with the performance of the contract, the court, if it considers it just to do so having regard to all the circumstances, may allow the party to retain or to recover, as the case may be, the whole or any part of the sums paid or payable not exceeding the amount of the expenses, and, without restricting the generality of the foregoing, the court, in estimating the amount of the expenses, may include such sum as appears to be reasonable in respect of
incurring the expenses. R.S.O. 1990, c. F.34, s. 3 (2).
14
Frustrated Contracts Act, RSO 1990, c F.34 Benefits (3) If, before the parties were discharged, any of them has, by reason of anything done by any
than a payment of money, the court, if it considers it just to do so having regard to all the circumstances, may allow the other party to recover from the party benefitted the whole or any part of the value of the benefit. R.S.O. 1990, c. F.34, s. 3 (3).
15
Frustrated Contracts Act, RSO 1990, c F.34 Assumed obligations (4) Where a party has assumed an obligation under the contract in consideration of the conferring
contract or not, the court, if it considers it just to do so having regard to all the circumstances, may, for the purposes of subsection (3), treat any benefit so conferred as a benefit obtained by the party who has assumed the obligation. R.S.O. 1990, c. F.34, s. 3 (4).
16
Frustrated Contracts Act, RSO 1990, c F.34 Insurance (5) In considering whether any sum ought to be recovered or retained under this section by a party to the contract, the court shall not take into account any sum that, by reason of the circumstances giving rise to the frustration of the contract, has become payable to that party under any contract of insurance unless there was an obligation to insure imposed by an express term of the frustrated contract or by or under any enactment. R.S.O. 1990, c. F.34, s. 3 (5).
17
Frustrated Contracts Act, RSO 1990, c F.34 Special contractual provisions (6) Where the contract contains a provision that upon the true construction of the contract is intended to have effect in the event of circumstances that operate, or but for the provision would
extent, if any, as appears to the court to be consistent with the provision. R.S.O. 1990, c. F.34,
18
Frustrated Contracts Act, RSO 1990, c F.34 Where contract severable (7) Where it appears to the court that a part of the contract can be severed properly from the remainder of the contract, being a part wholly performed before the parties were discharged, or so performed except for the payment in respect of that part of the contract of sums that are or can be ascertained under the contract, the court shall treat that part of the contract as if it were a separate contract that had not been frustrated and shall treat this section as applicable only to the remainder of the contract. R.S.O. 1990, c. F.34, s. 3 (7).
19
applicable in the circumstances
(e.g. not just quarantine, but government-ordered closing of non-essential businesses, bans on public gatherings, social distance measures, etc.)
20
21
gowlingwlg.com
Gowling WLG (Canada) LLP is a member of Gowling WLG, an international law firm which consists of independent and autonomous entities providing services around the world. Our structure is explained in more detail at gowlingwlg.com/legal
Brent J. Arnold
Partner Technology Sub-Group Leader (Com Lit) brent.arnold@gowlingwlg.com 416-369-4662