ODOT Region 1 I-5: Interstate Bridge Trunnion Replacement Project During Closure Approximately two weeks September 2020 A.M. Configuration (3 am to 10 am) During Closure Approximately two weeks September 2020 A.M. Configuration (3


  1. ODOT – Region 1 I-5: Interstate Bridge Trunnion Replacement Project

  2. During Closure Approximately two weeks September 2020 A.M. Configuration (3 am to 10 am)

  3. During Closure Approximately two weeks September 2020 A.M. Configuration (3 am to 10 am)

  4. Oregon Hayden Island NB On-Ramp Closure Use Hayden Island Southbound On-Ramp to Northbound Victory Blvd. On-Ramp Exit, Closed then use I-5 NB On-Ramp

  5. Oregon Marine Drive NB On-Ramp Closure Northbound On-Ramp Closed Use MLK and Columbia Blvd. to I-205

  6. Washington SR14 NB Off-Ramp Closure Use Mill Plain Blvd. Exit, Then use I-5 Southbound On-Ramp to SR14 Northbound Southbound Off-Ramp Off-Ramp Closed

  7. Washington SR14 SB On-Ramp Closure Use I-5 Northbound On-Ramp to Mill Plain Blvd. Exit, Then use I-5 Southbound Southbound On-Ramp On-Ramp Closed

  8. Oregon Northbound I-5 Alternate Route Use I-5 Northbound Off-Ramp to Lombard St. Exit, Then use Columbia Blvd and Killingsworth St. to I-205 Northbound On-Ramp

  9. Washington Southbound I-5 Alternate Route Use I-5 Southbound Off-Ramp to 39th St., Then use Eastbound On-Ramp to SR500 to I-205 Southbound On-Ramp

  10. I-5 Alternate Routes Use US30 Northbound and Southbound between Portland and Longview/Kelso Use I-205 Northbound and Southbound from Tualatin to Salmon Creek

  11. Before/After Closure Restrictions I-5 Northbound and Southbound For single lane closures: • Nightly, Sunday night through Friday morning between 8:00 p.m. and 5:00 a.m. • Friday night through Saturday morning between 9:00 p.m. and 8:00 a.m. • Saturday night through Sunday morning between 9:00 p.m. and 9:00 a.m. For two-lane closures: • Nightly, Sunday night through Friday morning between 10:00 p.m. and 5:00 a.m. • Friday night through Saturday morning between 11:00 p.m. and 7:00 a.m. • Saturday night through Sunday morning between 11:00 p.m. and 8:00 a.m. I-5 Northbound and Southbound Entrance and Exit-Ramps • Nightly, Sunday night through Friday morning between 10:00 p.m. and 5:00 a.m. • Friday night through Saturday morning between 10:00 p.m. and 7:00 a.m. • Saturday night through Sunday morning between 10:00 p.m. and 8:00 a.m.

  12. Mitigation Vehicle queuing could be double the normal peak hours and extend for more hours of the day Public Information and Outreach • Transit Improvements • Demand Management • Incident/Emergency Management • Closures and Detours •

  13. Schedule Bid Opening – December 6, 2018 • Fabrication – 2019 to Early 2020 • Mobilization – Summer 2020 • Closure – 2 weeks in September 2020 • Project Completion – October 30, 2020 •

  14. Project Website • www.interstatebridge.org Questions? •

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.