ODOT Region 1 I-5: Interstate Bridge Trunnion Replacement Project During Closure Approximately two weeks September 2020 A.M. Configuration (3 am to 10 am) During Closure Approximately two weeks September 2020 A.M. Configuration (3


slide-1
SLIDE 1

ODOT – Region 1

I-5: Interstate Bridge Trunnion Replacement Project

slide-2
SLIDE 2

During Closure

Approximately two weeks September 2020 A.M. Configuration (3 am to 10 am)

slide-3
SLIDE 3

During Closure

Approximately two weeks September 2020 A.M. Configuration (3 am to 10 am)

slide-4
SLIDE 4

Oregon Hayden Island NB On-Ramp Closure

Northbound On-Ramp Closed Use Hayden Island Southbound On-Ramp to Victory Blvd. Exit, then use I-5 NB On-Ramp

slide-5
SLIDE 5

Oregon Marine Drive NB On-Ramp Closure

Northbound On-Ramp Closed Use MLK and Columbia Blvd. to I-205

slide-6
SLIDE 6

Washington SR14 NB Off-Ramp Closure

Northbound Off-Ramp Closed Use Mill Plain

  • Blvd. Exit,

Then use I-5 Southbound On-Ramp to SR14 Southbound Off-Ramp

slide-7
SLIDE 7

Washington SR14 SB On-Ramp Closure

Southbound On-Ramp Closed Use I-5 Northbound On-Ramp to Mill Plain Blvd. Exit, Then use I-5 Southbound On-Ramp

slide-8
SLIDE 8

Oregon Northbound I-5 Alternate Route

Use I-5 Northbound Off-Ramp to Lombard St. Exit, Then use Columbia Blvd and Killingsworth St. to I-205 Northbound On-Ramp

slide-9
SLIDE 9

Washington Southbound I-5 Alternate Route

Use I-5 Southbound Off-Ramp to 39th St., Then use Eastbound On-Ramp to SR500 to I-205 Southbound On-Ramp

slide-10
SLIDE 10

I-5 Alternate Routes

Use I-205 Northbound and Southbound from Tualatin to Salmon Creek Use US30 Northbound and Southbound between Portland and Longview/Kelso

slide-11
SLIDE 11

Before/After Closure Restrictions

I-5 Northbound and Southbound For single lane closures:

  • Nightly, Sunday night through Friday morning between 8:00 p.m. and 5:00 a.m.
  • Friday night through Saturday morning between 9:00 p.m. and 8:00 a.m.
  • Saturday night through Sunday morning between 9:00 p.m. and 9:00 a.m.

For two-lane closures:

  • Nightly, Sunday night through Friday morning between 10:00 p.m. and 5:00 a.m.
  • Friday night through Saturday morning between 11:00 p.m. and 7:00 a.m.
  • Saturday night through Sunday morning between 11:00 p.m. and 8:00 a.m.

I-5 Northbound and Southbound Entrance and Exit-Ramps

  • Nightly, Sunday night through Friday morning between 10:00 p.m. and 5:00 a.m.
  • Friday night through Saturday morning between 10:00 p.m. and 7:00 a.m.
  • Saturday night through Sunday morning between 10:00 p.m. and 8:00 a.m.
slide-12
SLIDE 12

Mitigation

Vehicle queuing could be double the normal peak hours and extend for more hours of the day

  • Public Information and Outreach
  • Transit Improvements
  • Demand Management
  • Incident/Emergency Management
  • Closures and Detours
slide-13
SLIDE 13

Schedule

  • Bid Opening – December 6, 2018
  • Fabrication – 2019 to Early 2020
  • Mobilization – Summer 2020
  • Closure – 2 weeks in September 2020
  • Project Completion – October 30, 2020
slide-14
SLIDE 14
  • Project Website

www.interstatebridge.org

  • Questions?