NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
Masa Ono, Jon Menard, Stefan Gerhardt
September 30, 2016 FY 2016 Q4 Review
NSTX-U Project Update Masa Ono, Jon Menard, Stefan Gerhardt - - PowerPoint PPT Presentation
NSTX-U Project Update Masa Ono, Jon Menard, Stefan Gerhardt September 30, 2016 FY 2016 Q4 Review NSTX-U FY 2016 Q4 Review September 30, 2016 NSTX 6 Outline Machine Recovery Status and Plan On-Going Facility Enhancement Status and
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
September 30, 2016 FY 2016 Q4 Review
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
http://nstx.pppl.gov/DragNDrop/NSTX_Meetings/Run_Assessment/2016/
– And ~16 weeks where we tried to run.
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
~15 Calendar Weeks ~12 Operations Weeks ~9 Calendar Weeks ~4 Operations Weeks
Last Full Boronization Mini Boronizations
PF-1AU Flux / Current
Coil failure
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
Core Profile Diagnostics BES AXUV Core Bolometer Poloidal CHERS Toroidal CHERS ERD MPTS MSE-CIF MSE-LIF USXR Poloidal Arrays (2) rtVPhi ME-SXR Fast Ion Diagnostics T-FIDA V-FIDA SNPAs (3) Neutron Detectors S-FLIP I-FLIP Fixed-f Reflectometer Spectroscopy ENDD XEUS LOWEUS MonaLISA VIPS DIMS VB EIES (Filterscopes) DIBS Other Plasma TV (2) Shunt Tiles GPI Penning Gauges
Operational In Progress
Magnetics Operations Magnetics Diamagnetic Loop RWM sensors High-f and high-n arrays Divertor Divertor AXUV Bolometer (LADA) Divertor Fast Cameras Divertor Intensified Cameras Infrared Video Bolometer Divertor Langmuir Probes
1D CCDs MAPP Divertor Tangential Imaging Wide Angle Infrared Camera Fast Infrared Cameras Divertor SPRED
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
center-stack to replace the damaged copper divertor cooling tubes. This will also give the opportunity to replace PF-1AL.
September 19. The radiology results were reviewed and the phase I destructive test (the coil sectional cuts) plan was discussed.
coil mandrel fabrication, coil conductor procurement, and procurement of coil fabrication parts.
performed in preparation for IAEA and APS. Plan to complete the calibration on October 7.
mid-October around the time of IAEA.
activities.
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
7
PF-1AU coil failed June 28 Decision to stop the run and remove PF-1AU
PF-1AU removed
Copper cooling line problem discovered on
First PF-1AU forensic meeting
Second forensic meeting on Sep. 19 Decision to remove CS
X-ray radiography Phase 1 disection Post run in-vessel diagnostic calibration TF joint removal
PF-1AL mandrel fabr.ationat PPPL PF-1AU mandrel fabr.ationat a vendor Coil shop being set up at PPPL Conductor procirement
Post run calibration
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
pack into three portions in feature-free areas
Borescope cooling paths from section planes
blockages – Borescope
joints – Borescope
Helium Leak Testing
Helium Leak, & Hydrostatic Testing
methods for Phase II DT
Region with “features” “features-free” section “features-free” section
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
joints
selected – based on careful considerations – Facility available at PPPL – Aiming to start next week.
perform CT in mid-October. Will consider sending a section once cooling line inspection/test is complete.
Aiming to complete forensic activities by the end of October
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
subcontractor was not satisfactory so we will request the remedy for it.
another lower mandrel.
were fabricated.
Making the joggle with the conductor long way was particularly challenging
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
cooling tube damage in the lower divertor
air pressure.
cannot be cooled between long-pulse higher power NSTX-U operations.
tubes at this time.
1. Removing CS from VV. 2. Pulling CS casing from OH-TF bundle
installation schedule is similar to the new PF- 1AL and –U installation schedule so they can be performed in parallel with no significant schedule hit.
CS Casing TF/OH VV
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
Heat transfer panel concept (used in Tore Supre) is being explored because of the radially thin design.
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
top for well over 1000 shots.
disassembled.
modeling data, bench measurements, and in-situ measurements.
Joint surfaces degraded in NSTX due to lift-off
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
After campaign 09/19/2016 Before campaign 12/05/2014
http://nstx.pppl.gov/DragNDrop/Operations/In_vessel_inspections/Post_run_2016/
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
Some spares for the next run period will be procured.
the TFTR Test Cell.
leak in vacuum.
Decon Room Source shop refurbishments requires a repair.
an update to fiber optics telemetry and an update to PLC controls. This long outage is an opportune time to address soon to be
Three Helium refrigerator compressors were removed and prepared for shipment to go out for full rebuilds.
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
Aug‐16 Sept‐16 Oct‐16 Nov‐16 Dec‐16 Jan‐17 Feb‐17 Mar‐17 Apr‐17 May‐17 Jun‐17 July‐17 Aug‐17 Sept‐17
Lift CS
Pump & Purge
Remove NBI-duct NBI related repair and maintenance: armor leak, calorimeters, source 1-A isolation valve, compressor rebuild, etc. In-vessel diagnostic calibration Remove components Remove PF-1AL Install ss cooling tubes Install new PF-1AL Install CS Install new PF-1AU
Continuous conductor procurement Autopsy and analyses Existing design review and improvements Review #1 PF-1AL mandrel fabr.at PPPL PF-1AL Fabri. at PPPL ISTP Install TF LE PF-1AU Fabri. at vendor Review #2
T est
PF-1AU mandrel fabr.atvendor Pump down
T est
We also have a large number of parallel tasks for diagnostics, research tools, and engineering projects including OH water heater, high Z tiles, etc.
Test plan being developed for PF-!AL
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
point heating of any coil
– Operated at BT ~ 0.65T for ~ 2 sec for over 1000 shots. All joints came out clean and nominal.
Parameter NSTX (Max.) FY 2016 NSTX-U Operations Achieved FY 2017 NSTX-U Preparation Year 3 NSTX-U Operations NSTX-U Ultimate Goal IP [MA] 1.2 ~1.1 2.0 2.0 2.0 BT [T] 0.55 ~0.65 1.0 1.0 1.0 Max Pulse length (s) ~ 1 ~ 2 5 5 5
17
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
New center-stack 2nd NBI
Li granule injector
Lower divertor cryo-pump
Graphite CHI/Lower Bullnose DBS, PCI, or other intermediate-k Snowflake
Run Weeks:
Incremental enables 5 year plan enhancements including DCP, NCC, ECH
MGI disruption mitigation AE antenna HHFW limiter upgrade Establish control of: Rotation High k Laser blow-
Boronization Enhanced MHD sensors Neutron collimator Charged fusion product sß Upgraded halo sensors Pulse-burst MPTS 10 20 20 ne
Integrated Scenarios Core Science Boundary Science
+ Particle Control
2016 2017 2018 2019 2020
0.5 T 1T, 1.5 2 MA, 1s 5s
MAPP MPTS BES MSE/LIF FIReTIP
Major enhancements:
Base funding incremental funding Fiscal Year:
1 MW ECH/EBW
High-Z tile row on lOBD CPS B diag. LiTER Upward LiTER APD-based GPI Scanning MLP XICS Divertor Prad Resistive Bolometer s
Off-midplane 3D coils (NCC)
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
Transfer line layout
– Pump radius, throat dimensions taken from the modeling. – The entire lower outer divertor region to be reduild.
– Diagnostic access and cryo-ring maintainability were assessed. – Graphite PFC with bake-out capability considered.
“Baffle Top” (BT) “Upper Bullnose” (UB)
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
21
fast evaporation
remote control
21” Li
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
22
EPI-V1 designed, fabricated, and assembled for NSTX-U EPI system prototype testing
linear rail gun is that the ambient magnetic field in ITER can be used to increase the gun efficiency
close to the vessel, which further improves the system response time and efficiency
conducted at UW and will be reported during IAEA FEC 2016
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
Vendor Fabrication Complete – High-Z tiles were delivered to PPPL in September on schedule . – While high-Z tiles are available, whether to install the at this outage will be decided by the programmatic needs.
Surface heat flux Temperature First fabricated high-Z tile
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
500 feet of supply and return piping
r Proposed 400 W L-He Linde LR-140 refrigerator
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6 2 6
Two flashlamps connected in series 9 mm NdYAG rod
Cut of the pumping chamber
NSTX-U rep rate
activities are on schedule
developed and tested at PSL, U Wisconsin.
2016 and received on Sept 26th at PPPL.
being finalized.
fabricated and slated for delivery mid-October.
supplies and then laser head in FY 17.
Initial test of 20 KHz rep rate!
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
27
Three level FIReTIP / High-K Table Installed
accelerometer to be used by UC Davis graduate student (E. Scott) for thesis on real- time vibration compensation for FIReTIP Three diagnostics for complete coverage of transport physics
channels
core to edge
(L-mode core and H-mode pedestal)
CO2 pump laser FIReTIP laser High-k laser table
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
J port Horizontal Modifications for installation of the XICS
enable implementation of tangential x-ray PHA and a TIV for later installation of the XICS.
Detector Houing Crystal Gate Valve
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
1066 plasma shots.
copper cooling water line damage discovered. After consultation with FES and PPPL management, decision to lift the CS was made on Sept 12. This will enable replacing PF-1AL without significantly impacting the schedule.
Phase 1 of the destructive testing is being prepared. The actual cutting will likely next week.
in the C-site, the same area as the NSTX-U TF/OH shop Mandrels are being fabricated and the coil conductors ordered. Other coil related material are also being procured. .
term and longer term enhancements.
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
LITERs
Lithium Evaporator (LITERs) Granule injector (GI) for ELM pacing
Rotating Impeller
Successfully tested
Granules: Li, B4C, C f ~ up to 500 Hz
Granular Reservoir
high bay south of NSTX-U Test Cell.
implemented for Li safety, used for the quick argon vent.
run.
GI installed on NSTX-U
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
poloidal location with identical injection set-up
torque) based on the ORNL ITER MGI design
NSTX-U MGI Valve
MGI also tested on the U. Washington test stand with magnetic field
Magnets Magnets MGI Valve
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
Prototype testing of joint design conducted
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
Vertical Tangential
Fast Ion D-Alpha Diagnostics
Supported number of experiments on NSTX-U
FIDA Views
new tangential (parallel) FIDA systems are ready.
cm, ≈ 10 keV resolutions.
HHFW Antennas CHI Gap Center-Stack sFLIP TAE antennas
FY 2016 - 2017 Energetic Particle Conceptual Design and Diagnostic Upgrade
spectroscopy then active excitation at few kW level.
being complete.
UCI FIU UCLA
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
ORNL
Divertor Imaging Spectrometer Dual-band fast IR Camera Multiple fast 2D visible and IR cameras with full divertor coverage
Li I C II
LLNL, ORNL, UT-K
LLNL ORNL Divertor fast eroding thermocouples MAPP probe for between-shots surface analysis – took data
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
Beam Emission Spectroscopy
for low k turbulence Supported experiments Cross-Polarization Scattering for magnetic fluctuations being developed in collaboration with DIII-D and MAST
Low k High k
UC Davis UCLA
High-k scattering for ETG
Available for FY 17 BES-2D-Fiber Assembly U Wisconsin
4x1 subharmonic mixer array Collection optics (Bay L)
4–channel CPS system in 2017
NSTX
NSTX-U FY 2016 Q4 Review
September 30, 2016 6
cold for HHFW absorption.
and then NB current drive can support the ramp and sustain the current – crucial for OH solenoid-free compact STs
– Good first pass absorption predicted.
incremental funding.
28 GHz Gyrotron Development
gyroton being developed at Tsukuba University.
and the preliminary power test looks promising for 1.5 MW operations.
NSTX-U Test Cell
Power Supply Room Gyroton room
28 GHz Gyrotron Room
28 GHz 1 MW Tube by Tsukuba
Gyrotron will be located in the TFTR basement. Stray magnetic fields was measured to be negligible