Norwegian Experience with Highway Concessions 2nd Workshop on - - PowerPoint PPT Presentation

norwegian experience with highway concessions
SMART_READER_LITE
LIVE PREVIEW

Norwegian Experience with Highway Concessions 2nd Workshop on - - PowerPoint PPT Presentation

Case Study 08.10.03 Norwegian Experience with Highway Concessions 2nd Workshop on Applied Infrastructure Research Dr. Ansgar Bendiek, Head of Infrastructure and Maritime HSH Nordbank, Hamburg, Germany 08.10.03 Page 2 Content. The


slide-1
SLIDE 1

08.10.03

Norwegian Experience with Highway Concessions

2nd Workshop on Applied Infrastructure Research

  • Dr. Ansgar Bendiek, Head of Infrastructure and Maritime

HSH Nordbank, Hamburg, Germany

Case Study

slide-2
SLIDE 2

08.10.03 Page 2

Content.

The Norwegian Road Program

– Decision Making Process – PPP - Road Projects

E39 Klett-Bårdshaug: Project Description

– Map – Scope of work – Main Elements – Project Contracts – Scope of Work

E 39 Klett-Bardshaug: Financing

– General terms – Structure – Tenor & Repayment – Security & Guarantees – Risk Allocation

Timetable Outlook

slide-3
SLIDE 3

08.10.03 Page 3

Decision Making Process

The Norwegian Road Program

Decision in the Storting to test the PPP concept

– Autumn 1998: The Storting asks the Government to propose road projects to test the PPP concept

National Transport Program

– February 2001: The Storting approves three road projects. Aims to test efficiency and effectiveness in achieving political objectives through the PPP model.

E39 Klett – Bårdshaug

– June 2001: The Storting approves the financing of new E39 Øysand – Thamshamn, partly financed by tolling, and asks the Vegdirektoratet to procure E39 Klett – Bårdshaug as a PPP- project.

slide-4
SLIDE 4

08.10.03 Page 4

PPP - Road Projects

E39 Klett – Bårdshaug, Sør-Trøndelag

– Financial Close and Construction start-up 04/2003. Completion 09/2005. Construction cost NOK 1.3 billion

E39 Lyngdal – Flekkefjord, Vest-Agder

– Indicative Bid 09/2003. Scheduled Financial Close and Construction Startup 04/2004. Construction cost NOK 0.8 – 1.1 billion.

E18 Kristiansand – Grimstad, Aust-Agder

– Pre-qualification 2003. Construction cost not defined.

The Norwegian Road Program

slide-5
SLIDE 5

08.10.03 Page 5

E 39 Klett- Bårdshaug: Map

Project Desciption

slide-6
SLIDE 6

08.10.03 Page 6

Scope of work

Engineering, Procurement and Construction: Øysand- Thamshamn 21.9 km. Approx. 2,5 year construction period. Cost NOK 1.3 billion. Operation and Maintenance: Klett-Bårdshaug 26.9 km. Concession period 25 years. Financing of construction and operating period.

Project Desciption

slide-7
SLIDE 7

08.10.03 Page 7

Contractual Structure

Selmer Skanska AS Based on Statens Vegvesen Vegdirektoratet

Project Desciption

Vegdirektoratet Orkdalsvegen

PPP Contract

Skanska BOT AB Laing Roads Debt Lenders

Loan Repayment Equity Return

Users Toll Company

AP, MMP, TP, SP, and ERC Toll Toll

The Storting

Ministry of Transport

Right to collect toll Additional Funds Fixed Price Turn Key Contract O&M Contract

Construction Company D&C Contractor O&M Contractor

Three Party Agreement

slide-8
SLIDE 8

08.10.03 Page 8

Project Parties

Tendering Authority: Statens Vegvesen

Vegdirektoratet

Sponsors SPC Lead Arrangers

Project Desciption

slide-9
SLIDE 9

08.10.03 Page 9

Main Elements

Two lane highway. 7 tunnels, totalling 10.2 km. 4 main intersections. Daily traffic:

– 7,900 AADT at Øysand – 5,600 at Thamshamn

Project Desciption

slide-10
SLIDE 10

08.10.03 Page 10

Project Contracts

Concession Contract

– 25 years operation, plus 2.5 years construction – Risks placed with party that can influence them – No traffic risk – Payment subject to completion – Payment mechanism during operation linked to performance – Handover to Vegdirektoratet at end of concession

Evaluation criteria: Net Present Value of future payments

Project Desciption

slide-11
SLIDE 11

08.10.03 Page 11

Project Contracts

EPC Contract

– Fixed-price date-certain turn-key contract – Back-to-back w/ concession (quality, dates, penalties, etc) – Penalties for non-performance (delays etc)

O&M Contract

– Defined service level for 25 years – Back-to-back w/ concession (services, penalties, reporting, etc.) – Penalties for non-performance

Project Desciption

slide-12
SLIDE 12

08.10.03 Page 12

Payment Mechanism

Concept

– Monthly/annual unitary payments being available for the SPC, but with the actual level of payment being varied according to performance against a number of pre-defined criteria.

Five Elements

– Availability Payments – Maintenance Monitoring Payments – Safety Payments – Traffic Payments – Early Repayment of Construction Cost

Project Desciption

slide-13
SLIDE 13

08.10.03 Page 13

E 39 PPP Road - Scope of Work

  • Availability Payment

Toll Collection

  • Operation
  • Construction
  • Design

Candidate (SPV) Toll Collector Storting Legal Framework

  • Project

Description

slide-14
SLIDE 14

08.10.03 Page 14

General Terms

Borrower Orkdalsvegen AS Sponsors Skanska BOT and Laing Roads Facility NOK 1,414 million Bank Syndicate HSH Nordbank Nordea Svenska Handelsbanken Dexia IKB ING SEK

Financing

Lead Arranger Co- Arranger

slide-15
SLIDE 15

08.10.03 Page 15

Structure

Combined construction and long-term facility: Tranche A NOK 1,150 million Tranche B - NIB tranche NOK 300 million Total NOK 1,450 million

Financing

slide-16
SLIDE 16

08.10.03 Page 16

Security & Guarantees

Security

  • Assignment of contracts and other rights
  • Pledge on SPC shares
  • Pledge on assets

Guarantees

  • D&C and O&M contract backed by Skanska AB

Reserve Accounts

  • 6 months DSRA
  • MMRA built up over 2 years in advance

Hedging

  • Interest fixing (swap) required

Financing

slide-17
SLIDE 17

08.10.03 Page 17

E 39 PPP Road - Risk Allocation and Means of Mitigation

  • Force Majeure
  • Political Risks
  • Payment Risk
  • Financial Risks
  • Inflation
  • Interest / Currency Risks
  • Insolvency
  • Operational Risks
  • Construction Risks
  • Planning Risks
  • Geotechnical Risks

Shared SPV State

  • Financing
slide-18
SLIDE 18

08.10.03 Page 18

Timetable E39 - I

15 January 2003 Appointment of preferred bidder final negotiations, due diligence, documentation 7 April 2003 Financial Close 26 June 2003 Syndication Closed April 2003 Construction start-up September 2005 Road completion

Timetable

slide-19
SLIDE 19

08.10.03 Page 19

Conclusion

Norway‘s first PPP project E39 I has successfully proven

– Interest from bidders ➭ availability of contractors – strong support from banks ➭ availability of funds – favorable terms and conditions ➭ competitive bidding – sound risk allocation and sharing ➭ Public Private Partnership

groundbreaking reference for projects to follow!

Conclusion

slide-20
SLIDE 20

08.10.03 Page 20

Outlook

Potential Scandinavian follow up projects

– Norway:

  • E18 Grimstad-Kristianssand (Motorway)
  • Sandnes-Stavanger, new double track railway

– Denmark:

  • Parking facility Ørestad, Copenhagen
  • Link across Roskilde Bay

– Finland:

  • E18 Tusken -Helsinki Motorway

Outlook

slide-21
SLIDE 21

08.10.03 Page 21

Structured Corporate Finance

The Infrastructure & Maritime Team

slide-22
SLIDE 22

08.10.03 Page 22

Infrastructure & Maritime - The team and the market.

  • The Infrastructure and Maritime Team as part of the Structured Corporate

Finance Division offers advisory and arranging services. Our Market:

  • Infrastructure (Roads, Tunnels, Bridges et al)
  • Maritime infrastructure (Substructures, Container, Öl & Gas terminals)
  • PPP-projects (Schools, Hospitals, Prisons et al)
  • Utilities
  • Broadband cable market
slide-23
SLIDE 23

08.10.03 Page 23

  • Dr. Ansgar Bendiek

Tel. +49 (0)40 / 3333 13484 Team head Fax +49 (0)40 / 3333 6 13484 e-Mail ansgar.bendiek@hsh-nordbank.com Maik Tschentschel Tel. +49 (0)40 / 3333 12584 Fax +49 (0)40 / 3333 6 12584 e-Mail maik.tschentschel@hsh-nordbank.com Thorsten Lundius Tel. +49 (0)40 / 3333 10062 Senior Manager Fax +49 (0)40 / 3333 6 10062 e-Mail thorsten.lundius@hsh-nordbank.com Matthias Meyer Tel. +49 (0)40 / 3333 12662 Senior Manager Fax +49 (0)40 / 3333 6 12662 e-Mail matthias.meyer@hsh-nordbank.com

Team Infrastructure & Maritime.

slide-24
SLIDE 24

08.10.03 Page 24

Carl Augustin Tel. +49 (0)40 / 3333 14611 Senior Manager Fax +49 (0)40 / 3333 6 14611 e-Mail carl.augustin@hsh-nordbank.com Petra Hoefle Tel. +49 (0)40 / 3333 12789 Manager Fax +49 (0)40 / 3333 6 12789 e-Mail petra.hoefle@hsh-nordbank.com Karen Raguse Tel. +49 (0)40 / 3333 13530 Junior Manager Fax +49 (0)40 / 3333 6 13530 e-Mail karen.raguse@hsh-nordbank.com Phillip Staake Tel. +49 (0)40 / 3333 13250 Assistance Fax +49 (0)40 / 3333 6 13250 e-Mail phillip.staake@hsh-nordbank.com

Team Infrastructure & Maritime.