North Precinct Overview Dan Eder & Amy Tsai, Council Central - PowerPoint PPT Presentation

North Precinct Overview Dan Eder & Amy Tsai, Council Central Staff Gender Equity, Safe Communities & New Americans July 27, 2016 Project Scope Precinct o Command staff offices o Locker rooms o Training rooms o Community Amenities o


  1. North Precinct Overview Dan Eder & Amy Tsai, Council Central Staff Gender Equity, Safe Communities & New Americans July 27, 2016

  2. Project Scope • Precinct o Command staff offices o Locker rooms o Training rooms o Community Amenities o Detention facilities o Basement training facilities • Garage • Public Plazas & Public Parking 3

  3. Project Schedule • Land Acquisition: Completed • Design & Permits: 2013 to 2016 • Construction: 2017 to 2018 • Building Opens: 2019 4

  4. Budget: Current Cost Estimate $ 14,300,000 Land Acquisition Design / Other $ 17,300,000 Construction $ 105,100,000 Contingency $ 22,700,000 Public Art $ 800,000 Grand Total $ 160,200,000 Rounded to nearest $100,000 5

  5. Budget: Project Funding $ 21,000,000 Appropriated Real Estate Excise Tax $ 2,000,000 LTGO Bonds $ 17,500,000 Interfund Loans $ 1,500,000 Not Yet Appropriated / “To Be Determined” $ 139,000,000 Pacific Place Garage Proceeds $ 15,000,000 Additional REET in 2018 and 2019 $ 22,000,000 LTGO Bonds backed by REET $102,000,000 GRAND TOTAL $ 160,000,000 6

  6. Highlighted Policy Decisions 1. Garage 2. Basement Training Facility 3. Community Amenities 7

  7. Garage – Two Bay Garage (Status Quo) 8

  8. Garage – One Bay Garage 9

  9. Garage – Eliminate Garage • No rendering available • Other Considerations – Future garage addition would be challenging – Access to the sally port via an open-air fast ramp – Current design requires officers to access 3 rd floor 10

  10. Garage – Options Summary Options Gross Savings Added Costs Net Effect A. Status Quo N/A N/A N/A 331 stalls B. One bay garage ($7.2 million) + $0.2 million ($7.0 million) 228 stalls C. Eliminate garage + $9.1 million ($5.5 million) ($17.0 million) to to 142 stalls plus + $11.5 million ($8.0 million) speed ramp to “sally port” 11

  11. Basement Training Facility • Independent training room • Tactical simulation space • Vehicular training space • Firing range 12

  12. Basement Training Facility – Options Summary Options Gross Savings Added Costs Net Effect A. Status Quo N/A N/A N/A B. Eliminate ($2.8 million) + $50,000 ($2.8 million) Basement Training Facility 13

  13. Community Amenities • Third- floor “training bar” • Public lobby • Community room • Other lobby amenities 14

  14. Community Amenities – Options Summary Options Gross Savings Added Costs Net Effect A. Status Quo N/A N/A N/A B. Eliminate ($7.9 million) + $6.7 million ($1.2 million) All Amenities 15

  15. Discussion & Questions 16

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.