New West End Elementary School Community Meeting Tuesday, May 16, - - PowerPoint PPT Presentation

New West End Elementary School Community Meeting Tuesday, May 16, 2017 | 6:30 PM 8:00 PM www.acps.k12.va.us Capacity Adjustments K-5 Seating K-5 K-5 Change Status FY 17 Capacity Deficit/ Enrollment Additions Current Capacity 6974


slide-1
SLIDE 1

www.acps.k12.va.us

Community Meeting

Tuesday, May 16, 2017 | 6:30 PM – 8:00 PM

New West End Elementary School

slide-2
SLIDE 2

www.acps.k12.va.us www.acps.k12.va.us

2

Capacity Adjustments

Note: This analysis does not take into consideration any other approved capacity projects.

Status K-5 Capacity K-5 FY 17 Enrollment K-5 Seating Change Deficit/ Additions Current Capacity 6974 8096

  • 1122

New School 638 638 Capacity with New School 7612 8096

  • 484

This building and adjacent garage became the most optimal solution for addressing elementary capacity given its square footage, location on the West End, and general building condition.

slide-3
SLIDE 3

www.acps.k12.va.us www.acps.k12.va.us

3

ACPS 2020 STRATEGIC PLAN Every Student Succeeds

  • Rich, rigorous and

engaging instructional program

  • Strong continuum of

student support services from highly skilled staff

  • Strong parent

engagement and parent centered activities

  • Variety of community

business partnerships

slide-4
SLIDE 4

www.acps.k12.va.us www.acps.k12.va.us

4

Instructional Program Features

  • GLAD
  • World Language
  • AVID
  • University Partnership
  • PBIS
slide-5
SLIDE 5

www.acps.k12.va.us www.acps.k12.va.us

5

Student Supports

  • Breakfast in the Classroom
  • Contract Custodial
  • Parent Liaison
  • Art & Music
  • Extended Academic Program
  • Communities in Schools
slide-6
SLIDE 6

www.acps.k12.va.us www.acps.k12.va.us

6

ACPS Policy FF: Naming the New School

The School Facilities Naming Committee: [10 Alexandria Citizens + Chair]

  • Chair – School Board Vice Chair
  • 9 Members nominated by each

School Board Member

  • 1 Member nominated by

City Council Committee Responsibilities:

  • Develop a timetable

& tasks for the naming

  • Review community

recommendations

  • Forward 3

recommendations to School Board.

Newly constructed school facilities shall be named by the School Board, based upon the recommendations of an ad hoc School Facilities Naming Committee. For full policy, visit https://www.acps.k12.va.us/cms/lib/VA01918616/Centricity/Shared/documents/school-board- policies/ff.pdf

slide-7
SLIDE 7

www.acps.k12.va.us www.acps.k12.va.us

7

New School Staffing

  • Funding in FY 2018 budget for
  • a principal to start July 2017*
  • a registrar/ administrative assistant to start

January 2018*

  • There will be a limit of how many teachers can

apply from each of the other schools

*Subject to approval by the School Board in the add/delete work sessions

slide-8
SLIDE 8

www.acps.k12.va.us www.acps.k12.va.us

8

Planned Use for 1701/1705

  • N. Beauregard

650 STUDENTS

PLAYSPACE + PARKING GARAGE BUSINESS USE + ELEMENTARY SCHOOL

2 FLOORS OF OFFICE SPACE

465 SPACES

TOP-LEVEL PLAYSPACE

1701 N. BEAUREGARD 1705 N. BEAUREGARD

slide-9
SLIDE 9

www.acps.k12.va.us www.acps.k12.va.us

9

Benefits of 1701/1705

  • N. Beauregard Site Selection

High Quality Instructional Space Cost-effective Capacity Solution Minimal Student Transfers Outdoor Space Potential Modern Building

TRANSFERS 650 STUDENTS

slide-10
SLIDE 10

www.acps.k12.va.us www.acps.k12.va.us

10

Cost Details:

PURCHASE PRICE:

$15 million

RETROFIT COST ESTIMATE:

approximately $23.2 million

slide-11
SLIDE 11

www.acps.k12.va.us www.acps.k12.va.us

11

Anticipated Timeline of Acquisition

REVIEW PERIOD Aug 1 – Sep 30, 2016 EXTENDED REVIEW PERIOD Oct 1 – Jan 31, 2017 CLOSING PERIOD April, 2017 NEXT STEPS

TODAY

slide-12
SLIDE 12

www.acps.k12.va.us www.acps.k12.va.us

12

Design & Construction Process

  • Jun, 2017:

Design-Build Firm on Board

  • Jul, 2017:

Develop Schematic Design

  • Sep, 2017:

DSUP Hearing at City Council

  • Oct-Dec, 2017: Finalize Construction Drawings
  • 1st quarter of 2018: Begin Construction
  • Sep, 2018:

Anticipated School Opening

slide-13
SLIDE 13

Front Elevation

13

slide-14
SLIDE 14

Floorplan – 1st Floor

14

slide-15
SLIDE 15

Floorplan – 3rd Floor

15

slide-16
SLIDE 16

Floorplan – 5th Floor

16

slide-17
SLIDE 17

Gym Addition – Phase II

17

slide-18
SLIDE 18

Front Elevation with Gymnasium Addition

18

slide-19
SLIDE 19

Garage Top Level with Playspace

19

slide-20
SLIDE 20

Concept Civil Plan – Concept II

20

SCHOOL BUILDING PARKING GARAGE/ PLAYSPACE

SCHOOL BUSES HIGHVIEW LANE PARENT QUEUE RAISED MEDIAN TRAFFIC CIRCLE

slide-21
SLIDE 21

www.acps.k12.va.us www.acps.k12.va.us

21

Transportation

  • There will be access for 3-5 buses
  • Walk routes will be reassessed for the new

school (sidewalks/practicality/safety)

  • A traffic study is in the process of being

conducted

  • The need for X-ing guards will be assessed
slide-22
SLIDE 22

Rooftop Playground Examples

Joan Fenichel Therapeutic Nursery JFTN Preschool in Brooklyn, New York

Time to Play: JFTN Rooftop Reopens. Digital image. League Center. League Education & Treatment Center, 7 July 2015. Web. 11 Jan. 2017.

22

slide-23
SLIDE 23

Rooftop Playground Examples

Lubinavitch School in Tenafly, New Jersey West Side Montessori in New York, New York

6,000 SF Rooftop Playground in Tenafly, NJ. Digital image. Unity Surfacing Systems. Unity Creations, Ltd., n.d. Web. 11 Jan. 2017. UNITY at W Side Montessori Rooftop Playground in NYC. Digital image. Unity Surfacing

  • Systems. Unity Creations, Ltd., n.d. Web. 11 Jan. 2017.

23

slide-24
SLIDE 24

Roof/Parking top Field Examples

The Northwest School (day and boarding school) - Seattle, Washington Sidwell Friends School in Washington, District of Columbia Pomona College in Claremont, California

400m Track and Football Field. Digital

  • image. Cannon Design. Cannon Design, n.d.
  • Web. 11 Jan. 2017.

6,000-foot Rooftop Sports Field. Digital

  • image. The Northest School. The Northest

School, n.d. Web. 11 Jan. 2017. Sustainable Parking Garage Pomona College South Campus. Digital image. National Precast Concrete Association. National Precast Concrete Association, 7

  • Feb. 2013. Web. 11 Jan. 2017.

24

slide-25
SLIDE 25

www.acps.k12.va.us www.acps.k12.va.us

25

Discussion Points

  • 1. What is your vision for the New West End

Elementary School?

  • 2. What programs would you like to see being
  • ffered at the NWEES or nearby locations?
slide-26
SLIDE 26

www.acps.k12.va.us www.acps.k12.va.us

26

  • 1. What are your hopes for the New

West End Elementary School?

GROUP DISCUSSION

slide-27
SLIDE 27

www.acps.k12.va.us www.acps.k12.va.us

27

  • 2. What programs would you like to see

being offered at the new school or at nearby locations?

http://educationalways.com/wp-content/uploads/2015/08/Importance-of-Extracurricular-Activities-in-School-Life.jpg

GROUP DISCUSSION

slide-28
SLIDE 28

www.acps.k12.va.us www.acps.k12.va.us

28

Key Engagement Activities

 Community Meeting – January 17, 2017  Possible Visit to Bailey’s Upper Elementary School for Arts and Sciences – TBD  Updates to John Adams ES and William Ramsay ES PTAs – April-May, 2017  Community Meeting - May 16, 2017

  • School Principal Selection – July, 2017
  • Community Meeting – Fall 2017
  • Open House Tour – June, 2018
  • School Opening Event – August, 2018
slide-29
SLIDE 29

www.acps.k12.va.us

Superintendent School Board Ramee A. Gentry, Chair Ronnie Campbell William E. Campbell Hal E. Cardwell Karen A. Graf Christopher J. Lewis Margaret Lorber Veronica Nolan Cindy Anderson, Vice Chair

  • Dr. Alvin L. Crawley

29

QUESTIONS?

CONTACT PERSON: Richard Jackson, Director of Educational Facilities, (703) 619-8038