New features of 660 MW Units
Sipat Super thermal power project
Turbine Maintenance
New features of 660 MW Units Turbine Maintenance Sipat Super thermal - - PowerPoint PPT Presentation
New features of 660 MW Units Turbine Maintenance Sipat Super thermal power project New features of 660 MW units Constructional features Operational features Lube oil system Governing system Feed water system Turbine
Sipat Super thermal power project
Turbine Maintenance
OJSC Power machines, Russia
LMZ, Russia
K-660-247 Four Cylinder, tandem compound, Reheat, Condensing Turbine Spring deck foundation
HPT, reverse flow, 17 (1-control stage,16 Reaction stages) IPT 11 X 2 impulse stages. LPT 2 nos. - 5 X 2 impulse stages.
4
2
4
35.8 Mtr
Clockwise (Viewed from front pedestal towards Generator)
simultaneously
sequence
Governing Box HP Turbine IP Turbine LP Turbine # 1 LP Turbine # 2 MS CRH HRH HPH#8A HPH#7A HPH#6A CRH LPH#4 LPH#3 LPH#2 LPH#1 LPH#1 Deareator HPH#8B HPH#7B HPH#6B Steam cooler HPH#8A HPH#7A HPH#6A LPH#4 LPH#3 LPH#2 LPH#1b LPH#1a Deareator HPH#8B HPH#7B HPH#6B Steam cooler
540ºC 247 KSc 349ºC 68.8 KSc 298ºC 47.9 KSc 565ºC 43.1 KSc
Parameters Units Value Live steam consumption, HPT inlet
t/h
2023.7 Rated total pressure of live steam, HPT inlet
MPa (kgf/cm 2 abs)
24.2 (247) Live steam rated temperature
°С
537 T after HPT exhaust
°С
297.8 P after HPT exhaust
MPa (kgf/cm 2 abs)
4.8 (47.9 kgf/cm2) Steam absolute pressure before IP SV
MPa (kgf/cm 2 abs)
4.3 (43.1 kgf/cm2) Live steam consumption , IPT inlet
t/h
1678.5 steam temperature before IPSV
°С
565 steam absolute pressure in condenser
MPa (kgf/cm 2 abs)
0.105 Inlet condenser CW temp
°С
33 cooling-water consumption
m3/h
64000
Locations Pressure (bar) – Absolute Temperatures (oC) Initial steam HPT inlet 247 537 HP cylinder exhaust 48 298.50 IP cylinder stop valve Inlet 43.20 565 Extraction 8 (HPT 13th stage to HPH 8) 68.8 349 Extraction 7 (CRH to HPH 7) 45.6 295.62 Extraction 6 (IPT 3rd stage to HPH 6 & TDBFP) 21.7 470 Extraction 5 (IPT 6rd stage to Deareator) 11.34 374.28 Extraction 4 (IPT 8th stage to LPH 4) 6.25 301 Extraction 3 (IPT 11th stage to LPH 3) 2.97 214 Extraction 2 (LPT 2nd stage to LPH 2) 0.624 0.79% / 89 Extraction 1 (LPT 4th stage to LPH 1) 0.264 4.38% / 68 LP cylinder exhaust 0.105 7.84%
system
Material: – HP outer casing: 15Cr1Mo1V – HP blade carrier/casings: 15Cr1Mo1V – HP shaft: 25Cr1Mo1V – HP Turbine Moving Blades first stage (1-5): 18Cr11MoNiVNb – HP Turbine Moving Blades stages (6-17): 15Cr11MoV – HP Turbine Fixed Blades first stage (1-5): 18Cr11MoNiVNb – HP Turbine Fixed Blades stages (6-17): 15Cr11MoV – HPT Casing Joint Bolts: 20Cr1Mo1V1TiB, 25Cr1MoV, 18Cr12WMoNbVB – Shaft Couplings: 25Cr1MoV – HP Labyrinth Seals: 20CrMo, 15CrMo
Material: – IP outer casing: 15Cr1Mo1V – IP Inner casing: G-X 12CrMoVNbN9-1 – IP shaft: 26CrNi3Mo2V – IP Turbine Moving Blades first stage (1-3): 18Cr11MoNiVNb – IP Turbine Moving Blades stages (4-11): 15Cr11MoV – IP Turbine Fixed Blades first stage (Ist ST): 18Cr11MoNiVNb – IP Turbine Fixed Blades stages (2-11): 15Cr11MoV – IPT Casing Joint Bolts: 20Cr1Mo1V1TiB, 25Cr1MoV, – 18Cr12WMoNbVB – Shaft Couplings: 25Cr1MoV – IP Labyrinth Seals: 20MnSi
Material: – LP inner & outer casing: Steel 3 – LP shaft: 26CrNi3Mo2V – LP Turbine Moving Blades first stage (1-2, 3-4): 20Cr13, – 15Cr11MoV – LP Turbine last stage moving blades: 13Cr11Ni2W2MoV – LP Turbine Fixed Blades first stage (1-4): 12Cr13 – LP Turbine Fixed Blades stages (5): 08 Cr13 – LPT Casing Joint Bolts: Steel 25 – Shaft Couplings: 25Cr1MoV – LP Labyrinth Seals: 26CrNi
To condenser From HRH From HRH
turbine
prevent inadmissible relative extensions of HPC and IPC rotors
time shall be increased by 30-60 minutes
rotor > +3.0 mm or differential temperature across the width of any HPC flanges > 40 ºC.
– Steam pressure in hot reheat pipeline is above 6.0 kg/cm2 – Steam temperature in hot reheat pipeline is above 150 ºC – Pressure in main turbine condensers is below 0.5 kg/cm2 (abs).
temperature of any flange.
closed.
– Relative expansion of rotor < - 1.0 mm or – Temperature difference between outer surface temperature of any HPC and HPC top or bottom > 80 ºC or – if the HPC top metal temperature exceeds 350 ºC
– The gate valve closes on the HPC flange heating steam supply line. – Control valve closes and drain opens
rotor > +1.0 mm or differential temperature across the width of any HPC flanges > 40 ºC.
– Steam pressure in hot reheat pipeline is above 6.0 kg/cm2 – Steam temperature in hot reheat pipeline is above 150 ºC – Pressure in main turbine condensers is below 0.5 kg/cm2 (abs).
temperature of any flange.
closed.
– Relative expansion of rotor < - 1.0 mm or – Temperature difference between outer surface temperature of any IPC and IPC top or bottom > 80 ºC or – if the IPC top metal temperature exceeds 350 ºC
– The gate valve closes on the IPC flange heating steam supply line. – Control valve closes and drain opens
Screw Jacks HRH Strainer
Bearing No 2 Bearing No 3
provides lubrication even at fully closed control valve
Equipment Capacity (m3/hr) Head (Ksc) AC Lube oil pump 300 4.3 DC Lube oil pump 250 2.0
TG LUBE OIL SYSTEM
M M M M M M GENERATOR ECT M
M
COOLER A COOLER B DUPLEX FILTER A DUPLEX FILTER B DMCW O/L DMCW INLET HPC IPC LPC1 LPC2 HEATER R/C PUMP OIL TRAP VAP.EX.FAN MAIN OIL TANK MOP A MOP B EOP A EOP B PCV LUBE OIL RETURN HEADER LUBE OIL SUPPLY HEADER FROM TOP UP OIL TANK
FROM SEAL OIL SYSTEM FROM PURIFIER UNIT TO SEAL OIL SYSTEM TO PURIFIER UNIT TO EOT TO JACKING OIL SYSTEM TO TRANSFER PUMP
VAPOUR LINE FILTRATION UNIT
HPT Front N1 (Multi wedge Tilting type JB) HPT Rear N2 (Multi wedge Tilting type JB) IPT Front (TB) N3 IPT Rear N4 LPT-1 Front N5 LPT-1 Rear N6 LPT-2 Front N7 LPT-2 Rear N8 Generator Front N9 Generator Rear N10 Exciter Front N11 Exciter Rear N12
Lube oil return Lube oil supply Vapor exhauster line HPC FRONT BRG
Lube oil return line Lube oil supply Vapour exhauster
Shell N Dia of orifice to standby tank Dia of orifice to shell Pressure at stand by tank N1 39 20 0.9 Ksc N2 39 20 0.9 N3 39 39 0.4 N3 Shell holder
39 29 1.0 N5 39 29 1.05 N6 30 29 0.95 N7 30 29 0.95 N8 33 29 0.95 N9 29 29 0.75
Brg No.4 & Brg No.5
wheel clutch (on turbine rotor)
handle is provided at first stage of Reduction gear. (15- 20 min by 180 deg manually)
Barring gear motor (30 KW, 735 rpm,) Hand drive for hand barring Reduction gears (3 stages) Free wheel clutches Rotor shaft, 1.05 rpm
TG ROTOR JACKING OIL SYSTEM
GENERATOR M M AC ROTOR JOP DC ROTOR JOP
LUBE OIL COOLER OUT LET
BRG1 HPC LPC 1 IPC LPC 2 BRG2 BRG3 BRG4 BRG5 BRG6 BRG7 BRG8 BRG9 BRG10
FROM MOT
H= 120 ksc
r
Rotor Jacking oil Oil outlet points Oil inlet from JOP discharge header
TG ROTOR JACKING OIL SYSTEM
(Td=60 sec).
Remotely from CCB motor can be started if
Rotor oil jacking pump (DC) starts automatically with Time delay 10sec , if
Rotor oil jacking pump (DC) stops automatically if
LL=20 ksc (Td=60 sec).
Remotely from CCB motor can be started if
TG BEARING JACKING OIL SYSTEM
GENERATOR M
AC BRG. JOP
FROM OUT LET OF COOLER
BRG1 HPC LPC 1 IPC LPC 2 BRG2 BRG3 BRG4 BRG6 BEARING HOUSING ORIFICE BRG5 BRG7 BRG8 BRG9 BRG10
FROM MOT
JOP suction Header Jop Discharge header
During turbine start-up and unit load variation conditions the rotor neck displacement occurs in the bearing inserts. To level the position relative to the rotor necks the bearing jacking oil pump starts. The rotor neck displacement(X-Y) in the inserts < 0.1mm Bearing JOP stops. No Standby Bearing JOP.
Bearing insert JOP starts automatically if
bearings 4-9.
Bearing insert JOP stops automatically with time delay of 30 sec if
bearings 4…9
ksc (Td=60 sec).
concealed governing.
systems & smaller sizes of the systems
EHCs ie 8NOS. of EHC
cum filtration units
M M M M M VAP.EX.FAN FROM GOV BOX FROM CF PURIFIER FROM CLEAN CF TANK MAIN CF TANK V= 6.9 M3 FROM GOV SYSTEM TO CF PURIFIER CF TRANSFER PUMP TO CLEAN CF TANK TO CF DRAIN TANK TO CF DRAIN TANK CF PUMP A CF PUMP B DUPLEX FILTER CF COOLER
STABILIZED PR. LINE NON-STABILIZED
ACCUMULATOR TO DRAIN HEADER CF SEPARATOR
T/hr. design capacity and 50ksc head with one in standby located at 0m height.
– Stabilized pressure header (50ksc). – Unstabilized pressure header (50 ksc). – Stabilized header (50NB) provides control oil to all SVs & EHCs through governing block.
SV & CV.
connected to Non stabilized pressure header
SCHEME OF 660 MW Governing System
– Control gear – Over speed governor – Trip solenoids – Test electromagnets – Manual trip buttons. – Intermediate shaft. – Intermediate shaft lever. – Pressure limiting device. – Test valve.
Control gear Intermediate shaft lever Test valve
Stabilized oil (50 ksc) To SV To EHC
governor(OG) slide valve(50 ksc).
solenoids
(35 ksc).
Control gear from its position 00 to 900 either by operator command or hand wheel.
signal oil supply to all S.V.
and EHC signal oil at the time turbine protection action.
comes out from 110% OG.
results pressure drop in protection line and due to pressure in cocking line & Inlet SV line OG pilot valve moves down which cuts the oil supplying to S.V & EHC and connects it to drain. 111% OVERSPEEDING
OG2
110% OVERSPEEDING
OG1
bolts under oil injection testing.
conditions:
INTERMEDIATE SHAFT
LEVER
TEST VALVE
LEVER
– 1. when pressed : OG1(110%) switched out. – 2. when pulled : OG2(111%) switched out. – 3. At mid position : OG1 & OG2 are in service.
– Overspeeding (110% & 111%). – Oil injection testing.
With manual trip button
With manual trip button
STABILISED OIL(50ksc) UNSTABLISED OIL STREAM CONTROL OIL FOR EHC(35ksc) CONTROL OIL FOR STOP V/V CONTROL OIL FOR CRH NRVS
Head oil I/L Drain oil above piston Head oil I/L to servomotor Drain
piston Tie rods Pilot v/v
Head oil I/L Drain port Control
Head oil I/L CAM ATT LEVER FEED BACK LEVERS TIE RODS HP CONTROL VALVE
valve for HPT & IPT.
stabilized oil(50ksc) are used for the
results zero output pressure from EHC to CONTROL V/VS.
HEAD OIL/ STABILISED OIL I/L (50 KSc) I/L CONTROL OIL PR FROM GOV BLOCK (35 KSc) O/L CONTROL OIL / SECONDARY OIL
Control oil/secondary oil from EHC : 1&2 for CRH NRVS
Head oil/un stablised oil
– Test for partial closing and opening of the CV is performed from the turbine controller i.e. EHC signal. – Test only carried out on fully open CV. – Turbine load range during testing : 40%-100%. – During testing EHCs are controlled by test program. – As per OJSC’s guideline testing of partial closing of CV is carried out once in a week. – Test of partial closing is carried out separately for each CV.
– The test program for trip solenoid is used to monitor
– Trip solenoid gets isolated from main circuit by the help of corresponding test electromagnet for testing. – As per guideline testing of trip solenoids carried out once in a month. – In case of any protection acts during testing ; testing program is stopped and testing mechanism set into initial position.
Speed gradients as per Manufacturer’s start up curve are as follows: Rolling Condition Target Speed Preset Time
Cold Startup ( > 72 H ) 3 - 500 rpm 150 sec 300 sec 1200 rpm* 550 sec 300 sec 3000 rpm 630 sec
72H 3 - 500 rpm 75 sec 120 sec 3000 rpm 240 sec
3 - 3000 rpm 360 sec
3 - 3000 rpm 300 sec
to 500 rpm
rpm* and subsequently to 3000 rpm
load > 80MW when “HPC ON” signal is generated
HPCV demand crosses 80%, switch ON Position controller to hold 80% as the o/p to control valves for raising pressure to rated value
START UP CURVES OF TURBINE AFTER SHUTDOWN OF THE UNIT
HPCV position & HP heaters charged
START UP CURVES OF TURBINE AFTER SHUTDOWN OF THE UNIT
START UP CURVES OF TURBINE AFTER SHUTDOWN OF THE UNIT
CONDITIONS OF TRIPPING THROUGH TRIP SOLENOID
Recirculatio n to Condenser
HOTWELL 1 HOTWELL 2
CEP-A CEP-C CEP-B
CPU GSC
LPH1.1 LPH1.2 LPH 2 LPH 3 LPH 4
DEAERATOR
DRIP P/P-A DRIP P/P-B CEP-A DRIP P/P-A DRIP P/P-A DRIP P/P-A
– Separate Condenser, CEP, Vacuum pump system
No of stages -07 Tapping stage for RH spray -02 Capacity- 769.95 T/hr Head- 3654.47 m Tapping flow & press – 48.12 T/hr , 112.2 ksc BP inlet/outlet- 14/21 ksc , 186.2 ºC Shut off head- 4830m Rated motor power -11.5 MW Full travel time of scoop tube- 8 sec Critical speeds – 8548/10122 operating speeds-BP/MP- 1490/6275 Min R/C flow -220 T/hr Double piston balancing device with segmental tilting pad thrust bearing
FST
Warm up line From
BP’s Boiler fill pump s Ammonia. hydraine Oxygen RH spray Hdr BFP Dish Hdr 2nd stage 7th stage Strainer cooling system BFP warm up scheme
TO HPH-7A HPH-6 FROM BFP’s TO DEA FROM IPT- 3rd STAGE TO HPH-8 OUTLET FROM HPH-8 OUTLET 22.7/224.5/231.3 373.6/196/1135 22.7/470/41.78 22.7/308/41.78 373.6/215/1135 373.6/287.3/100 373.6/316/100 (Ksc/ºc/T/hrr)
CONDENSOR DEAERATOR CASCADE DRIP & VENT SYSTEM HPH-8 HPH-7 HPH-6
HP bypass spray 100 % BYPASS 50% BYPASS HPH-8A HPH-7A HPH-6A To TDBFP AUX PRDS SPRAY HPH-8A HPH-7A HPH-6A ECO INLET TO SH SPRAY 3-WAY VALVE BFP dish header
TO DRAIN BYPASS TO BOILER FROM BFP HP HEATERS Change over line close INITIAL FILL LINE close DRAIN LINE
BYPASS TO BOILER FROM BFP HP HEATERS DRAIN LINE Change over line close
INITIAL FILL LINE
HPH LEVEL HI-HI
Self cleaning type Model: S 871 Make: Alfa laval
Overhaul was carried out by 5S
Which saved valuable time in retrieval of spares and materials during box up and avoided un necessary mess up due to intermixing and loss of materials Completed in 21 days and saved 3 days of original schedule