NEIGHBORHOOD STORAGE PROJECT Hibbard Park & Community Rec - - PowerPoint PPT Presentation

neighborhood storage project
SMART_READER_LITE
LIVE PREVIEW

NEIGHBORHOOD STORAGE PROJECT Hibbard Park & Community Rec - - PowerPoint PPT Presentation

NEIGHBORHOOD STORAGE PROJECT Hibbard Park & Community Rec Center Underground Storage PRESENTATION OUTLINE 1. Summary of Hibbard Park Flood Storage 2. Community Rec Center Future Facility Assessment 3. Underground Storage Configuration 4.


slide-1
SLIDE 1

NEIGHBORHOOD STORAGE PROJECT

Hibbard Park & Community Rec Center Underground Storage

slide-2
SLIDE 2

PRESENTATION OUTLINE

  • 1. Summary of Hibbard Park Flood Storage
  • 2. Community Rec Center Future Facility Assessment
  • 3. Underground Storage Configuration
  • 4. Next Steps
slide-3
SLIDE 3

HIBBARD PARK FLOOD STORAGE

Underground Flood Storage = 10 acre-ft

slide-4
SLIDE 4

HIBBARD PARK SITE PLAN

slide-5
SLIDE 5

HIBBARD PARK PROGRAM ANALYSIS

slide-6
SLIDE 6

HIBBARD PARK PROGRAM DIAGRAM

slide-7
SLIDE 7

CONCEPT FACILITY

ONE FLOOR

slide-8
SLIDE 8

EXISTING FACILITY

slide-9
SLIDE 9

CONCEPT FACILITY REVISED

SCHEME A – TWO FLOORS

slide-10
SLIDE 10

CONCEPT FACILITY REVISED

SCHEME B – TWO FLOORS

slide-11
SLIDE 11

CONCEPT FACILITY REVISED

SCHEME C – TWO FLOORS

slide-12
SLIDE 12

UNDERGROUND STORAGE CONFIGURATION

  • Underground Storage
  • Volume = 10 acre-ft
  • Height of system = 5’8”
  • Average depth of cover ≈2 ft
  • No pump station required
  • Tree Survey
  • Completed March 2019
  • Approximately 40 trees within

footprint

  • Opportunities for

replacement on perimeter

  • Existing Amenities Replaced
  • Skate park, parking, open

space

  • Site drainage improvements
  • Geotechnical Analysis
  • Silty Clay/Lean Clay Soils
  • Groundwater varies
slide-13
SLIDE 13

NEXT STEPS

  • Continue discussions with Park District
  • Site meeting on April 24, 2019
  • 30% design development of underground storage
slide-14
SLIDE 14

END OF PRESENTATION

QUESTIONS?