- Mt. Hayes
Liquefied Natural Gas Storage Facility Terasen Gas (Vancouver Island) Inc.
Stakeholder Workshop for the CPCN Application
June 27th, 2007 Coast Bastion Inn, Nanaimo BC
B-2
Mt. Hayes Liquefied Natural Gas Storage Facility Terasen Gas - - PowerPoint PPT Presentation
B-2 Mt. Hayes Liquefied Natural Gas Storage Facility Terasen Gas (Vancouver Island) Inc. Stakeholder Workshop for the CPCN Application June 27 th , 2007 Coast Bastion Inn, Nanaimo BC Overview Peak shaving storage facility located near
June 27th, 2007 Coast Bastion Inn, Nanaimo BC
B-2
2
near Ladysmith on Vancouver Island
current facility located on Tilbury Island in Delta BC
via existing pipeline system during summer months, stored as LNG and then sent out during winter peaking periods
proposal that was approved by the BCUC but subsequently deferred due to termination of Duke Point Power Project
Proposed LNG Storage facility
3
Capacity 1.5 Bcf Liquefaction 7.5 MMcfd Deliverability 150 MMcfd Capital Investment $176 million Target In-Service Date 2011
4
Introduction Cynthia Des Brisay Director, Business Development & Resource Planning Project Overview and Description Guy Wassick, Project Manager Gas Supply Portfolio Cynthia Des Brisay TGVI System Benefits Edmond Leung Project Assessment Manager Economic Justification Dave Perttula Manager, Market Development Regulatory Process Review & Next Steps Tom Loski Director, Regulatory Affairs Questions / Discussion All
5
6
Terasen Gas (Vancouver Island) Inc Terasen Gas (Whistler) Inc Terasen Gas (Vancouver Island) Inc Terasen Gas (Whistler) Inc Terasen Storage Inc Terasen Energy Services Inc LNG Storage Facility
Shared Services Agreements
Terasen Inc A Kinder Morgan Company Terasen Inc A Fortis Company Terasen Gas Inc Terasen Gas (Vancouver Island) Inc Terasen Gas (Whislter) Inc Terasen Gas Inc Terasen Gas (Vancouver Island) Inc Terasen Gas (Whistler) Inc Terasen Storage Ltd Terasen Energy Services Inc Terasen Gas Inc Terasen Gas Inc
7
– Provides long term storage capacity to meet core market peak day growth on Vancouver Island and the Lower Mainland – Reduces dependence on storage facilities located in Washington and Oregon states to serve residential and commercial customers – Avoids transmission facility additions on the Vancouver Island transmission system and the Coastal Transmission System – On-System storage facility enhances reliability and security of supply – Allows the utilities to better manage future industrial and generation demand uncertainty (Island Cogen and Burrard Thermal)
8
Optimization and Allocation
Deliverability
1.5 bcf 150 mmcfd
0.5 bcf 50 mmcfd
1.0 bcf 100 mmcfd
Guy Wassick LNG Project Manager
10
11
cooled until it condenses into a clear liquid.
at atmospheric pressure in a “thermos” like storage container.
1/600th of its original volume as a gas.
becomes a lighter-than-air gas and is flammable only when it occurs in a 5% to 15% concentration in air.
12
LNG storage with liquefaction and vaporization capability; send out on peak days; connected to a pipeline system
Large storage capacity and continuous operation;
tankers
sendout to a pipeline system
For peaking or smaller base load send out; supplied by truck transport; with vaporization capability only
13
14
15
16
17
(freezer)
(thermos)
(hot water tank)
Preheater Boil-off Compressor LNG Vaporizers LNG Tank LNG Tanker Unloading & Loading to Transmission Pipeline System LNG Pumps Feed Gas Tail Gas Dessication Liquefaction
18
19
LNG Storage
– Storage 1-1.5 bcf – Send-out 100-150 mmcf/d – Liquefaction 5 – 7.5mmcf/d
Ladysmith, West of
center on Southern Vancouver Island
20
21
22
23
24
Property to be purchased 142 ha
25
42 ha
Rezoned Area
26
Plant area 12 ha
27
Exclusion Zone
Total area 82 ha
28
29
Impact Significance* Impact Topic Unmitigated Mitigated PHYSICAL ENVIRONMENT
N N
N N
S N
N N BIOLOGICAL ENVIRONMENT
S N
N N
N N
N = Not Significant S = Significant B = Beneficial N/A = Not applicable, project design and construction standards incorporate these requirements U = Unknown due to lack of information
30
Impact Significance* Impact Topic Unmitigated Mitigated HUMAN ENVIRONMENT
N N
N N
N N
N N
N N
N N
N N
N N
B B
N = Not Significant S = Significant B = Beneficial N/A = Not applicable, project design and construction standards incorporate these requirements U = Unknown due to lack of information
31
Impact Significance* Impact Topic Unmitigated Mitigated FACILITY AND PUBLIC SAFETY
N/A N
N/A N
N/A N
N/A N
N/A N
N/A N CUMULATIVE EFFECTS
N N
N N
N = Not Significant S = Significant B = Beneficial N/A = Not applicable, project design and construction standards incorporate these requirements U = Unknown due to lack of information
32
33
34
35
36
37
38
39
40
ID Task Name Duration 1 BCUC 5.5 mons 2 Application Preparation 2 mons 3 Application Approval 3.5 mons 4 UPDATING PHASE 5 mons 5 LNG Facility EPC 5 mons 6 Contract Negotiation 2 mons 7 Design Development 2 mons 8 Geotechnical Evaluation 2 mons 9 Cost Development 3 mons 10 Owner's Project Work 3 mons 11 Power Line Update 2 mons 12 Site Prep Design/Contract 3 mons 13 ESR Update 2 mons 14 APPROVALS UPDATING 3 mons 15 OGC - Facility 3 mons 16 Prov Ministries - Permits 2 mons 17 DECISION TO PROCEED 0 mons 18 ONGOING COMMUNICATION 49 mons 19 LAND 3 mons 20 Exercise Site Option 0 mons 21 R-O-W Acquisition 3 mons 22 CONSTRUCTION 41 mons 23 LNG Facility Project Work 12 mons 24 Site Grading 4 mons 25 Road Improvements 3 mons 26 R-O-W Preparation 3 mons 27 Power Line 3 mons 28 LNG Facility EPC 37 mons 29 Facility EPC On-Site 30 mons 30 Commission & Test 3 mons 31 Final Acceptance 4 mons 32 FILLING 5 mons 33 Operation by TGVI 5 mons 34 RESTORATION 3 mons Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 2007 2008 2009 2010 2011
41
ID Task Name Duration 1 BCUC 5.5 mo 2 Application Preparation 2 mo 3 Application Approval 3.5 mo 4 UPDATING PHASE 3 mon 5 Design & Cost Update 2 mo 6 ESR Update 2 mo 7 OGC - Facilities 2 mo 8 Prov Ministries - Permits 2 mo 9 DECISION TO PROCEED - LNG 0 mo 10 DECISION TO PROCEED 0 mo 11 ONGOING COMMUNICATION 35 mo 12 LAND 3 mon 13 R-O-W Acquisition 3 mo 14 TGVI PROJECT WORK 40 mo 15 R-O-W's Preparation 3 mo 16 Pipelines 6 mo 17 Gas Msmt/Odour Faciity 6 mo 18 Reverse Flow Facilities 6 mo Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4 2007 2008 2009 2010 2011
42
43
P10 P50 P90 1.5 Bcf LNG Facility $154.9 $165.0 $185.7 1.0 Bcf LNG Facility $116.3 $124.9 $140.8 P10 P50 P90 1.5 Bcf LNG Facility $155.7 $166.0 $186.8 1.0 Bcf LNG Facility $116.8 $125.7 $141.6 LNG Storage Facility Costs (Direct 2007$ millions) LNG Storage Facility Costs (AsSpent$ millions)
44
P10 P50 P90 Pipelines $6.0 $6.4 $6.8 Msmt & Odour Stn $0.8 $0.8 $0.9 Reverse Flow Facilities $2.1 $2.4 $2.7 Project Management $0.1 $0.1 $0.1 Contingency $0.5 $1.0 $1.5 Projects for 1.5 Bcf Facility $9.5 $10.7 $12.0 Projects for 1.0 Bcf Facility $6.3 $7.1 $7.9 P10 P50 P90 Projects for 1.5 Bcf Facility $10.4 $11.6 $13.2 Projects for 1.0 Bcf Facility $6.9 $7.8 $8.7 System Facilities Costs (AsSpent$ millions) System Facilities Costs (Direct 2007$ millions)
45
46
47
48
Total construction expenditures $165 Million
indirect/induced)
indirect/induced) Facility operation provides;
50
– Meeting Future Peak Load Growth – Infrastructure projects have long lead times
– Current and Future – Best Fit for TGI/TGVI
51
storage resources, supply basins.
associated with a single source.
NWGA
region.
advance).
52
Design Peak Day Requirements
Pipeline for average day supply
contracts and upstream storage for winter average day
efficient for short term peaks Provide security of supply in event of failures Pipeline capacity sets a price cap
1 2 3 4 5 6 7 8 9 1 ,0 1 ,1 1 ,2 1 ,3 1 ,4 1 / 1 1 / 2 6 1 5 / 1 1 / 2 6 2 9 / 1 1 / 2 6 1 3 / 1 2 / 2 6 2 7 / 1 2 / 2 6 1 / 1 / 2 7 2 4 / 1 / 2 7 7 / 2 / 2 7 2 1 / 2 / 2 7 7 / 3 / 2 7 2 1 / 3 / 2 7 4 / 4 / 2 7 1 8 / 4 / 2 7 2 / 5 / 2 7 1 6 / 5 / 2 7 3 / 5 / 2 7 1 3 / 6 / 2 7 2 7 / 6 / 2 7 1 1 / 7 / 2 7 2 5 / 7 / 2 7 8 / 8 / 2 7 2 2 / 8 / 2 7 5 / 9 / 2 7 1 9 / 9 / 2 7 3 / 1 / 2 7 1 7 / 1 / 2 7 3 1 / 1 / 2 7 TJ/d
P e a k in g R e s
rc e s M a rk e t A re a S to ra g e /S h a p e d P ip e lin e C a p a c ity P ip e lin e C a p a c ity D e s ig n N
a l
D e s ig n P e a k D a y
53
year need combination of pipe/incremental shorter duration resources…..
– Growth in peak day requirements is higher than average day. – All utilities in our region face need to add new resources to meet growth. – Availability of Shaped Resources vs baseload – Large infrastructure projects require longer lead times
1 2 3 4 5 6 7 8 9 1 ,0 1 ,1 1 ,2 1 ,3 1 ,4 1 / 1 1 / 2 6 1 5 / 1 1 / 2 6 2 9 / 1 1 / 2 6 1 3 / 1 2 / 2 6 2 7 / 1 2 / 2 6 1 / 1 / 2 7 2 4 / 1 / 2 7 7 / 2 / 2 7 2 1 / 2 / 2 7 7 / 3 / 2 7 2 1 / 3 / 2 7 4 / 4 / 2 7 1 8 / 4 / 2 7 2 / 5 / 2 7 1 6 / 5 / 2 7 3 / 5 / 2 7 1 3 / 6 / 2 7 2 7 / 6 / 2 7 1 1 / 7 / 2 7 2 5 / 7 / 2 7 8 / 8 / 2 7 2 2 / 8 / 2 7 5 / 9 / 2 7 1 9 / 9 / 2 7 3 / 1 / 2 7 1 7 / 1 / 2 7 3 1 / 1 / 2 7 TJ/d
P e a k in g R e s
rc e s M a rk e t A re a S to ra g e /S h a p e d P ip e lin e C a p a c ity P ip e lin e C a p a c ity D e s ig n
D e s ig n P e a k D a y
54
Upstream Supply/Storage Pipeline Capacity Market Area Storage On System Resources Pipeline Capacity
55
– JPS Expansion
for avg term 32 years
Expensive (30-50% of Firm NWP Rate)
– Mist Expansion
Expansions
– Tilbury LNG Storage Expansion – Proposed Mount Hayes Storage
On System Storage
56
based on
– Incremental JPS Storage based
– Redelivery based on discounted NWP TF1 transport rate
– T-South tolls with and without mitigation – Mitigation based on full recovery
JPS + TF-1@30% JPS + TF-1@50% T-South (with mitigation) T-South (no mitigation)
Equivalent Cost for 10 Day Service
$180 $115 $131 $137
Annual Cost of Market Area Storage Deliverability to Huntingdon ($ per GJ)
57
58
Infrastructure projects have long lead times
– No Expansion on T-South in the near term – No Expansion North of JPS scheduled
– JPS Expansion and potential Mist Expansion – Firm redelivery will cost more than existing contracts
– Security of Supply – Value of resource comparable to cost of Off System Market Area Storage and/or Westcoast Pipe
59
– Incremental JPS Storage based on recent expansion
– Redelivery based on discounted NWP TF1 transport rate
– T-South tolls with and without mitigation – Mitigation based on full recovery of demand charges in winter
JPS + TF-1@30% JPS + TF-1@50% T-South (with mitigation) T-South (no mitigation)
Equivalent Cost for 10 Day Service
$180 $99 $130 $132
Annual Cost of Market Area Storage Deliverability to Huntingdon ($ per GJ)
60
61
62
63
FRASER VALLEY
VANCOUVER
Langley Comp Stn
Nichol-Coquitlam Loop
64
Coquitlam Stn Texada Stn Pt. Mellon Stn
65
100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1 / 1 1 / 2 6 1 5 / 1 1 / 2 6 2 9 / 1 1 / 2 6 1 3 / 1 2 / 2 6 2 7 / 1 2 / 2 6 1 / 1 / 2 7 2 4 / 1 / 2 7 7 / 2 / 2 7 2 1 / 2 / 2 7 7 / 3 / 2 7 2 1 / 3 / 2 7 4 / 4 / 2 7 1 8 / 4 / 2 7 2 / 5 / 2 7 1 6 / 5 / 2 7 3 / 5 / 2 7 1 3 / 6 / 2 7 2 7 / 6 / 2 7 1 1 / 7 / 2 7 2 5 / 7 / 2 7 8 / 8 / 2 7 2 2 / 8 / 2 7 5 / 9 / 2 7 1 9 / 9 / 2 7 3 / 1 / 2 7 1 7 / 1 / 2 7 3 1 / 1 / 2 7 TJ/d
Peaking Resources Market Area Storage/Shaped Pipeline Capacity Pipeline Capacity Design
Design Peak Day
66
TGVI Design Day Forecast
50 100 150 200 250
2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Year beginning November
Terajoules per Day TGVI Core Squamish Whistler VIGJV ICP
System Capacity
67
Coquitlam Stn Texada Stn Pt Mellon Stn Squamish Coquitlam Sechelt Dunsmuir Crofton Nichol –Coquitlam Loop in the Coastal Transmission System Watershed Loop
68
Coquitlam Stn Texada Stn Port Mellon Stn
Coquitlam Squamish Dunsmuir
69
– Weather forecast error ranging from 1 to 3 oC – LNG to make up shortfall – No need to follow 3rd party nomination cycle
– Currently relies on line-pack to meet transient demands, to manage pressure upset from unplanned compressor shutdown or valve closure – LNG can respond quickly with lower optimum line-pack
– Currently O/M windows requiring pipeline isolation limited by line- pack available to downstream customers – LNG would provide a secondary source of supply to extend O/M windows.
70
Coquitlam Stn Texada Stn Pt Mellon Stn
71
Coquitlam Stn Texada Stn Pt Mellon Stn
72
Summary
Transmission System
day growth
line-pack requirement, increase O&M windows)
73
74
– Cost of Service of the LNG Facility – Gas Supply benefits for gas customers of TGVI and TGI
– TGVI System Benefits
greatly reduced with the LNG facility.
– Potential TGI System Benefits
75
transmission and distribution system
methodology with adjustments
– Fair return for investment (TGVI ROE + 50 BP) – Adjusted depreciation schedule to reduce up front costs
2.1% 2.1% 2.1% 2.2% 2.2% 2.2% 2.3% 2.4% 2.5% 2.6% 2.8% 3.0% 3.1% 3.3% 3.5% 3.8% 4.0% 4.3% 4.6% 4.9% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% $0 $1 $2 $3 $4 $5 $6 $7 $8 $9 $10 2 1 1 2 1 3 2 1 5 2 1 7 2 1 9 2 2 1 2 2 3 2 2 5 2 2 7 2 2 9 2 3 1 2 3 3 2 3 5 2 3 7 2 3 9 2 4 1 $M illions Adjusted Depreciation Straight Line Depreciation
76
156 125 165 230 163 117 230 148 50 100 150 200 250 15 Year 25 Year 15 Year 25 Year Present Value Straight Line Depreciation Adjusted Depreciation
$Millions
77
Based on to 0.5 bcf 50 mmcfd
Based on 1.0 bcf 100 mmcfd
$12.6 M $1.9 M $6.3 M Annual Cost of Service Year 2015
Allocation to gas portfolios based on alternative peaking resource Allocation to system capacity compares to P&C Alternative Annual Revenue requirement based
78
5 10 15 20 25 2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030 $ Millions LNG Portfolio Pipe & Compression Portfolio
79
P&C Portfolio LNG Portfolio P&C Portfolio LNG Portfolio 115 21 72 15 230 163 (68) (48) (135) (97) 115 49 72 33
15-Year Evaluation Period
48 14 36 11 148 117 (45) (36) (90) (72) 48 27 36 21 6.20% 10% TGVI System Costs TGVI LNG Costs ($ Millions) 25-Year Evaluation Period TGVI Gas Supply Benefit Storage Revenues from TGI Storage Revenues from TGI Net Portfolio Cost Net Portfolio Cost TGVI System Costs TGVI LNG Costs TGVI Gas Supply Benefit
Baseline Scenario
80
Scenario Assumptions Baseline Scenario
Baseline Demand scenario (no firm service to ICP)
Base + ICP Scenario
scenario which includes firm service to ICP
Low Core Demand Scenario
firm service to ICP
High Cost Scenario
Baseline Demand
Upside Case
+ ICP Demand Scenario
81
$0 $20 $40 $60 $80 $100 $120 $140 $160 $ Millions Pipe & Compression Portfolio LNG Portfolio 25 Year 15 Year 15 Year 25 Year Baseline Scenario High Cost Scenario 115 49 48 27 135 74 57 43
82
20 40 60 80 100 120 140 160 180 Baseline Scenario Base + ICP Demand Scenario Low Core Demand Scenario High Cost Scenario Upside Scenario $ Millions Pipe & Compression Portfolio LNG Portfolio 66 69 32 61 87
Net LNG Benefit Net LNG Benefit Net LNG Benefit Net LNG Benefit Net LNG Benefit
Present Value @ 6.2%, 25 Year Evaluation Period
83
Levelized Allocated Average Delivery Cost Impact Baseline Scenario - Core Market
7.2 7.3 7.4 7.5 7.6 7.7 7.8 7.9 8.0 8.1 $ / GJ 15 Year Evaluation Period 25 Year Evaluation Period Pipe & Compression LNG
84
LNG LNG Pipe & LNG LNG Pipe & Approach 1 Approach 2 Compression Approach 1 Approach 2 Compression
Core Market 7.65 7.52 7.75 7.77 7.63 8.02 Firm Transport 0.96 1.14 1.17 0.94 1.13 1.17 Core Market 7.35 7.08 7.56 7.32 Firm Transport 0.83 1.07 0.85 1.08 Impact of Firm Service to ICP to 2018 Levelized Allocated Cost 2011 - 2032 ($/GJ) Baseline Scenario Levelized Allocated Cost 2011 - 2022 ($/GJ)
Comparison of Levelized Allocated Average Delivery Costs Excluding Gas Costs
85
86
– Pursuant to Section 45 of the Utilities Commission Act – TGVI
– Pursuant to Section 61 of Act – TGVI – Pursuant to Section 71 of Act – TGI
– Pursuant to Section 56 of Act – TGVI
87
1. Application Submitted to BCUC Tuesday, June 5 2. BCUC Procedural Order No. G-63-07 Friday, June 8 3. Public Notice Friday, June 15 4. Intervenor Comments on Procedure Monday, June 25 5. Workshop Wednesday, June 27
88
TGVI MT. HAYES LNG STORAGE FACILITY WORKSHOP
Held in Nanaimo on June 27, 2007 At the Coast Bastion Inn Terasen Presenters and Attendees