monthly stakeholder meeting presentation october 21 2019
play

Monthly Stakeholder Meeting Presentation October 21, 2019 This - PowerPoint PPT Presentation

Monthly Stakeholder Meeting Presentation October 21, 2019 This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any


  1. Monthly Stakeholder Meeting Presentation October 21, 2019

  2. This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this presentation by anyone or entity other than FDOT staff is not official. Any questions can be sent to FDOT- D6PIO@dot.state.fl.us. This presentation may not be altered. 2

  3. CURRENT DESIGN STATUS OVERALL DESIGN STATUS • • Structures – 45% • Maintenance of Traffic (MOT) – 55% Roadway - 90% MAJOR DESIGN SUBMITTALS TO DATE: • Roadway plans for I-95 north segment (segment 2A) complete • Roadway plans for I-95 south segment (segment 2B) 90% complete • Roadway plans for I-395 complete • Surface street plans complete • Phase I TCP plans complete for I-95, I-395 and SR 836 • Phase 2 and 3 TCP plans for I-95, 90% complete • 60% signature bridge plans • TCP generic plans and detour routes complete 3

  4. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES * This schedule does not reflect days added to the contract for holidays, weather days or special events • Construction of new drainage, median concrete barrier wall and pavement replacement on I-95 between NW 17 Street and NW 29 Street (Ongoing) • Ongoing full NB and SB I-95 closures for overhead sign structure including two DMS 4

  5. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES * This schedule does not reflect days added to the contract for holidays, weather days or special events 5

  6. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES * This schedule does not reflect days added to the contract for holidays, weather days or special events 6

  7. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES * This schedule does not reflect days added to the contract for holidays, weather days or special events 7

  8. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES * This schedule does not reflect days added to the contract for holidays, weather days or special events Foundation work on northbound I-95 bridge approaching ramp to I-195 (Ongoing) 8

  9. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Ongoing work on eastbound SR 836 from NW 17 Avenue to the Miami River and from NW 12 Avenue to I-95 for bridge widening. 9

  10. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES 10

  11. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES 11

  12. ONGOING LANE THREE MONTH LOOK CLOSURES AHEAD SR 836 UPCOMING CONSTRUCTION ACTIVITIES ANTICIPATED NIGHTTIME LANE CLOSURES ON SR 836 CORRIDOR: • Lane closures along eastbound and westbound SR 836 • NW 17 Avenue under SR 836 • Eastbound SR 836 ramp to NW 17 Avenue • Eastbound SR 836 ramp to northbound I-95 • Arterial Roads under SR 836 12

  13. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES • Implemented a traffic shift 1 on westbound I-395 from 2 NE 1 Avenue to I-95. Traffic has been shifted to the left • Ongoing demolition of 2 outside I-395 on-ramp that was closed as part of the NE 12 Street Closure 1 13

  14. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES * This schedule does not reflect days added to the contract for holidays, weather days or special events 14

  15. UPCOMING & ONGOING I-395 BRIDGE WORK CONSTRUCTION ACTIVITIES 1. Demolition of median separator between the 3 eastbound I-395 mainline and local road connector (Ongoing) Concrete closure pour between the eastbound I-395 mainline and local road connector (Ongoing) 2 2. Removal of median separator between the eastbound I-395 mainline and the westbound 4 SR 836 UPCOMING CONSTRUCTION ACTIVITIES mainline (November) 3. Begin construction on westbound outside, local road lanes. Foundations will begin at NE 2 Avenue and move towards the west (October/November) 1 4. Begin construction on eastbound, local road lanes. Foundations will begin at NW 1 Avenue and move towards the west (November) 15

  16. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES * This schedule does not reflect days added to the contract for holidays, weather days or special events 16

  17. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES * This schedule does not reflect days added to the contract for holidays, weather days or special events Auger Cast Pile Load Testing Scheduled - Ongoing 17

  18. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES * This schedule does not reflect days added to the contract for holidays, weather days or special events 18

  19. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES * This schedule does not reflect days added to the contract for holidays, weather days or special events 19

  20. UPCOMING CONSTRUCTION THREE MONTH LOOK ACTIVITIES AHEAD SR 836 UPCOMING CONSTRUCTION ACTIVITIES Bridge foundation work for westbound Signature Bridge (December) 20

  21. ONGOING LANE THREE MONTH LOOK CLOSURES AHEAD SR 836 UPCOMING CONSTRUCTION ACTIVITIES ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR: • Southbound I-95 and northbound I-95 ramps to eastbound I-395 • Lane closures along I-395 mainline and connector road • Lane closures along Biscayne Boulevard • Arterial roads under I-395 • Shift traffic on eastbound I-395 mainline to the right from I-95 to approximately NW 1 Avenue to allow for the removal of the eastbound and westbound traffic separator (late October) 21

  22. TRAFFIC MANAGEMENT SYSTEM Smart Work Zone Management System (SWZMS) - The project is N implementing a SWZMS that will utilize Intelligent Transportation System (ITS) devices such as traffic cameras, data collection devices and portable message signs to: • Provide drivers with real-time travel information; • Encourage motorists to take alternate routes; • Clear incidents more quickly, thereby reducing secondary incidents; and • Make work zones safer for highway workers and motorists. 22

  23. COMMUNITY OUTREACH PROJECT WEBSITE • www.i-395miami.com • Sign-up for project alerts/updates Lane closure information Upcoming construction activities Presentations • Calendar of events OUTREACH OFFICE IN THE OVERTOWN COMMUNITY • 1035 NW 3 Avenue, Miami, Florida 33136 STAKEHOLDER MEETINGS • Ongoing individual stakeholder meetings and presentations • Next stakeholder meeting – November 18, 2019 23

  24. THANK YOU! www.i-395miami.com Contact: Oscar Gonzalez 786-280-0983 OGonzalez@mrgmiami.com 24

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.