SLIDE 1
Monthly Stakeholder Meeting Presentation October 21, 2019
SLIDE 2 2
This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this presentation by anyone or entity
- ther than FDOT staff is not official. Any questions can be sent to FDOT-
D6PIO@dot.state.fl.us. This presentation may not be altered.
SLIDE 3 3
CURRENT DESIGN STATUS
- Roadway plans for I-95 north segment (segment 2A) complete
- Roadway plans for I-95 south segment (segment 2B) 90% complete
- Roadway plans for I-395 complete
- Surface street plans complete
- Phase I TCP plans complete for I-95, I-395 and SR 836
- Phase 2 and 3 TCP plans for I-95, 90% complete
- 60% signature bridge plans
- TCP generic plans and detour routes complete
OVERALL DESIGN STATUS
- Roadway - 90%
- Structures – 45%
- Maintenance of Traffic (MOT) – 55%
MAJOR DESIGN SUBMITTALS TO DATE:
SLIDE 4 * This schedule does not reflect days added to the contract for holidays, weather days or special events
4
- Construction of new drainage, median concrete barrier wall and pavement replacement on I-95 between
NW 17 Street and NW 29 Street (Ongoing)
- Ongoing full NB and SB I-95 closures for overhead sign structure including two DMS
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES
SLIDE 5
* This schedule does not reflect days added to the contract for holidays, weather days or special events
5
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES
SLIDE 6
* This schedule does not reflect days added to the contract for holidays, weather days or special events
6
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES
SLIDE 7
* This schedule does not reflect days added to the contract for holidays, weather days or special events
7
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES
SLIDE 8
* This schedule does not reflect days added to the contract for holidays, weather days or special events
8
Foundation work on northbound I-95 bridge approaching ramp to I-195 (Ongoing) UPCOMING & ONGOING CONSTRUCTION ACTIVITIES
SLIDE 9
9
Ongoing work on eastbound SR 836 from NW 17 Avenue to the Miami River and from NW 12 Avenue to I-95 for bridge widening. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES
SLIDE 10
10
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES
SLIDE 11
11
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES
SLIDE 12 SR 836 UPCOMING CONSTRUCTION ACTIVITIES
12
ANTICIPATED NIGHTTIME LANE CLOSURES ON SR 836 CORRIDOR:
- Lane closures along eastbound and westbound SR 836
- NW 17 Avenue under SR 836
- Eastbound SR 836 ramp to NW 17 Avenue
- Eastbound SR 836 ramp to northbound I-95
- Arterial Roads under SR 836
ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD
SLIDE 13 13
- Implemented a traffic shift
- n westbound I-395 from
NE 1 Avenue to I-95. Traffic has been shifted to the left
- Ongoing demolition of
- utside I-395 on-ramp that
was closed as part of the NE 12 Street Closure
1 2
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES
1 2
SLIDE 14
* This schedule does not reflect days added to the contract for holidays, weather days or special events
14
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES
SLIDE 15 SR 836 UPCOMING CONSTRUCTION ACTIVITIES
15
1. Demolition of median separator between the eastbound I-395 mainline and local road connector (Ongoing) Concrete closure pour between the eastbound I-395 mainline and local road connector (Ongoing) 2. Removal of median separator between the eastbound I-395 mainline and the westbound mainline (November) 3. Begin construction on westbound outside, local road lanes. Foundations will begin at NE 2 Avenue and move towards the west (October/November) 4. Begin construction on eastbound, local road
- lanes. Foundations will begin at NW 1
Avenue and move towards the west (November)
I-395 BRIDGE WORK
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES
3 2 1 4
SLIDE 16
* This schedule does not reflect days added to the contract for holidays, weather days or special events
16
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES
SLIDE 17
* This schedule does not reflect days added to the contract for holidays, weather days or special events
17
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Auger Cast Pile Load Testing Scheduled - Ongoing
SLIDE 18
* This schedule does not reflect days added to the contract for holidays, weather days or special events
18
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES
SLIDE 19
* This schedule does not reflect days added to the contract for holidays, weather days or special events
19
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES
SLIDE 20
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
20
Bridge foundation work for westbound Signature Bridge (December) UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD
SLIDE 21 SR 836 UPCOMING CONSTRUCTION ACTIVITIES
21
ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR:
- Southbound I-95 and northbound I-95 ramps to eastbound I-395
- Lane closures along I-395 mainline and connector road
- Lane closures along Biscayne Boulevard
- Arterial roads under I-395
- Shift traffic on eastbound I-395 mainline to the right from I-95 to
approximately NW 1 Avenue to allow for the removal of the eastbound and westbound traffic separator (late October)
ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD
SLIDE 22
- Provide drivers with real-time
travel information;
- Encourage motorists to take
alternate routes;
- Clear incidents more quickly,
thereby reducing secondary incidents; and
- Make work zones safer for
highway workers and motorists. Smart Work Zone Management System (SWZMS) - The project is implementing a SWZMS that will utilize Intelligent Transportation System (ITS) devices such as traffic cameras, data collection devices and portable message signs to:
TRAFFIC MANAGEMENT SYSTEM
22
N
SLIDE 23 23
COMMUNITY OUTREACH
PROJECT WEBSITE
- www.i-395miami.com
- Sign-up for project alerts/updates
Lane closure information Upcoming construction activities Presentations
OUTREACH OFFICE IN THE OVERTOWN COMMUNITY
- 1035 NW 3 Avenue, Miami, Florida 33136
STAKEHOLDER MEETINGS
- Ongoing individual stakeholder meetings and presentations
- Next stakeholder meeting – November 18, 2019
SLIDE 24
786-280-0983 OGonzalez@mrgmiami.com Contact: Oscar Gonzalez
www.i-395miami.com
THANK YOU!
24