Mobuoy Remediation Project Todays Ask of Council Council to endorse - - PowerPoint PPT Presentation

mobuoy remediation project today s ask of council council
SMART_READER_LITE
LIVE PREVIEW

Mobuoy Remediation Project Todays Ask of Council Council to endorse - - PowerPoint PPT Presentation

Mobuoy Remediation Project Todays Ask of Council Council to endorse engagement with DAERA/ NIEA to work in Partnership to co-design future development plans Overview Site Overview Criminal Case Mobuoy Working Group Follow up Waste


slide-1
SLIDE 1

Mobuoy Remediation Project

slide-2
SLIDE 2

Today’s Ask of Council Council to endorse engagement with DAERA/ NIEA to work in Partnership to co-design future development plans

slide-3
SLIDE 3

Overview

Site Overview Criminal Case Mobuoy Working Group – Follow up Waste Regulation Site History Protecting the Drinking Water Remediation Options Appraisal DAERA / Council Partnership to develop Site Vision Q&A

slide-4
SLIDE 4

Mobuoy Criminal Case

Ongoing criminal case; Trial date set for 7th Sept 2020; Some project information is evidence in the criminal case; We remain limited in what information we are able to share at this point.

slide-5
SLIDE 5

Council Mobuoy Working Group - Summary of Issues Raised

  • 1. Provide an explanation of what happened & the extent of investigation;

knowledge of extent and type of waste present;

  • 2. Provide an update on the proposed Public Inquiry into all illegal waste in N.

Ireland, what was done?

  • 3. How to ensure Polluter Pays Principle is adopted;
  • 4. What are the plans to deal with waste? What decisions have been taken in

respect to remediation of the site? Has a preferred option been agreed? 5 Will drinking water will be safe? Can this be guaranteed without removing the waste?

  • 6. Cost estimates appear to be wide ranging; can the Department confirm the

estimated costs to remediate the site? 7.What would happen if the waste started to leach?

  • 8. What are repercussions for the proposed A6 (Drumahoe to Stradreagh)?
  • 9. There are reports the water treatment plant has been moved up above

Mobuoy.

slide-6
SLIDE 6

Response to Failure in Waste Regulation

Implementation of Mills and CJI Action plans; Remediation Strategy for Mobuoy under development; Pro-active intelligence led approach to tackling waste crime under development; Regulatory Transformation Programme; Increased partnership working with councils to manage waste; Waste promotion and development of the Circular Economy;

slide-7
SLIDE 7

What's been achieved:

Remediation Enforcement Strategy Cost Recovery Protocol and updated guidance Enforcement Technical Advisory Group Remediation enforcement through Environmental Liability (Prevention and Remediation) Regulations (NI) 2009 process

Enforcement

slide-8
SLIDE 8

Protecting Drinking Water

slide-9
SLIDE 9

NI Water’s abstraction from the River Faughan Raw water is abstracted from the River Faughan at approx. 2 miles downstream of the landfill site; Oil and Ammonia monitors with alarms ensure automatic shutdown;

slide-10
SLIDE 10

Drinking Water Quality - how do we ensure we provide safe, clean drinking water?

slide-11
SLIDE 11

Is Our Water Safe to Drink? YES The raw water and final water quality is monitored 24/7 at the Water Treatment Works (WTW); Daily analytical testing of raw water and final water samples; Daily samples are taken at customer taps to monitor water quality; Results are assessed against the requirements of the Drinking Water Regulations.

slide-12
SLIDE 12

Contingency

Contingency measures in place to maintain continued supply of high quality drinking water; Contingency Plans in place for all of NI Water WTWs; Interconnectivity to two

  • ther WTWs to

maintain supply to customers.

NI Water’s Contingency Measures

slide-13
SLIDE 13

Objectives of the Mobuoy Monitoring Programme

To protect water quality of the River Faughan; To determine the impacts of the waste on the underlying groundwater body and surface water bodies on site; To update the risk assessments and support NIEA’s enforcement actions; To inform the need for mitigation actions in advance of site remediation.

slide-14
SLIDE 14

Overview of Mobuoy Monitoring Programme

Programme is supported with new dedicated resources within NIEA’s laboratories; Leachate monitoring and groundwater monitoring; Surface water monitoring; Groundwater level monitoring; Landfill gas monitoring.

slide-15
SLIDE 15

Developing the Remediation Strategy - Options Appraisal

slide-16
SLIDE 16

Protect NI Water’s raw water abstraction and supply; Protect water quality of the River Faughan; Improve and remedy environmental damage; Reduce landfill gas risks to protect site users; Timely and continued engagement with stakeholders.

Remediation Objectives

slide-17
SLIDE 17

Appraisal of Remediation Options – Sustainable Remediation Forum UK (SuRF-UK)

slide-18
SLIDE 18
  • Local stakeholder engagement events
  • n 8 Feb. & 24 Mar. 2017 & with Gov.

Agencies on 25 Jan. and 4 Apr. 2017;

  • Stakeholder questionnaire survey;
  • Local industrial/regulatory knowledge.
  • Scoring criteria for economic,

environmental and social factors on an equal basis;

  • Site-specific decision matrix of viable

remediation options;

  • Identified priorities for the selection

criteria and decision making.

Framing the remediation options appraisal

slide-19
SLIDE 19

Other er issues es r raised ed

  • Very strong feeling that lessons should be learnt to prevent recurrence;
  • The critical sensitivity of River Faughan to short term impacts is

recognised;

  • The desire for a beneficial end use, with a particular focus on ecology

was expressed;

  • There are still uncertainties regarding control of future end uses;
  • Strong sense that those responsible for the waste deposition shouldn’t

benefit from remedial works.

slide-20
SLIDE 20

10% 10% 50% 20% 10%

Environmental Factors

Air Soil and Ground Conditions Groundwater and Surface Water Ecology Natural Resources and waste

35% 15% 10% 5% 35%

Economic Factors

Direct Economic Costs & Benefits Indirect economic costs and benefits Employment & Employment Capital Induced Economic Costs & Benefits Project Lifespan & Flexibility

40% 25% 25% 10%

Social Factors

Human Health & Safety Ethics & equality Neighborhood & Locality Communities & Community Involvement

Sustainability Criteria

slide-21
SLIDE 21

Stage 1: Shortlisting of Options

Options Screening Assessment: Identified range of potentially applicable remediation techniques; Direct treatment of wastes (3) Containment options (5) Leachate management options (8) Pathway barriers (4) Source treatment options (13) Options considered for each waste zone and for the whole site assessed on the basis of; Applicability; Permissibility ; Sustainability ; Time; Cost was not included as a decision factor at the shortlisting stage; Options that scored zero in any shortlisting not taken forward

Small Business Research Initiative (SBRI) – funded Phase 1 of 5 potential emerging remediation technologies (October 2016 to March 2017)

slide-22
SLIDE 22

Stage 2: Detailed Assessment of Options

By waste source zone & for the whole site; Weighted scoring system based on stakeholder consultation; Decision by multi-criteria analysis; Budget cost estimates for each shortlisted option considered; Provides for sensitivity analysis and uncertainty.

slide-23
SLIDE 23

 Integration of options to manage All risks across the site;  Integrated approach needed to take account of DAERA, DfI and NI Water’s interests;  Contingency for failure of certain elements or impact due to climatic variability;  Management of system capacity and maintenance;  Addressing specific waste / site issues

Integrated Remediation

slide-24
SLIDE 24

Remediation Options Appraisal

  • Identify feasible
  • ptions
  • Detailed evaluation of
  • ptions
  • Develop & agree the

Remediation Strategy

Final Costed Remediation Strategy subject to:

  • review & update of options via a new

ICT contract;

  • integration with NI Water’s

contingency plans & the A6 scheme (Drumahoe to Stradreagh);

  • approval of the business case.
  • Strategy to provide combination of

the highest performing options to manage risks and support site vision

Remediation Strategy – Next Steps

slide-25
SLIDE 25

Mobuoy Masterplan & Vision Why a focus on Vision and Future Uses?

2017- A positive and lasting site legacy – benefit the whole community Create &

  • pen up an

asset on the edge of the City Creation & development

  • f multi-

functional Green & Blue Infrastructure Add value to existing environmental designations Partnership - statutory, voluntary, community & interest based stakeholders Collaborative & co-design approach to a Vision & Development Plan Complement the Strategic Growth Plan ++

slide-26
SLIDE 26

NIEA Business Plan DCSDC Inclusive Strategic Growth Plan 2017- 2032 DCSDC Local Development Plan DCSDC Green Infrastructure Plan

Strategic Drivers

Draft Programme for Government 2016-21 Circular Economy/ Zero Waste Strategy DCSDC

slide-27
SLIDE 27
slide-28
SLIDE 28

Site Potential

Contribute to the outcomes of DAERA’s Vision & Council’s plans incl. GIP A flagship multifunctional green and blue space Create a beacon of innovative environmental management practices Co-design partnership between statutory, voluntary, community and interest based stakeholders Partner with other “Landfill to Park” projects on a world wide basis Contribute to EU Circular Economy targets & waste management targets Complement the creation of jobs in the Green Economy & Cleantech sector Build on DCSDC’s experience in the restoration of former landfill sites

slide-29
SLIDE 29

Potential Multiple Functions of site post remediation

  • Green and Blue corridors, walks & recreation spaces
  • Active lifestyles – Health and well being; family focus

Recreation

  • A learning hub – Environmental management practices
  • Research & education - innovative remediation techniques
  • Awareness of waste as a resource - Behaviour changes

Education

  • For wildlife – an eco wetland; Natural capital
  • Improved biodiversity; STEAM agenda

Improved Habitat

  • Co-designed with community and interest based groups
  • Local and regional asset; Citizen engagement opportunities

Cohesion

  • Complement employment & research in Cleantech Sector

& green economy

  • Partner with other worldwide “Landfill to Park” projects

Economic

  • Use of bicycles and walking; Park & Ride facility (A6)
  • Better air quality; reduced CO2 emissions
  • Climate change focus

Modal Shift

slide-30
SLIDE 30

Vision Building

Multifunctional Asset – Multiple

  • utcomes

Interactive Faughan Eco-Wetlands Education Park - Biodiversity STEAM Education Centre – Outdoor classrooms - Prevention & Behavioural Change Learning Hub on renewables & Centre

  • f Excellence on Waste Remediation

techniques Epicentre for Research & exploration of new technologies Model for Placing Value on Natural Capital

slide-31
SLIDE 31
slide-32
SLIDE 32

Stakeholder Engagement Stage 1: Secure Council endorsement for a partnership based approach moving forward Stage 2: Co-designed Vision Building and Master Plan for potential site uses

slide-33
SLIDE 33

Surface Activities & Management – Other stakeholders & Council Remediation Proposal- DAERA

Delivery

Underlying sub surface of site - DAERA

slide-34
SLIDE 34

Project Timeline

slide-35
SLIDE 35

Council Mobuoy Working Group- Summary of Queries

  • 1. Provide an explanation of what happened & the extent of investigation; knowledge of

extent and type of waste present; 

  • 2. Provide an update on the proposed Public Inquiry into all illegal waste in N. Ireland;

what was done?

  • 3. How to ensure Polluter Pays Principle is adopted:

  • 4. What are the plans to deal with waste. What decisions have been taken with

respect to remediation of the site? Has a preferred option been agreed?  5 Will drinking water be safe? Can this be guaranteed without removing the waste? 

  • 6. Cost estimates appear to be wide ranging; can the Department confirm the

estimated costs to remediate the site? 7.What would happen if the waste started to leach? 

  • 8. What are repercussions for the proposed A6 (Drumahoe to Stradreagh)?

  • 9. There are reports the water treatment plant has been moved up above Mobuoy?

slide-36
SLIDE 36

Next Steps

Ongoing environmental monitoring; Develop Site Vision with community / stakeholder engagement; Appoint an ICT to develop remediation options & plans; Secure planning permission and further update business case; and Implement Remediation Strategy.

slide-37
SLIDE 37

Summary of Outcomes

Council to endorse engagement with DAERA/ NIEA to work in Partnership to co-design future development plans

slide-38
SLIDE 38

Faughan Wetlands Park?