Commercialisation of CCS “What needs to happen?”
- Dr. L. A. Hackett CEng, FIChemE
London December 5th 2016
6-Dec-16 Commercialisation of CCS – what needs to happen? 1
Commercialisation of CCS What needs to happen? Dr. L. A. Hackett - - PowerPoint PPT Presentation
Commercialisation of CCS What needs to happen? Dr. L. A. Hackett CEng, FIChemE London December 5 th 2016 6-Dec-16 Commercialisation of CCS what needs to happen? 1 Background Global efforts to develop CCS have so far proved largely
6-Dec-16 Commercialisation of CCS – what needs to happen? 1
6-Dec-16 Commercialisation of CCS – what needs to happen? 2
6-Dec-16 Commercialisation of CCS – what needs to happen? 3
6-Dec-16 Commercialisation of CCS – what needs to happen? 4
1 Cost Reduction Task Force 2 2012 prices Scottish power EA1
6-Dec-16 Commercialisation of CCS – what needs to happen? 5
Commercial Banks ECAs, Multilaterals, Other debt providers Insurers [TBC] Fuel Supplier [TBC] Drax Drax O&M Supplier [TBC] GE Services GE Drax Linde Engineering (ASU) Power Offtaker [TBC]
GB Wholesale Power Market
NGET (as TSO)
EUA Offtaker [TBC] EU Emissions Trading System
Project Management Services [TBC] Early & Enabling Works Contractor(s) [TBC] Sub-contractors [TBC]
GB 400 kV Transmission System
Sub-contractors, insurers
National Grid Carbon Limited
Miners, coal markets, logistics suppliers [TBC] BOC Sub-contractors, technology licensors, insurers etc [TBC] Sub-contractors, insurers etc [TBC]
Third Party Debt
Supply-Side Services Supply-Side Works Project Management Services Pre-NTP Works Emissions Trading Services Power Offtake Services
Project insurance programme Security Trust and Inter-creditor Deed Common Terms and Facilities Agreements Comprehensive security package Coal Supply Agreement Site Services Agreement
(incl. Inter-Connection O&M)
Option Agreement
(OPP Site Lease, Laydown Lease, Easements)
Pig-Trap Sub-Lease O&M Agreement ASP O&M Sub-Contract OPP Major Maintenance Agreement (including ASP major maintenance) OPP EPC Agreement Inter-Connections EPC Agreement Early Works Agreement, Enabling Works Agreement Project Management Services Agreement EU Emissions Allowance Agreement Grid Connection Agreement, TNUoS Agreement Power Purchase Agreement Project Contract, Direct Agreements
with Key Sub-Contractors
Contract for Differences NER300
BOC GE Other(s) [TBC]
Equity
Equity Commitment PCGs
Re- insurers Insurance DECC SoS Principal Consents
(Oxy Power Plant)
Re-insurance
Construction Project Management Contractor - [TBC]
Project Management Contractor Agreement
National Grid Carbon Limited Carbon Sentinel Limited
Sub-contractors, insurers etc. [TBC] The Crown Estate
CO2 Offtake Services CO2 Storage
Transportation & Storage Services Agreement Transportation & Storage System EPCs Agreements Storage Services Agreement DCO
Capture Power Limited
Developer
Including a Storage Operating Agreement Principal Consents (Transportation & Storage
System)
DECC SoS
Development Consent Order Agreement for Lease, Lease (Offshore) Storage Licence Storage Permit
Sub-contractors, insurers etc. [TBC]
DECC/E C
Shareholders’ Agreement, Shareholder Loans, Secondment Agreements and other Equity Arrangements
DECC
Authority Funding
LCCC
6-Dec-16 Commercialisation of CCS – what needs to happen? 7
Financial Incentives & Electricity Market Reform Raising Finance Clustering Part Chain Capture Part Chain Storage EOR (Enhanced
Oil Recovery)
Industrial CCS BECCS (Bio- energy with CCS) CCU (Carbon Capture & Utilisation)
6-Dec-16 Commercialisation of CCS – what needs to happen? 8
New CCS Commercial Models
Anchor project & infrastructure Risk Intra-chain project on project risk T&S Capacity availability and market risk Long-term storage risk
6-Dec-16 Commercialisation of CCS – what needs to happen? 9
i. Cross chain default (project on project risk) ii. Post decommissioning CO2 storage risk iii. Sub-surface CO2 storage performance risk iv. Decommissioning cost sufficiency and financial securities relating to CO2 storage permits v. Insurance market limitations for CO2 transport and storage operations
6-Dec-16 Commercialisation of CCS – what needs to happen? 10
and CO2 T&S providers
chain model
additions to the network
CO2 Source G&C/EII Operators: Users T&S Infrastructure: Service providers CO2 Transport Factory Boundary CO2 Storage
All providing project on project risk protection for the G&C/EII operator e.g. through:
Humberside)
6-Dec-16 Commercialisation of CCS – what needs to happen? 11
developers take their FID.
development
6-Dec-16 Commercialisation of CCS – what needs to happen? 12
realisation
proven unpersuasive
installing CCS and producing clean power
6-Dec-16 Commercialisation of CCS – what needs to happen? 13
willing to take, e.g. project development, storage
finance
institutional investors and/or debt capital markets further reducing costs of capital.
6-Dec-16 Commercialisation of CCS – what needs to happen? 14
6-Dec-16 Commercialisation of CCS – what needs to happen? 15
6-Dec-16 Commercialisation of CCS – what needs to happen? 16
6-Dec-16 Commercialisation of CCS – what needs to happen? 17