1
MMR IAC Hearing
Submission on behalf of
- f RMIT University
MMR IAC Hearing Submission on behalf of of RMIT University 12 th - - PowerPoint PPT Presentation
MMR IAC Hearing Submission on behalf of of RMIT University 12 th September 2016 Tim Marks 1 Airborne Construction Noise Mitigation thresholds should be established particularly for daytime when teaching occurs Guideline noise levels only
1
2
3
Step 1: Construct guide walls around full perimeter of the excavation Step 2: Excavate panel (day 1) Step 2.1: Final grab pass (day 2) Step 3: Insert rebar (day 2) Step 4: Concrete (day 2)
4
5
D-walling proposed for CBD North shafts Panel sizes 2.4m wide, 30-35m deep Each shaft perimeter 200m (75m x 25m)~90 panels 2 days per panel, total 180 work days 36 weeks with one Bauer MC-64, 18 weeks with two D walling rigs plus two cranes Crossrail 12-14 hrs per day through London Clay Possibly up to 16hrs per day (0700-2300hrs) through Melbourne Formation Exposure duration –normal working hours 0700- 1800hrs 11hrs/day!
6
Human Comfort – eVDV not appropriate use RMS velocity! (NV 9) No valid basis or precedence for eVDV, very difficult to estimate or predict. Unlike VDV, velocity enables real time validation. TN 032 explains velocity criteria preferred, but stated no applicable standard but ISO 10137 can apply.
7
8
9
10
11
12
13
Delta 1=10dB Delta 2 = 39dB 1 2
14
FST Cost $A2,500 track/m LVT Cost $A800 track/m
15
16
17
18
19