MMR IAC Hearing Submission on behalf of of RMIT University 12 th - - PowerPoint PPT Presentation

mmr iac hearing
SMART_READER_LITE
LIVE PREVIEW

MMR IAC Hearing Submission on behalf of of RMIT University 12 th - - PowerPoint PPT Presentation

MMR IAC Hearing Submission on behalf of of RMIT University 12 th September 2016 Tim Marks 1 Airborne Construction Noise Mitigation thresholds should be established particularly for daytime when teaching occurs Guideline noise levels only


slide-1
SLIDE 1

1

MMR IAC Hearing

Submission on behalf of

  • f RMIT University

12th September 2016 Tim Marks

slide-2
SLIDE 2

Airborne Construction Noise

Mitigation thresholds should be established particularly for daytime when teaching occurs Guideline noise levels only considers residential scenarios not educational ones CBD North Scenario B, initial shaft construction, is external to Acoustic Shed (p185,187) See Fig A24 Piling or D-walling? EES not clear which process Piling Lw 111dB - too low (s/b 116dB) D-wall machine Lw 91 dB too low (s/b 105dB) Rock-breakers Lw 114dB too low (s/b 118dB)

2

slide-3
SLIDE 3

Construction Noise Targets

EPA 1254 only considers residential receivers; and not appropriate for RMIT and projects of this duration, scale or intensity. Preference for NSW ICNG or TfNSW Guideline - proven, comprehensive, robust and effective! Propose typical UK, NSW, USA daytime thresholds for teaching of 35-45dB LAeq indoors Example: teaching thresholds are 45dB (NSW )

  • r 35dB (UK BB93)

Need to ensure the assessment and mitigation process should be trusted by the community and stakeholders

3

slide-4
SLIDE 4

Step 1: Construct guide walls around full perimeter of the excavation Step 2: Excavate panel (day 1) Step 2.1: Final grab pass (day 2) Step 3: Insert rebar (day 2) Step 4: Concrete (day 2)

4

slide-5
SLIDE 5

5

slide-6
SLIDE 6

Shaft Construction Noise

D-walling proposed for CBD North shafts Panel sizes 2.4m wide, 30-35m deep Each shaft perimeter 200m (75m x 25m)~90 panels 2 days per panel, total 180 work days 36 weeks with one Bauer MC-64, 18 weeks with two D walling rigs plus two cranes Crossrail 12-14 hrs per day through London Clay Possibly up to 16hrs per day (0700-2300hrs) through Melbourne Formation Exposure duration –normal working hours 0700- 1800hrs 11hrs/day!

6

slide-7
SLIDE 7

Construction vibration

Human Comfort – eVDV not appropriate use RMS velocity! (NV 9) No valid basis or precedence for eVDV, very difficult to estimate or predict. Unlike VDV, velocity enables real time validation. TN 032 explains velocity criteria preferred, but stated no applicable standard but ISO 10137 can apply.

7

slide-8
SLIDE 8

Vibration predictions (p43)

20 t rock breaker 4.7mm/s Excavator with ripper 1.3mm/s Bored piling 1-3mm/s Sensitive equipment, VC-B (less sensitive, higher vibration), or VC-D(more sensitive, lower vibration) (Table 3-9) Bldg 14, L2 (Radiation Store, Micro CT scanners), L5 (Confocal microscope, VC- B), and L7 Electron Microscopes (0.1 nano-m) do not comply (Table 11-11)

8

slide-9
SLIDE 9

Ground propagation (p42)

9

slide-10
SLIDE 10

Bored piling (auger) AAS 2011

10

slide-11
SLIDE 11

Buffer distances

11

slide-12
SLIDE 12

Operational Vibration

FTA method commonly used Not used correctly in EES, 3 options: Screening, general and detailed methods a combination (p55) is not appropriate FTA General calculation shows ASHRAE Curve VC-B will be exceeded Detailed studies required Significant long term risks to RMIT

12

slide-13
SLIDE 13

Claimed track bed isolation (p57,58)

13

Delta 1=10dB Delta 2 = 39dB 1 2

slide-14
SLIDE 14

Floating track slab

14

FST Cost $A2,500 track/m LVT Cost $A800 track/m

slide-15
SLIDE 15

Ground propagation (p58)

15

slide-16
SLIDE 16

Detailed analysis: what Fig 4-7 should show (p56)

16

slide-17
SLIDE 17

Operational vibration analysis

Vibration mitigation controls are not “standard”, “high” and “very high” Three choices: low medium, high:

  • LVT (low vibration track) 4-8 dB
  • IST (isolated slab track) 6-12 dB (∆=2-4dB)
  • FST (floating slab track) 15-18 dB (∆=10-11dB)

EES Analysis not transparent or convincing with high risks! Force density and transfer mobility measurements required (Fig 4-3)

17

slide-18
SLIDE 18

EPR’S

As noted, unanimity between all experts in Conclave on most EPR’s Particular concern over NV1 (EPA 1254 should be replaced by ICNG), as no daytime controls Definition of “Unavoidable” works is a smoking gun, undefined and subject to abuse NV 5 to be revised to include teaching and research spaces NVB in its current form is incomplete (CNVMP) Concern over Construction Vibration metrics (NV9) Serious Concerns over achieving Operational Vibration (NV10) thresholds Propagation measurements essential (new

18

slide-19
SLIDE 19

Commercial, Medical and Educational Impact Mitigation

Mitigation for daytime not required, yet noise at façade >80-90dB (Fig A.24) Building / facade insulation should be required for RMIT when internal thresholds likely to be exceeded. Compares poorly to NSW, UK(Crossrail) and USA (Boston) (35dB - 45dB) Impact and impairment on learning development (Ref AAAC Guidelines, esp for ESL or Overseas students)

19