Mid Argyll Community Liaison Group Inveraray Crossaig Project - - PowerPoint PPT Presentation

mid argyll community liaison group
SMART_READER_LITE
LIVE PREVIEW

Mid Argyll Community Liaison Group Inveraray Crossaig Project - - PowerPoint PPT Presentation

Mid Argyll Community Liaison Group Inveraray Crossaig Project Inaugural Meeting 23 rd June 2020 Welcome and Introductions SSEN Transmission Keith Inglis (Project Director) Ian Clark (Lead Project Manager) Local Community Councils


slide-1
SLIDE 1

Inveraray – Crossaig Project Inaugural Meeting 23rd June 2020

Mid Argyll Community Liaison Group

slide-2
SLIDE 2

Welcome and Introductions

2

SSEN Transmission ‐ Keith Inglis (Project Director) ‐ Ian Clark (Lead Project Manager) ‐ David Fraser (Project Manager) ‐ Kelly Scott (Community Liaison Manager) Local Ward Councillors ‐ Cllr Dougie Philand ‐ Cllr Sandy Taylor Local Community Councils ‐ Linda Divers (Inveraray CC) ‐ Fred Bruce (West Loch Fyne CC) ‐ Lynda Syed (Furnace CC) ‐ Andy Buntin (Lochgilphead CC) ‐ Ken McVicar (Ardrishaig CC) ‐ Jim Malcolm (Dunadd CC) Residents Associations ‐ Julie Young (Brenchollie RA) Balfour Beatty ‐ John Rennie (Project Director)

slide-3
SLIDE 3

Agenda

1.Purpose of the CLG 2.Overview of project and current status 3.Temporary accommodation for workers 4.COVID 19 Update 5.Questions

  • 6. Future meetings:

‐ Elect chairman ‐ Formalise ongoing agenda ‐ Date of next meeting

slide-4
SLIDE 4

Purpose of the CLG

  • Help to effectively identify and address any continued

concerns with appropriate actions

  • Establish a platform for meaningful engagement between

SSEN Transmission and nominated members of the local community where updates can be provided, concerns raised, questions answered, and input provided

  • Keep the community well informed of the project

progression and encourage meaningful engagement

slide-5
SLIDE 5

Why are SSEN working in the area?

5

The main elements of the project are as follows:

  • Construction of a new 80km 275kV overhead line, initially operating at 132kV between Inveraray and Crossaig
  • Extend the existing connection from Port Ann to the new overhead line
  • Decommissioning and removal of the existing 132kV transmission line between Inveraray and Crossaig

Construction of the project will take place in 2 phases:

  • Phase 1 – Inveraray – Port Ann – 2019 – 2021
  • Phase 2 – Port Ann – Crossaig – 2021 – 2024

The aim of the Inveraray – Crossaig project is to reinforce the existing transmission network in Argyll and Kintyre by replacing the overhead electricity transmission power line that runs between Inveraray and Crossaig. This line was installed in the 1950s and is reaching the end of its operational life. This asset is defined by Government as critical national infrastructure, with its replacement deemed essential in line with the latest Government coronavirus guidance. It is therefore essential that the timely replacement of this ageing asset continues in order to maintain security of supply for Argyll and Kintyre communities.

slide-6
SLIDE 6

Full Inveraray – Crossaig Overhead Line Route

6

slide-7
SLIDE 7

Phase 1 ‐ Overhead line route

7

Existing line New line

slide-8
SLIDE 8

Key Programme Milestones and Development – Phase 1

8

Project construction commenced – October 2019 Construction paused ‐ March 2019 Foundations – over one third complete Tower assembly – underway near Inveraray and Garvachy Forestry works substantially complete Phased return to work – From Mid April 2020

slide-9
SLIDE 9

Upcoming Key Milestones – Phase 1

9

Foundations and tower assembly will be substantially completed this year Wiring of new towers end of summer through to spring/summer 2021

Forestry works substantially c

New overhead line energised in 2021

Forestry works substantially c

Dismantling and decommissioning Autumn/Winter 2021/22 Access track completion ‐ Late Summer 2020

slide-10
SLIDE 10

Access Installation

10

slide-11
SLIDE 11

Access Installation

11

slide-12
SLIDE 12

Foundation Installation

12

slide-13
SLIDE 13

Foundation Installation

13

slide-14
SLIDE 14

Tower Assembly & Erection

14

slide-15
SLIDE 15

Future Activity

15

slide-16
SLIDE 16

Piloting

16

slide-17
SLIDE 17

Wiring

17

slide-18
SLIDE 18

Wiring

18

slide-19
SLIDE 19

Workforce accommodation

19

  • Enquiries commenced at start of 2020 to source potential locations for

temporary worker communication as mitigation for expected tourist peak in Summer

  • Planning applications were lodged relating to potential temporary

accommodation sites

  • SSEN acknowledge missed opportunity to adequately liaise in advance
  • f these planning submissions which coincided with ongoing pandemic
  • Key lesson learned for project teams
  • Project is currently reviewing alternative locations for these sites and

we are committed to keeping the community updated as this progresses

slide-20
SLIDE 20

COVID 19

What steps have been taken to reduce public interface?

20

  • Work paused March to mid April 2020 to review Government guidance, update

work methods and procedures

  • Workforce fully briefed on these new methods and procedures
  • Alternative arrangements made for fuelling project vehicles
  • Site catering including temporary provision of meals
  • On site laundry facility
  • Increased number of temporary accommodation pods to house workers
  • Appropriate face coverings provided to workers for use in the local community
  • Operatives sharing accommodation classed as ‘Family Units’ identified on site

with same coloured hard hat covering

  • Perspex screens in vans
  • Additional site vehicles

Opportunity for discussion relating to COVID 19

slide-21
SLIDE 21

General discussion /Questions?

slide-22
SLIDE 22

Future Meetings:

22

  • Chairman
  • Future agenda items
  • Date of next meeting