metro nashville
play

Metro Nashville DISTRICT ENERGY SYSTEM Advisory Board Quarterly - PowerPoint PPT Presentation

Metro Nashville DISTRICT ENERGY SYSTEM Advisory Board Quarterly Meeting First Quarter FY09 Presented to District Energy Advisory Board November 20, 2008 Metro Nashville DISTRICT ENERGY SYSTEM Agenda 1. Call to Order 2. Election of


  1. Metro Nashville DISTRICT ENERGY SYSTEM Advisory Board Quarterly Meeting First Quarter FY09 Presented to District Energy Advisory Board November 20, 2008

  2. Metro Nashville DISTRICT ENERGY SYSTEM Agenda 1. Call to Order 2. Election of Chair & Vice Chair 3. Review & Approval of Previous Meeting Minutes 4. Summary of Performance 5. Natural Gas Purchasing Up-Date 6. Financial Reports – 1 st Qtr FY09 7. Capital Projects Review 8. DES Capacity – New Convention Center 9. Other Board Member Items 10. Adjourn 2

  3. Metro Nashville DISTRICT ENERGY SYSTEM 1. Call to Order 2. Election of Chair & Vice Chair 3. Review and Approval of Previous Meeting Minutes 3

  4. Metro Nashville DISTRICT ENERGY SYSTEM 4. Summary of Performance Contractor (CNDE) is in compliance with their contractual obligations for FY09. Excellent Performance – No Improvement Necessary Satisfactory Performance – Some Improvement Could Be Made Poor Performance – Much Improvement Necessary 4

  5. Metro Nashville DISTRICT ENERGY SYSTEM Summary Table 4: Customer Cost Comparison for the Previous 12 Months Steam Chilled Water ($ millions) ($ millions) 10/06 – 10/07-9/ % Diff. 10/06-9/ 10/07-9/ % Diff. 9/07 08 07 08 Private $2.587 $2.350 -9.2% $3.877 $3.883 <0.2% State $3.150 $2.898 -8.0% $3.144 $3.224 2.5% Metro $3.330 $3.162 -5.0% $4.531 $4.591 1.3% New Customers $1.558 $1.503 -3.5% $3.068 $3.120 1.7% Aggregate $9.067 $8.410 -7.2% $11.552 $11.698 1.3% 5 Includes MFA allocated to Metro Buildings (post-True-up)

  6. Metro Nashville DISTRICT ENERGY SYSTEM FY08 Operations: Steam 70,000,000 1,000 900 60,000,000 800 50,000,000 700 Pounds of Steam 600 40,000,000 HDD 500 30,000,000 400 300 20,000,000 200 10,000,000 100 0 0 December October November April January February March May June July September August 6 Sales Sendout HDD Losses

  7. Metro Nashville DISTRICT ENERGY SYSTEM FY08 Operations: Chilled Water 9,000,000 500 450 8,000,000 400 7,000,000 350 6,000,000 300 Tonhrs 5,000,000 CDD 250 4,000,000 200 3,000,000 150 2,000,000 100 1,000,000 50 0 0 November December April October July September January February March May June August Sales Sendout CDD Losses 7

  8. Metro Nashville DISTRICT ENERGY SYSTEM Performance Measurement FY08: Steam Electric Conversion 7.00 6.00 5.00 Ratio (kWhr/Mlb) 4.00 3.00 2.00 1.00 - r r l r y r y y h y e e e e i t e r c r a n l s b r b b p u b a a u r M u m o m u a A J m u g J t r M e n u c e b e v c a A O t e e J p o F D e N S GMQ Elec to Steam FY08-FY09 Actual Elec to Steam FY08-FY09 8

  9. Metro Nashville DISTRICT ENERGY SYSTEM Performance Measurement FY08: Steam Plant Efficiency 2 1.8 Ratio (Dktherm/Mlb) 1.6 1.4 1.2 1 0.8 0.6 0.4 0.2 0 December April October November January February March May June July September August GMQ Fuel to Steam FY08-FY09 Actual Fuel to Steam FY08-FY09 9

  10. Metro Nashville DISTRICT ENERGY SYSTEM Performance Measurement FY08: Steam Water Conversion 4,000,000 3,500,000 3,000,000 Gallons of Water 2,500,000 2,000,000 1,500,000 1,000,000 500,000 - November December April October February June July September January March May August 10 GMQ Water to Steam FY08-FY09 Actual Water to Steam FY08-FY09

  11. Metro Nashville DISTRICT ENERGY SYSTEM Performance Measurement FY08: Chilled Water Electric Conversion 1.20 1.00 Ratio (kWhr/tonhr) 0.80 0.60 0.40 0.20 0.00 December April October November January February March May June July September August GMQ Elec to CHW FY08-FY09 Actual Elec to CHW FY08-FY09 11

  12. Metro Nashville DISTRICT ENERGY SYSTEM Performance Measurement FY08: Chilled Water Water Conversion 6 5 Ratio (gal/tonhr) 4 3 2 1 0 December April October November July September January February March May June August 12 GMQ Water to CHW FY08-FY09 Actual Water to CHW FY08-FY09

  13. Metro Nashville DISTRICT ENERGY SYSTEM Water Treatment • Steam/Condensate – Corrosion – Iron – Hardness – Chlorine/Sulfite • Condensing Water – Conductivity – Biologicals • Chilled Water – Hardness – Corrosion 13 – Biologicals

  14. Metro Nashville DISTRICT ENERGY SYSTEM EGF Walkthrough Quarterly Inspection Process • Equipment Maintenance • Operations • Electrical • Housekeeping • Building Structure • Building Exterior and Grounds 14

  15. Metro Nashville DISTRICT ENERGY SYSTEM EDS Walkthrough Quarterly Inspection Process • Manhole/Tunnel Housekeeping • Maintenance Items – Insulation Repair/Replacement – Water Infiltration – Corrosion of Structural Metal Components • Safety Items 15

  16. Metro Nashville DISTRICT ENERGY SYSTEM 5. Natural Gas Purchasing Update Natural Gas Purchasing Review Table 5: FY08 Gas Spending & Budget Comparison Actual Gas Costs for FY08 Projected Gas Costs for FY09 16

  17. Metro Nashville DISTRICT ENERGY SYSTEM Table 5: FY09 Gas Spending & Budget Comparison Actual FY09 Budget FY09 To date (Sept 30) Steam Sendout (Mlbs) 43,003 44,217 Fuel Use (Dth) 60,587 64,159 Plant Eff (Dth/Mlb) 1.408 1.451 Total Gas Cost $765,491 $771,833 Unit Cost of Fuel ($/Dth) $12.635 $12.030 17

  18. Metro Nashville DISTRICT ENERGY SYSTEM Projected Gas Cost Comparison for FY09 $14.00 $12.00 $10.00 $ per dekaTherm $8.00 $6.00 $4.00 $2.00 $0.00 November December April July September October January February March May June August FY08 Actual Unit Cost FY09 Budgeted Unit Cost FY09 Projected Unit Cost FY08 Market Price 18

  19. Metro Nashville DISTRICT ENERGY SYSTEM 6. Financial Reports: 1 st Qtr FY09 Item FY09 1st Qtr FY09 Percent of Percent of Budget Expenses FY09 Budget FY08 Actual for 1st Qtr FOC: Basic $ 3,852,170 $ 963,042.51 25.00% 103.00% FOC: 9th Chiller $ 36,100 $ 9,023.76 25.00% 103.00% FOC: Change Order 6A $ 71,260 $ 17,815.74 25.00% 103.00% FOC: Change Order 6B $ 62,390 $ 15,597.00 25.00% 103.00% Chemicals $ 156,510 $ 43,118.73 27.55% 92.99% Engineering $ 40,000 $ 5,678.87 14.20% n.a. Insurance $ 42,440 $ 29,721.89 70.03% 99.57% Marketing: CEPS Sales Activity $ 27,000 $ 2,005.57 7.43% n.a. Metro Marketing $ 52,890 $ - 0.00% n.a. Incentive Payments $ 30,150 $ 3,704.40 12.29% 51.03% Project Administration $ 22,090 $ - 0.00% n.a. Metro Incremental Cost $ 585,420 $ 94,099.04 16.07% 68.76% FEA: Steam $ - $ 34,016.86 n.a. 147.59% FEA: Chilled Water $ - $ 112,987.27 n.a. 97.74% ARFA $ - $ 13,986.69 n.a. 103.00% Metro Credit $ - $ (149,216.72) n.a. 85.31% Water/Sewer $ 681,600 $ 137,753.13 20.21% 82.74% Natural Gas/Propane $ 6,570,400 $ 765,490.08 11.65% 125.10% Electricity $ 4,437,300 $ 1,400,759.74 31.57% 106.07% EDS Repair & Improvement $ 171,430 $ 3,757.05 2.19% 12.28% $ - 0.00% n.a. EDS Surcharge $ 68,460 Sub-total Operations $ 16,907,610 $ 3,503,342 20.72% 106.05% 2002 Bonds $ 4,361,770 $ 1,090,373.43 25.00% 99.94% 2005 Bonds $ 631,590 $ 172,074.13 27.24% n.a. FY07 Projects $ 227,800 $ - 0.00% 0.00% $ - 0.00% n.a. FY08 Projects $ 220,500 Debt Service Interest Revenue $ (72,300) $ (46,161.38) 63.85% n.a. Oper. Reserve Funding Deposit $ 97,400 $ 24,435.00 25.09% 51.18% Sub-total Debt Service $ 5,466,760 $ 1,240,721 22.70% 103.76% $ 22,374,370 $ 4,744,063 21.20% 105.44% Total Expenses Customer Revenues $ 19,768,660 $ 4,498,667 22.76% 103.39% 19 Total Metro Funding Amount $ 2,605,710 $ 245,396 9.42% 75.97%

  20. Metro Nashville DISTRICT ENERGY SYSTEM 7. Capital Projects Review Financial Summary Table 7: Capital Projects Summary Active Project Status 20

  21. Metro Nashville DISTRICT ENERGY SYSTEM Table 7: Capital Project Summary (09/30/08) Spent to End of FY09 Balance to Date FY08 (09/30/08) Spending 2002A Bond $3,680,667 $0 $47,292 R&I Projects $626,555 $1,878 $415,280 2005B Bond $7,655,347 $8,633 $522,521 2007 Bond $2,620,771 $0 $237,729 2008 Bond $87,758 $29,075 $2,631,667 Total $14,671,098 $39,586 $3,854,489 21

  22. Metro Nashville DISTRICT ENERGY SYSTEM Active Project Status • DES 036: 4 th Ave Tunnel Fan (R&I) - in construction • DES 041/054: Symphony CND – in construction • DES 042: 401 Union St. CND Replacement – in closeout • DES 045: MH 6 to MH 23 CND Replacement – in close-out • DES 046: Ryman CND – in design • DES 047: State Tunnel CND Replacement – closed • DES 049: Temp. Boiler Conn. @ MH 15 – closed • DES 050: MH Insulation – in construction/ongoing • DES 052: Wildhorse CND Tempering – in close-out 22

  23. Metro Nashville DISTRICT ENERGY SYSTEM Return on Investment • Capital Project ROI – Boiler O 2 Trim – Power Factor Correction Capacitor – Condensate Return – New Customers • Funding 23

  24. Metro Nashville DISTRICT ENERGY SYSTEM 8. DES Capacity – New Convention Center • TEG Hydraulic Analysis for EDS Chilled Water • Expansion with New Convention Center – Peak Demands Decreasing Each Year: 2006, 2007, 2008 – 11,500 gpm Additional Export Possible – Potential Servable Load at NCC Location ~7,200 tons – 7,200 tons Consumes Remaining EGF Capacity • Potential Additional Customers at Other Locations 24

  25. Metro Nashville DISTRICT ENERGY SYSTEM 9. Other Board Member Items 10. Adjourn 25

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend