MERALCO Standards: Electrical Design Engr. Eduard Mercado - - PowerPoint PPT Presentation

meralco standards
SMART_READER_LITE
LIVE PREVIEW

MERALCO Standards: Electrical Design Engr. Eduard Mercado - - PowerPoint PPT Presentation

MERALCO Standards: Electrical Design Engr. Eduard Mercado Electrical Design Team Electrical Design Standards SERVICE VOLTAGES SECONDARY METERED - 240 V, 400 V, 460 V PRIMARY METERING -34.5 kV, 13.8 kV (portions of Cavite &


slide-1
SLIDE 1
  • Engr. Eduard Mercado

Electrical Design Team

MERALCO Standards:

Electrical Design

slide-2
SLIDE 2

Electrical Design Standards

slide-3
SLIDE 3

SERVICE VOLTAGES

  • SECONDARY METERED - 240 V, 400 V, 460 V
  • PRIMARY METERING -34.5 kV, 13.8 kV (portions
  • f Cavite & Bulacan), 115 kV (Subtransmission)

FACILITIES

  • 1. OVERHEAD
  • POLE MOUNTED TRANSFORMERS
  • PADMOUNT TRANSFORMERS
  • VAULT TYPE DT
  • 2. UNDERGROUND
  • PADMOUNT TRANSFORMERS
  • VAULT TYPE DT
slide-4
SLIDE 4

SURGE ARRESTER FUSE CUTOUT OR POWER FUSE ELBOW ARRESTER PADMOUNTED TRANSFORMER CT METER TO CUSTOMER’S MAIN SECONDARY CIRCUIT BREAKER CABLE TERMINATION UNDERGROUND PRIMARY CABLES INCOMING OVERHEAD LINE TERMINAL POLE

EPMC

Single Line Diagram

OVERHEAD LINE FEEDING A TRANSFORMER VAULT

TRANSFORMER VAULT TO BE CONSTRUCTED BY THE APPLICANT/CUSTOMER BASED ON MERALCO STANDARD ALL CIVIL WORKS, i.e., CONCRETE-ENCASED PVC DUCTS & FITTINGS, TO BE PROVIDED AND INSTALLED BY THE APPLICANT/CUSTOMER SECONDARY CABLES

slide-5
SLIDE 5

Single Line Diagram

ELBOW ARRESTER PADMOUNTED TRANSFORMER CT METER UNDERGROUND PRIMARY CABLES UNDERGROUND FEEDER PADMOUNTED SWITCHGEAR

EPMC

UNDERGROUND LINE FEEDING A TRANSFORMER VAULT

ALL CIVIL WORKS, i.e., CONCRETE-ENCASED PVC DUCTS & FITTINGS, TO BE PROVIDED AND INSTALLED BY THE APPLICANT/CUSTOMER TRANSFORMER VAULT TO BE CONSTRUCTED BY THE APPLICANT/CUSTOMER BASED ON MERALCO STANDARD SECONDARY CABLES TO CUSTOMER’S MAIN SECONDARY CIRCUIT BREAKER

slide-6
SLIDE 6

34.5 kV OH Line Vault Type DT's (SEE NOTE)

Single Line Diagram - 2 Banks w/ 4-Way Junction

Load Load Transformer Vault Elbow Arrester Lightning Arrester Fuse Cut-Out

  • r Power Fuse

4-Way Loadbreak Junction, 200A

PRIMARY SECONDARY

slide-7
SLIDE 7

4-WAY / 4-POINT JUNCTION

slide-8
SLIDE 8

Transformers for Vault Installation

 Three-phase, 34.5 GrdY/20 kV or 13.2 GrdY/7.62 kV  Available in either 240Y/139-V secondary (75-1000 kVA) or 480Y/277-V secondary (500-2000 kVA)  416Y/240 V secondary (500-1000 kVA) Meralco-Supplied Padmounted Transformers

slide-9
SLIDE 9

Transformers for Vault Installation

 Deadfront primary  Less flammable liquid filled  Completely self- protected with fuses  Provided with loop sectionalizing switch Meralco-Supplied Padmounted Transformers

slide-10
SLIDE 10

Transformers for Vault Installation

 Single-phase, 34.5 GrdY/20 kV or 13.2 GrdY/7.62 kV  Available in either 139/277-V secondary or 240/120-V secondary  Available in 167 – 333 kVA Meralco-Supplied Deadfront Distribution Transformer

slide-11
SLIDE 11

Transformers for Vault Installation

 Deadfront primary  Less flammable liquid filled  Provided with standard DT accessories  Round tank construction Meralco-Supplied Deadfront Distribution Transformer

slide-12
SLIDE 12

Standard Vault Location

slide-13
SLIDE 13

PREFERRED VAULT LOCATION:

  • PREFERRED VAULT LOCATION SHALL BE ON

THE GROUND FLOOR

  • SECOND FLOOR MAY BE ALLOWED (FOR VAULT

TYPE DT’s AND PADMOUNTED XF WITH HOISTING FACILITIES)

  • FIRST BASEMENT MAY BE ALLOWED FOR

BUILDINGS WITH MULTIPLE BASEMENT

slide-14
SLIDE 14
  • THE VAULT SHALL BE LOCATED ON PERIMETER OF

THE BUILDING

  • ADJACENT TO STREET/ROADWAY ACCESSIBLE TO

MERALCO TRUCKS AND CRANE TRUCK

MINIMUM ROAD WIDTH : 6.5 METERS

PREFERRED VAULT LOCATION:

slide-15
SLIDE 15

Standard Vault Specifications/Requirements

slide-16
SLIDE 16

STANDARD SPECIFICATION/ REQUIREMENTS:

  • WALLS AND ROOF SHALL BE MADE OF REINFORCED

CONCRETE NOT LESS THAN 150MM

  • THERE SHALL BE NO OPENING FROM THE VAULT TO ANY

PART OF THE BUILDING INTERIOR

  • 150 MM DOORSILL IS REQUIRED FOR LIQUID

CONFINEMENT

  • PROVISION FOR ADEQUATE AND PERMANENT

VENTILATION (EXHAUST FAN-TEMP CONTROLLED RATED ¾ HP, 71 CuM/Min (2500 CFM))

  • CLEAR HEADROOM SHALL NOT BE LESS THAN 4M FROM

THE BOTTOM OF THE I-BEAM TO MAINTAIN A 30°SLING ANGLE FROM THE VERTICAL (HOISTING FACILITY)

slide-17
SLIDE 17
  • DUCTS (PRIMARY AND SECONDARY) – 110 MM

DIAMETER, THICK WALLED, RED ORANGE COLOR, UNPLASTICIZED POLYVINYL CHLORIDE (UPVC) IN ACCORDANCE WITH PNS 14. IT SHOULD BE ENCASED IN CONCRETE

  • PROVISION OF PERSONNEL ACCESS DOORWAY

DIRECTLY ACCESSIBLE FROM OUTSIDE OF THE BUILDING

STANDARD SPECIFICATION/ REQUIREMENTS:

slide-18
SLIDE 18

Customer Vault Layouts for Transformers (pdt & vt)

slide-19
SLIDE 19

MINIMUM DIMENSION

PADMOUNT TRANSFORMER IN VAULT LOCATION 1-BANK 2-BANKS Ground Floor (W) 5m X (D) 4m X (H) 3m (W) 8m X (D) 4m X (H) 3m 2nd Floor (W) 5m X (D) 6m X (H) 4m* (W) 8m X (D) 6m X (H) 4m* 1st Basement (W) 5m X (D) 6m X (H) 3m (W) 8m X (D) 6m X (H) 3m

NOTES: [1] W = Width; D = Depth; H = Height (Headroom) EXCEPTION: For 2nd floor transformer vault with a hatchway, the depth requirement is 8m. *[2] 4m vertical distance measured from the bottom of the I-beam to the floor is required when hoisting the transformer

Requirements for Customer Vault

slide-20
SLIDE 20

MINIMUM DIMENSION

DEADFRONT (VAULT TYPE) DISTRIBUTION TRANSFORMERS

NOTE: W = Width; D = Depth; H = Height (Headroom)

LOCATION 1-BANK 2-BANKS Ground Floor (W) 5m X (D) 4m x (H) 3m (W) 6m X (D) 6m X (H) 3m 2nd Floor (W) 5m X (D) 4m x (H) 3m (W) 6m X (D) 6m X (H) 3m 1st Basement (W) 5m X (D) 4m x (H) 3m (W) 6m X (D) 6m X (H) 3m

Requirements for Customer Vault

slide-21
SLIDE 21

PRIMARY METERING

slide-22
SLIDE 22

SINGLE LINE DIAGRAM FOR PRIMARY METERING (OH)

slide-23
SLIDE 23

SINGLE LINE DIAGRAM FOR PRIMARY METERING (UG)

slide-24
SLIDE 24

TYPICAL PRIMARY METERING ARRANGEMENT

slide-25
SLIDE 25
slide-26
SLIDE 26

3 Way RMU with Metering Module

slide-27
SLIDE 27

3 Way RMU with Metering Module

slide-28
SLIDE 28

Thank you.