SLIDE 1
Vision One91
BURNSVILLE HIGH SCHOOL BOARD UPDATE MAY 28, 2015
Mark Hayes Mark Hovelson Eric Anderson Andy Hoffmann ATS&R Wenck
SLIDE 2 AGENDA
- Construction Phasing / Bid Packages
- Bid Package #1 – Scope
- Project Update
- Site
- West Classroom / Tech. Addition
- Activity Center Addition
- Science / Classroom Addition
- Preliminary Milestone Dates
Vision One91 – B.H.S.
SLIDE 3
Construction Phasing / Bid Packages
Bid Package Issue Bid Award #1– Annex Alts./ 4/30/15 5/21/15 5/28/15 Demo./ Site Utilities #2 - Precast Wall 5/15/15 6/4/15 6/11/15 Panels #3 - Footings / Conc. 7/1/15 7/28/15 8/13/15 / Steel / Conc. Blk. #4 - Finishes / Mech. 9/1/15 9/24/15 10/8/15 / Elec. / Tech.
SLIDE 4 Burnsville High School – Bid Package #1 Tech Lab
Classroom Construction Trades Auto Body Auto Shop
SLIDE 5
Burnsville High School – Bid Package #1 Tech Lab Elevation Existing Elevation
SLIDE 6 Construction Staging
Loss of 360 – 400 parking spaces during construction
SLIDE 7 Site Plan
Existing Site
SLIDE 8 Site Plan
PARKING
STAFF 250 STUDENT 637 VISITOR 14 BCTV 10 TOTAL 911 BUSES 31
11
245 402 111 26 101 8 18
SLIDE 9 Site Plan
WEST ADDITION
SLIDE 10 Site Plan
ACTIVITY CENTER
SLIDE 11 Site Plan
SCIENCE ADDITION
SLIDE 12 Burnsville High School – Project Scope
Mechanical
B.E.S.T. West Addition
- Classrooms
- Commons
- Tech Ed
- Staff Planning
- FTLA
Science Addition
Labs
Activities Addition
Classrooms
Lockers
- Athletic/ PE
- CNA Lab
- Pool Locker
Update Piano Lab
Storage
Storage
SLIDE 13
Burnsville High School – West Addition Main Level
SLIDE 14
Burnsville High School – West Addition Tech Ed House
SLIDE 15
Burnsville High School – West Addition Administration
SLIDE 16
Burnsville High School – West Addition Classroom/ FTLA
SLIDE 17
Burnsville High School – West Addition Upper Level
SLIDE 18
Burnsville High School – West Addition Lower Level
SLIDE 19
Burnsville High School – West Addition Perspective
SLIDE 20
Burnsville High School – West Addition Perspective
SLIDE 21
Burnsville High School – West Addition Perspective
SLIDE 22
Burnsville High School – Activities Addition Main Level
SLIDE 23
Burnsville High School – Activities Addition Upper Level
SLIDE 24
Burnsville High School – Activities Addition Perspective
SLIDE 25
Burnsville High School – Activities Addition Perspective
SLIDE 26
Burnsville High School – Science Addition Main Level
SLIDE 27
Burnsville High School – Science Addition Upper Level
SLIDE 28
Burnsville High School – Science Addition Perspective
SLIDE 29 Task Start Finish Bid Package #1 Mobilization 6/15/15 Site Demolition 6/20/15 8/21/15 Annex Renovations 6/20/15 10/23/15
- Reloc. of Underground Utilities
6/20/15 8/7/15
- Reloc. of Long Jump/Pole Vault
6/20/15 8/21/15 Precast Wall Panel Erection 12/15/15 1/15/16 Roofing 1/4/16 2/15/16 Building Enclosure 2/15/16 3/15/16 Rough Interior Work 1/15/16 5/15/16 Interior Finishes 3/1/16 8/18/16 Parking Lots/Site Improvements 6/1/16 8/18/16 Project Substantial Completion 8/19/16
Preliminary Milestone Dates