Meade Street Bridge Design Alternative Study Planning & Design Open Forum Stakeholder Meeting #1 January 10, 2011 Presented by: Dan Biggs, RLA Tonights Meeting Purpose: Schedule: Open House (part I) Introduce Project 1. 6:30


slide-1
SLIDE 1

Meade Street Bridge Design Alternative Study

Planning & Design Open Forum

Stakeholder Meeting #1

January 10, 2011

Presented by: Dan Biggs, RLA

slide-2
SLIDE 2

Tonight’s Meeting

Purpose:

1.

Introduce Project

2.

Review Goals & Objectives

  • f Study

3.

Listen, Learn and Share

4.

Next Steps for Feedback Schedule:

  • Open House (part I)

6:30 – 7:00

  • Introduction/ Presentation

7:00 – 7:30

  • Open House (part II)

7:30 – 9:00

slide-3
SLIDE 3

Toole Design Group

  • Locally based national planning & design firm
  • Specialty bicycle & pedestrian facilities
  • Federal, State, and Local Experience

– Bicycle & Pedestrian Planning – Multi-use Trail & Greenway Designs – Multi-modal Planning – Safe Route to Schools

Eastern Seaboard Plans:

  • Boston
  • Philadelphia
  • Pittsburgh
  • Baltimore
  • Washington
  • Richmond
  • Charleston
  • St. Louis

Seattle Denver Cincinnati Chicago Dallas San Antonio

slide-4
SLIDE 4

Project Goal & Objectives

  • Goal: to improve Bicycle and Pedestrian access and the user’s experience

along North Meade Street between Rosslyn and the Iwo Jima Memorial.

  • Objectives:

– Improving non-motorized access and user safety along corridor (RAFOM

#27, 27).

– Minimize vehicle and pedestrian conflict points (RAFOM #26). – Improve streetscape character of corridor (RAFOM #32, 42). – Improve bicycle, pedestrian, and motor vehicle wayfinding along corridor (RAFOM #26). – Maintain acceptable levels of service for all transportation modes

(Bicycle, Pedestrian, Motor Vehicles & Transit).

slide-5
SLIDE 5

What will come out of this Study?

This Study

  • Obtain Input from

Stakeholders

  • Review Existing Conditions
  • Develop three concept

design alternatives

  • Recommend One Design

Concept

  • Identify potential costs of

final design and construction Future Phases

  • Final Engineering Design
  • Final Construction
slide-6
SLIDE 6

Project Process

Information Gathering/ Field Review/ Preliminary Analysis Stakeholder Input #1 Concept Alternatives Development Stakeholder Input Session #2 Concept Alternatives Review / Selection Stakeholder Information Session #3 Final Concept Design

slide-7
SLIDE 7

Study Area

slide-8
SLIDE 8

Study Area

slide-9
SLIDE 9

Existing Conditions

slide-10
SLIDE 10

Opportunities & Constraints

slide-11
SLIDE 11
slide-12
SLIDE 12
slide-13
SLIDE 13

Walking Bicycling

slide-14
SLIDE 14

Complete Street Measures

slide-15
SLIDE 15

What Now? … and beyond

Schedule:

  • Open House (part I) 6:30 – 7:00
  • Intro/Presentation 7:00 – 7:30
  • Open House (part II) 7:30 – 9:00

“Comment on the Corridor” Upcoming:

  • Jan - Mar – Concept Design
  • Mar – Stakeholder Input Mtg #2
  • Apr – Preferred Concept

Presentation Mtg #3

  • May – Jun – Final Concept Design
slide-16
SLIDE 16

Thank you!

Daniel Biggs, RLA Toole Design Group, LLC DBiggs@tooledesign.com David Goodman, RA, AICP Arlington County Department of Environmental Services DGoodman@arlingtonva.us

We want to hear from you. Send Comments by February 10th

Next Meeting: March 2011 Project Website http://tinyurl.com/MeadeStreet

slide-17
SLIDE 17

Project Process / Schedule

Aug to Dec Jan Feb Mar Apr May Jun

Kickoff/ Existing Conditions Review Input Session #1 Input Session #2 Information Session #3 Preliminary Analysis Concept Alternatives Development

Preferred Concept Review

Final Concept Design

Project Complete

6.30.11