may 2015 1 project home and mpower roles in new market
play

May 2015 1 Project HOME and MPower Roles in New Market Tax Credit - PowerPoint PPT Presentation

Stephen Klein Wellness Center Philadelphia, PA May 2015 1 Project HOME and MPower Roles in New Market Tax Credit (NMTC) project MPower Owner (501c2) Project HOME Developer Leverage Lender Property Mgr


  1. Stephen Klein Wellness Center Philadelphia, PA May 2015 1

  2. Project HOME and MPower Roles in New Market Tax Credit (NMTC) project MPower • Owner (501c2) • Project HOME • Developer • Leverage Lender • Property Mgr • Tenants • Project HOME • YMCA • 2

  3. NMTC Structure 3

  4. Project Location Locus Map 4

  5. Neighborhood Overview  St. Elizabeth’s Center, with Jefferson Family Medicine, serving zip codes 19121/19132 for 18 yrs.  Patients served: 30% uninsured; 34% homeless or formerly homeless; 67% on medicaid or medicare.  Demographics show approximately 95% African American (compared with 41% citywide).  Nearly twice as likely to live in extreme poverty.  Unemployment rate twice city average.  Higher incidences of domestic violence, child neglect, and safety concerns. 5

  6. Wellness Center Overview Wellness Center: a dynamic place that integrates person-centered primary medical care, behavioral health care, physical fitness, nutrition education, rehabilitative services, pharmacy, dental care, case management, and peer-led health promotion. 6

  7. Federally Qualified Health Center (FQHC) Services  Primary Care (15 exam rooms)  Behavioral Health (4 consult rooms)  Dental (9 operatories)  Pharmacy  Fitness – YMCA  Physical Therapy  Healthy nutrition (teaching kitchen) 7

  8. Project Site / Location Neighborhood Plan 8

  9. Site Plan 9

  10. Design / Programming 10

  11. Project Budget 11

  12. Project Schedule DUE DILIGENCE/FEASIBILITY 105 days • Geotech/Environmental, Title & Survey, Civil Engineering. PREDEVELOPMENT 622 days • Site Control/Condemnation, Design, RCO & Community Meetings, Zoning. FINANCING 225 days • NMTC & RACP Applications, Closing CONSTRUCTION 371 days OVERALL PROJECT SCHEDULE - Start 1/7/13 thru Finish 12/22/15 714 days 12

  13. Pre-development Block was comprised of 48 individually addressed parcels. • Lot consolidation required. • Condemnation required. • 13

  14. Pre-development Existing land was underutilized, with a few • vacant, blighted buildings and one business that required relocation. Demolition and environmental remediation • required. 14

  15. Construction Earthwork Perimeter Footing 15

  16. Construction Steel Erection Slab Foundation 16

  17. Construction Roof Assembly Framing & Insulation 17

  18. Stephen Klein Wellness Center Interior Concourse/Lobby Main Entrance 18

  19. Wellness Center Pharmacy Living Room / Waiting Area 19

  20. YMCA YMCA Entrance YMCA Gym 20

  21. Project Impacts Business Utilization Goals Minority Business Enterprises 18% Women Business Enterprises 7% Employment Total # of Jobs created in 89 Philadelphia as a result of construction Total # of Jobs created in 295 PA as a result of construction Total # of Construction 102 Jobs created in PA 21

  22. NMTC Structure 22

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.