Mariposa Land Port of Entry Project Border Liaison Mechanism (BLM) - - PowerPoint PPT Presentation

mariposa land port of entry project
SMART_READER_LITE
LIVE PREVIEW

Mariposa Land Port of Entry Project Border Liaison Mechanism (BLM) - - PowerPoint PPT Presentation

Mariposa Land Port of Entry Project Border Liaison Mechanism (BLM) Meeting March 14, 2013 1 Mariposa Land Port of Entry Project Project Schedule and Progress 2 Mariposa Land Port of Entry, Nogales, Arizona Project Schedule Phase 2: September


slide-1
SLIDE 1

Mariposa Land Port of Entry Project

Border Liaison Mechanism (BLM) Meeting March 14, 2013

1

slide-2
SLIDE 2

Mariposa Land Port of Entry Project Project Schedule and Progress

2

slide-3
SLIDE 3

Phase 2: September 2010 – April 2012

  • 6 Northbound POV Primary Inspection Booths
  • Northbound POV Secondary Inspection Area
  • 8 Northbound Commercial Primary Inspection Booths
  • 5 Northbound Commercial Exit Control Booths

Mariposa Land Port of Entry, Nogales, Arizona Project Schedule

3

slide-4
SLIDE 4

6 Northbound POV Primary Inspection Booths

4

slide-5
SLIDE 5

Northbound POV Secondary Inspection Area

5

slide-6
SLIDE 6

8 Northbound Commercial Primary Inspection Booths

6

slide-7
SLIDE 7

5 Northbound Commercial Exit Control Booths

7

slide-8
SLIDE 8

Phase 3: May 2012 – November 2013

  • 6 Additional Northbound POV Primary Booths
  • Northbound POV Secondary Inspection Support Areas
  • Northbound Pedestrian Walkway and Processing Areas
  • Northbound Commercial Inspection Building and Docks (47)
  • 3 Outbound Primary Inspection Booths (2 POV & 1 Commercial)
  • Outbound POV Secondary Inspection Area
  • Outbound Bus Processing
  • Outbound Commercial Inspection Building and Docks (6)

Mariposa Land Port of Entry, Nogales, Arizona Project Schedule

8

slide-9
SLIDE 9

Phase 3

Mariposa Land Port of Entry Nogales, Arizona

9

slide-10
SLIDE 10

Mariposa Land Port of Entry Nogales, Arizona

Modified Outbound Inspection Facilities 5 Outbound Booths Total Equals: Phase 3 May 2012 – November 2013 2 POV Booths 1 POV / Commercial Booth Phase 4 December 2013 – August 2014 1 Commercial Booth 1 Oversized Commercial Booth 1 Pedestrian Booth

10

slide-11
SLIDE 11

Phase 4: December 2013 – August 2014

  • Removal of Temporary Facilities
  • 3 Additional Outbound Booths (2 Commercial & 1 Pedestrian)
  • Remainder of Northbound Commercial Inspection Building and Docks (9)
  • Miscellaneous Paving and Landscaping Throughout the Site

Mariposa Land Port of Entry, Nogales, Arizona Project Schedule

11

slide-12
SLIDE 12

Phase 4A

Mariposa Land Port of Entry Nogales, Arizona

12

slide-13
SLIDE 13

Phase 4B

Mariposa Land Port of Entry Nogales, Arizona

13

slide-14
SLIDE 14

Aerial Photo December 2011 – Phase 2 Under Construction

14

slide-15
SLIDE 15

Aerial Photo August 2012 – Phase 2 Complete & Phase 3 Under Construction

15

slide-16
SLIDE 16

Aerial Photo November 2012 – Phase 3 Under Construction

16

slide-17
SLIDE 17

Mariposa Land Port of Entry Project Final Build Out Configuration

17

slide-18
SLIDE 18
  • Phase 3 Build Out Configuration to Be Complete November 2013
  • 3 Northbound POV Lanes with 12 Inspection Booths
  • 8 Northbound Commercial Lanes with 8 Inspection Booths
  • Northbound Pedestrian Walkway between Northbound POV & Commercial Lanes
  • 2 Outbound POV & Commercial Lanes with 3 Inspection Booths (2POV & 1 Commercial)
  • Outbound Pedestrian Walkway West Side of Southbound Lanes
  • Phase 4 Build Out Configuration to Be Complete August 2014
  • 3 Additional Outbound Booths (2 Commercial & 1 Pedestrian)
  • Remainder of Northbound Commercial Inspection Building and Docks (9)
  • Schedule
  • November 2013 – Phase 3 Construction Complete & Operations will Start in New Areas
  • August 2014 – Phase 4 Construction will be Complete for Full Project Completion

Mariposa Land Port of Entry, Nogales, Arizona

18

slide-19
SLIDE 19
slide-20
SLIDE 20

Final Build Out at Phase 3 Completion November 2013

20

slide-21
SLIDE 21

Questions ?

Mariposa Land Port of Entry, Nogales, Arizona

21

slide-22
SLIDE 22

Thank You!

Jill Manzi, GSA Project Manager Tom Yearout, CBP Assistant Director Field Operations Mariposa Land Port of Entry, Nogales, Arizona

22