M R GANESAN CHIEF MANAGER/MECH NEYVELI LIGNITE CORPORATION LTD - - PowerPoint PPT Presentation

m r ganesan chief manager mech neyveli lignite
SMART_READER_LITE
LIVE PREVIEW

M R GANESAN CHIEF MANAGER/MECH NEYVELI LIGNITE CORPORATION LTD - - PowerPoint PPT Presentation

M R GANESAN CHIEF MANAGER/MECH NEYVELI LIGNITE CORPORATION LTD NEYVELI NEYVELI LIGNITE NEYVELI LIGNITE CORPORATION LTD, NEYVELI, CORPORATION LTD, NEYVELI, TAMIL NADU TAMIL NADU MINE I MINE I A MINE II MINE II EXPANSION


slide-1
SLIDE 1

M R GANESAN CHIEF MANAGER/MECH NEYVELI LIGNITE CORPORATION LTD NEYVELI

slide-2
SLIDE 2

NEYVELI LIGNITE NEYVELI LIGNITE CORPORATION LTD, NEYVELI, CORPORATION LTD, NEYVELI, TAMIL NADU TAMIL NADU

 MINE I  MINE I A  MINE II  MINE II EXPANSION

slide-3
SLIDE 3

NEYVELI LIGNITE NEYVELI LIGNITE CORPORATION LTD, CORPORATION LTD,

 Thermal Power Plant I 600 MW ( 6 X 50 MW + 3 x 100

MW)

 Thermal Power Plant I Expansion ( 2 x 210 MW)  Thermal Power Plant - II ( 7 x 210 MW)  Thermal Power Plant - II Expansion ( 2 x 250 MW)  Barsingsar Thermal Power Plant ( 2 x 125 MW)

slide-4
SLIDE 4

Ongoing Power Projects Ongoing Power Projects

 Tuticorin Thermal Power Project ( 2 x 500 MW) being

executed by NTPL - A Joint Venture of NLC and TNEB, Tamil Nadu – Under erection

slide-5
SLIDE 5

Ongoing Ongoing Power

Power Projects

Projects

 Neyveli New Thermal Power Project ( 2 x 500 MW),

Tamil Nadu Under finalisation of Contract.

slide-6
SLIDE 6

Proposed Power Projects Proposed Power Projects

 (3 x 660 MW) Super Critical Thermal Power Project

at Ghatampur in Uttar Pradesh

 (3 x 660 MW) Super Critical Thermal Power Project

at Sirkali in Tamil Nadu

slide-7
SLIDE 7

Needs of Air Handling systems in Needs of Air Handling systems in Power Plant Power Plant

 Unit control room, RCE room, UPS & rectifier rooms  Boiler Thyristor rooms  Static excitation rooms  Service building

slide-8
SLIDE 8

Package AC Package AC

 ESP control room  Switchyard control room  LHS control room

slide-9
SLIDE 9

Air washers Air washers

 TG hall

 Main Cable gallery  Main Switchgear room

slide-10
SLIDE 10

Supply air ventilation system Supply air ventilation system

 Major MCC rooms

Exhaust ventilation Exhaust ventilation

 All pump houses, plant buildings  Stores  Toilets

slide-11
SLIDE 11

HVAC system HVAC system

 Main Plant ( Steam Generator ) package  Main Plant ( Turbine Generator) package  BOP package.

slide-12
SLIDE 12

Ventilation S ystem Ventilation S ystem

 10 air changes per hour for washed air system  15 air changes per hour for fresh filtered air supply system  20 air changes for exhaust / general air exchange ventilation  Fresh filtered air supply system - fan & motor unit, dry panel

type air filter, air intake louvers, ducting, supply air grills, dampers, electrics, instrumentation & controls and multi louver gravity dampers.

slide-13
SLIDE 13

Ventilation S ystem Ventilation S ystem

 Exhaust ventilation system - fan & motor unit, out let

cowl with bird screen / back draft damper & ducting if any etc.

 Centrifugal fan - for fresh filtered air supply system.

However, axial flow (tube axial) fan for system capacity up to 5000 m3 /hr.

slide-14
SLIDE 14

Centrifugal Fan Centrifugal Fan

 The fan impeller shall be of backward curved blades.  The fan casing and blade shall not be less than 2.5

mm thick MS sheet.

slide-15
SLIDE 15

Centrifugal Fan Centrifugal Fan

 The shaft shall be of EN 8.  Variable inlet vane damper at the centrifugal fan

inlet.

 The fresh air intake louvers consists of parallel

metallic blades.

slide-16
SLIDE 16

Tube Axial Fan Tube Axial Fan

 Fan impeller - aerofoil section. The speed of the TA fan

preferably within 1000 rpm and outlet velocity within 12m/sec.

 The TA fan with Pre-filter - with rain protection Cowl & Bird

screen / wire mesh at the suction side of the TA fan for protection against physical & climatic encounters.

slide-17
SLIDE 17

Tube Axial Fan Tube Axial Fan

 Fan to be installed in fire hazardous/acid area

shall be spark proof construction and painted with acid resistant paint/anti corrosive lining.

 The impeller - cast aluminium alloy construction

  • f high efficiency aerofoil section blades.
slide-18
SLIDE 18

Tube Axial Fan Tube Axial Fan

 Axial flow fan casings for wall mounted/roof mounted

fans and their components shall be suitable for

  • utdoor installation. The casing shall be minimum 2

mm thick.

slide-19
SLIDE 19

Pre Pre-Filters Filters

 Dry panel type air filter shall be of high efficiency

cleanable type, constructed out of HDPE (6 ply) supported by layers of GI wire gauge.

 It shall be corrugated to the depth of filter casing in

  • rder to increase the ratio of filtration area to frontal

area.

slide-20
SLIDE 20

Pre Pre-Filters Filters

 It shall be covered by strong GI frame and have

space to ensure uniform distribution of air.

 Filtering panel shall be of standard size.  Face velocity of air shall not exceed 2 m/sec.

slide-21
SLIDE 21

Pre Pre-Filters Filters

 The resistance of air filter shall not exceed 10 mmWC

when dirty.

 Efficiency of the filter shall not be less than 90%

down to 10 microns.

 casing of not less than 3.15 mm thick M S sheet.

slide-22
SLIDE 22

Fire Damper Fire Damper

 The Fire damper shall be provided at out-let of the TA

Fan / Centrifugal Fan to isolate the served premises in case of fire occurrence.

 These shall be electrically operated & interlocked with

plant's fire protection system.

slide-23
SLIDE 23

Duct Duct

 The ducting

for ventilation and air conditioning systemsshall be fabricated from G.I. sheets.

 Guide vanes shall be provided in all large duct bends

for proper flow of air.

slide-24
SLIDE 24

Duct Duct

  • Large side of rectangular

Duct/diameter of Circular Thickness (mm) duct (mm)

  •  0 - 800

1.0

 801 - 1500

1.25

 1501 and above

1.6

slide-25
SLIDE 25

Duct Duct

 The joints & bracings for ventilation & air conditioning

systems - as per IS: 655.

 All flanged joints - with asbestos rope of dia. 5 mm for

proper sealing of the joints.

slide-26
SLIDE 26

Duct Duct

 Turning guide vanes shall be provided inside the

duct wherever change

  • f

direction

  • ccurs,

to minimise eddy formation.

 Duct work shall be complete with flanges, stiffeners,

fasteners, hangers, nuts, bolts, washer & gaskets etc.

slide-27
SLIDE 27

Supply Air Grilles / Diffusers Supply Air Grilles / Diffusers

 G.I.

sheets not less than duct thickness for the manufacture of grills.

 No distortion or warping is permitted.

slide-28
SLIDE 28

Availability Availability

 The equipment selected shall be new and best of its

type available with respect to material and workmanship considering the continuous and reliable operation.

 The equipment shall be maintenance free as far as

practicable.

 The spares shall be easily available.

slide-29
SLIDE 29

Availability Availability

 All materials used shall be free from surface defects,

rust, cracks and deformations.

 The finish of the equipment and its components shall

be of first class quality.

slide-30
SLIDE 30

Availability Availability

 The components and equipment shall be so selected

that the system down time is kept minimum. S ystem design shall be such that fast and easy replacement of componentscould bepossiblewherever necessary.

 To the extent possible models and sizes of equipment

shall be identical to ensure minimum inventory and interchangeability of parts, equipment and systems

slide-31
SLIDE 31

Performance of Air handling Performance of Air handling system in Power plants. system in Power plants.

 No major problems noticed.  Water

quality was a issue. Hence DM water was used for chilled water.

 Fine ash accumulation in Cooling coil fins

slide-32
SLIDE 32

Issues in Project Procurement Issues in Project Procurement

 Earlier, tenders were floated packages wise.  Now, 3 package system like SG, TG & BOP has been

followed

 Major deviations are taken by the contractors after

award of contract.

slide-33
SLIDE 33

Plant procurement Plant procurement

 Online registration with the Material Management

department.

 Limited tender enquiry  Press tender enquiry

slide-34
SLIDE 34

Sub vendors Sub vendors

 For major system like water treatment, CW system,

Fire protection system etc, a brief Qualifying requirements is included in the tender specification for BOP package. Accordingly sub venodrs for these system will be selected after award of contract of the BOP package.

slide-35
SLIDE 35

Expectations from Manufacturers Expectations from Manufacturers

 Compliance to the specification and avoid deviations.  equipments running with natural energy  Wind turbine ventilators.

slide-36
SLIDE 36

Thank Y

  • u

Thank you